High CourtsDivision Bench(2018) 05 SHI CK 0065

Adarsh Food Products (P) Ltd. vs State of Himachal Pradesh and anothers.

High Court Of Himachal Pradesh · Decided on 3 May 2018

HON’BLE JUDGES
TARLOK SINGH CHAUHAN, CHANDER BHUSAN BAROWALIA
RESULT
Partly Allowed
CASE NUMBER
CWP No. 1198 of 2017

AI Structured Summary

Not yet generated for this judgment

Judgment

447 paragraphs · 10,525 words

Tarlok Singh Chauhan, J.

1.Aggrieved by forfeiture of its earnest money of `25,00,000/-, the petitioner has filed this writ petition claiming therein the following substantive reliefs:

“(a) That a writ in the form of Certiorari may be issued against the respondent.

(b) That Annexure P-8 may be quashed and set-aside, being illegal and arbitrary and against the established principles of natural justice and fair play.

(c) That the respondents may be directed not to forfeit the earnest money deposited and also not to blacklist the petitioner and allow it to carry on its

business legally.â€​

2.

Brief facts leading to filing of the present writ petition are that respondent No.2 invited global tenders for the procurement of assorted pulses

namely (i) Malka (Red Lentil); (ii) Urd Sabut; (iii) Moong Sabut and (iv) Dal Channa. The last date for submission of online tender alongwith Earnest

Money Deposit (for short EMD), tender document fee and processing fee was 15.3.2017 upto 5.00 p.m. and the tenders in question was to be opened

on 16.3.2017 at 11.00 AM. The petitioner accordingly submitted his tender for Dal Chana on 11.3.2017 after completing all the formalities including

the deposit of EMD. According to the petitioner, the bids were not opened on the stipulated date and time and in the meanwhile due to abnormal

change in the market condition, the petitioner was forced to withdraw his bid vide its letter dated 30.3.2017 wherein the petitioner also requested the

respondent-Corporation to refund the EMD of ` 25 lacs. However, before the said letter could reach the respondents, the respondent No.2 vide letter

dated 31.3.2017 asked the petitioner to submit revised lower rates of pulses within two days, whereas according to the petitioner he had already

withdrawn from the bid on 30.3.2017.

3.

The respondents vide their letter dated 13.4.2017 directed the petitioner to submit the samples of Dal Chana contained in 25 KG bag for lab testing.

The petitioner vide its reply dated 15.4.2017 again reiterated and informed the respondent No.2 that it had already withdrawn its bid vide letter dated

30.3.2017 and, therefore, there was no occasion left for the petitioner to submit the samples for testing and its earlier request to refund the EMD was

also reiterated. However, instead of refunding the EMD, the respondent No.2 by citing condition No.2(2) of the tender document, sent a letter dated

17.4.2017 to the petitioner whereby it threatened the petitioner-firm of adverse action in case the sample was not submitted by the petitioner within

two days. In the letter it was mentioned that the State Government had already approved the rate submitted by the petitioner for supplying of Dal

Chana, but the petitioner would claim that no intimation in regard to the same had earlier been communicated to him and the fact that its bid has been

accepted, was only came to his knowledge vide the aforesaid letter. The petitioner sent its reply dated 19.4.2017 whereby it drew the attention of

respondent No. 2 that the reliance being placed by respondent No.2 on the condition No.2(2) of the tender document was not correct. However,

instead of refunding the petitioner’s EMD, respondent No.2 sent it a show cause notice dated 3.5.2017 whereby the petitioner has been asked to

show cause as to why its earnest money deposited be not forfeited and why the petitioner should not be black listed from participating in further

tenders issued by the respondent No.2-Corporation.

4.

The petitioner submitted the reply dated 12.5.2017 reiterating therein that respondent No.2 was liable to refund EMD of the petitioner as it had

already withdrawn from the tender vide letter dated 30.3.2017. However, when no action was taken, the petitioner was compelled to approach this

Court by filing the instant writ petition for the reliefs as already set out above.

5.

The respondent No.2, who otherwise only is the contesting party, has filed its reply wherein number of preliminary submissions/objections have

been raised. It is averred that in 2007, the Government of Himachal Pradesh introduced the State Special Subsidized Scheme under which it was

decided to distribute pulses, edible oil and salt to the ration card holders of the State at subsidized prices. For this purpose, a State Level Purchase

Committee (for short ‘SLPC’) was constituted by the Government for calling and finalizing the tenders. The respondent No.2 was nominated as

the nodal agency for implementation of the said scheme under which the tenders are invited under the guidance of the SLPC and are opened and

processed by the said Committee. Thereafter, recommendations of the SLPC were sent to the Government for finalizing the tenders and fixing the

rates of the items to be distributed. The State Government in turn after considering the burden of subsidy involved, fixed the price of the articles to be

distributed under this Scheme, finalized the tenders and accorded its approval.

6.

As regards the instant case, the respondent No.2 had called for global e-tender under the State Special Subsidized Scheme for the procurement of

four numbers pulses namely (i) Malka Dal (ii) Urd Sabut (iii) Moong Sabut and (iv) Dal Chana to be supplied for a period of three months from

March, 2017 to May, 2017. The date of opening of the tender document was fixed on 16.3.2017. The SLPC constituted by the State Government

opened the tenders on 16.3.2017 and the petitioner was declared as the lowest bidder (L-1) for Dal Chana. Thereafter the proceedings of the SLPC

were sent to the Government of H.P. through letter dated 20.3.2017 for its approval and consideration. The State Government, in turn, vide its letter

dated 29.3.2017 addressed to the Corporation directed that the revised lower rates from all the successful bidders may be obtained and sent to the

Government for consideration, In the meanwhile, the petitioner informed the respondent through letter dated 30.3.2017 regarding the withdrawal of its

bid for the aforesaid commodity i.e. Dal Chana. The letter of response of the bidders in reference to the directions of the State Government was sent

for the Government for consideration on 3.4.2017. The State Government vide its letter dated 12.4.2017 accorded its approval to the recommendation

made by the SLPC dated 16.3.2017 and after approval thereof, the petitioner was directed to submit the sample of Dal Chana as per the terms and

conditions of the tender document on 13.4.2017. However, the petitioner vide letter dated 15.4.2017 informed that he had already withdrawn its bid on

30.3.2017 and, therefore, its EMD worth `25 lacs may be refunded. Thereafter, the petitioner was again requested by respondent No.2 to submit the

sample for Dal Chana vide letter dated 17.4.2017 because as per the terms and conditions of the tender document, the petitioner was not allowed to

withdraw its bid when it had already been opened in the presence of the other parties on 16.3.2017. The matter of the petitioner was thereafter

referred to the SLPC, who recommended that a show cause notice be issued to the petitioner and a short terms e-tender be invited for the

procurement of Dal Chana immediately. After the receipt of the recommendation of the SLPC, a show cause notice dated 3.5.2017 was issued to the

petitioner and the matter of the petitioner alongwith the reply was again placed before the SLPC in its meeting held on 30.5.2017. The SLPC

recommended that since the petitioner had violated the terms and conditions of the tender document, therefore EMD of `25 lacs may be forfeited,

besides blacklisting of the bidder as per Clause 2 (2) of the tender document. The averments made in the preliminary objections have been reiterated

in the meanwhile, therefore, we need not to advert to the same.

7.

The petitioner has filed the rejoinder to the reply of respondent No.2, wherein its stand in the writ petition has been reiterated and the contrary

averments made in the reply have been denied.

8.

It is vehemently argued by Mr. Atul Jhingan, learned counsel for the petitioner that the respondent No.2 being a public authority was bound to act in

a bonafide manner and in good faith and even otherwise it was bound to comply with the provisions of Section 74 of the Contract Act and having

failed to do so, its action intended to forfeit the EMD and also blacklisted the petitioner as per the terms of show cause notice dated 3.5.2017 cannot

withstand judicial scrutiny and therefore, the said notice deserves to be quashed and set-aside and the respondent deserves to be directed to refund the

EMD to the petitioner and also ensure that it is not blacklisted.

9.

On the other hand Mr. Navlesh Verma, learned counsel for respondent No.2 would vehemently contend that the petitioner having participated in the

tender process is bound by all the terms and conditions thereof and can take no exception since the action of the respondent is strictly in accordance

with law and as the conditions as stipulated in the tender form. We have heard learned counsel for the parties and have gone through the records of

the case carefully.

10.

The condition No.2 of the tender relates to Earnest Money Deposit (EMD) and Performance Security Deposit and reads thus: “1. Every bid

should be accompanied with documentary proof in token of having deposited the Earnest Money amounting to Rs.25,00,000/- (Rupees Twenty five

lacs only) in respect of each pulse subject to a maximum of Rs. 75,00,000/- (Rupees Seventy Five Lacs only) in case a bidder bids for three or more

pulses, through RTGs in Corporation’s Current Account No.10836143047 of State Bank of India Branch at Shimla IFS Code No. SBIN0000718)

failing which the bid shall be out-rightly rejected. The successful tenderer shall have to deposit a Performance Security equal to Five percent (5%) of

the cost of approved Pulse in the form of account payee demand draft or duly pledged fixed deposit receipt or bank guarantee from any scheduled

bank with the HP State Civil Supplies Corporation in the shape of Performance Security within a week from the issue of supply order. The Earnest

Money of successful bidder shall also be returned immediately after the submission of 5% Performance Security. No interest shall be payable on such

security. The Performance Security shall remain valid for a period of 60 days from the date of completion of the contract including warranty and

guarantee period to the best of satisfaction of the Corporation. The Earnest Money of the unsuccessful bidder will be returned through RTGs within

15 days after finalization of the tender. 2. EMD is liable to be forfeited in case the tenderer withdraws his offer after filing the tender or after the

acceptance of the offer by the HPSCSC Ltd. or fails to deposit the performance security deposit within the specified time, apart from blacklisting the

tenderer.â€​

11.A perusal of the aforesaid condition, would clearly go to show that an amount of `25,00,000/- was towards the Earnest Money and in terms of

condition No. 2 (2), this amount was liable to be forfeited in case the tenderer:

(i) Withdraws his offer after filing the tender or ;

(ii) After the acceptance of the offer by the HPSCSC Ltd; or

(iii) fails to deposit the performance security deposit within the specified time, in addition thereof, it was also liable to be blacklisted.

12.

Section 74 of the Indian Contract Act, which have been heavily relied upon by the petitioner reads thus: “74. Compensation for breach of

contract where penalty stipulated for:- 34 [When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of

such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual

damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding

the amount so named or, as the case may be, the penalty stipulated for. Explanation.â€" A stipulation for increased interest from the date of default

may be a stipulation by way of penalty.] (Exception) â€" When any person enters into any bail-bond, recognizance or other instrument of the same

nature or, under the provisions of any law, or under the orders of the 35 [Central Government] or of any 36 [State Government], gives any bond for

the performance of any public duty or act in which the public are interested, he shall be liable, upon breach of the condition of any such instrument, to

pay the whole sum mentioned therein. Explanation.â€" A person who enters into a contract with Government does not necessarily thereby undertake

any public duty, or promise to do an act in which the public are interested.â€​

13.

Relying upon the aforesaid provision, it is vehemently contended by Mr. Atul Jhingan, learned counsel for the petitioner that the respondent at best

could have forfeited a reasonable amount paid towards the Earnest Money but could not have forfeited the said amount in its entirety as that would

amount to imposing a penalty which is not permissible under Section 74 (supra).

14.

In support of his contention, he has placed reliance upon the decision of three Judges of the Hon’ble Supreme Court in Maula Bux vs. Union

of India 1969 (2) SCC 554, more particularly, the following observations: “4. Under the terms of the agreements the amounts deposited by the

plaintiff as security for due performance of the contracts were to stand forfeited in case the plaintiff neglected to perform his part of the contract. The

High Court observed that the deposits so made may be regarded as earnest money. But that view cannot be accepted. According to Earl Jowitt in

The Dictionary of English Law"" at p. 689: ""Giving an earnest or earnest-money is a mode of signifying assent to a contract of sale or the like, by

giving to the vendor a nominal sum (e.g. a shilling) as a token that the parties are in earnest or have made up their minds."" As observed by the Judicial

Committee in Kunwar Chiranjit Singh v. Har Swarup, AIR (1926) PC 1: ""Earnest money is part of the purchase price when the transaction goes

forward: it is forfeited when the transaction falls through, by reason of the fault or failure of the vandee."" In the present case the deposit was made

not of a sum of money by the purchaser to be applied towards part payment of the price when the contract was completed and till then as evidencing

an intention on the part of the purchaser to buy property or goods. Here the plaintiff had deposited the amounts claimed as security for guaranteeing

due performance of the contracts. Such deposits cannot be regarded as earnest money. Section 74 of the Contract Act provides: ""When a contract

has been broken, if a sum is named in the contract as the amount to be paid in case (1) A.I.R. 1926 P.C. 1 of such breach, or if the contract contains

any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been

caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case

may be, the penalty stipulated for. There is authority, no doubt coloured by the view which was taken in English cases, that s. 74 of the Contract Act

has no application to cases of deposit for due performance of a contract which is stipulated to be forfeited for breach: Natesa Aiyar v. Appavu

Padayachi (1913) ILR 38 Mad 178; Singer Manufacturing Company v. Raja Prosad(1909) ILR 36 Cal 960; Manian Patter v. The Madras Railway

Company (1906) ILR 19 Mad 188. But this view is no longer good law in view of the judgment of this Court in Fateh Chand's case (supra). This Court

observed at p. 526: ""Section 74 of the Indian Contract Act deals with the measure of damages in two classes of cases (i) where the contract names a

sum to be paid in case of breach, and (ii) where the contract contains any other stipulation by way of penalty…….â€. “The measure of damages

in the case of breach of 'a stipulation by way of penalty is by Section 74, reasonable compensation no t exceeding the penalty stipulated for."" The

Court also observed: ""It was urged that the section deals in terms with the right to receive from the party who has broken the contract reasonable

compensation and not the right to forfeit what has already been received by the party aggrieved. There is however no warrant for the assumption

made by some of the High Courts in India, that Section 74, applies only to cases where the aggrieved party is seeking to receive some amount on

breach of contract and not to cases whereupon breach of contract an amount received under the contract is sought to be forfeited. In our judgment

the expression ""the contract contains any other stipulation by way of penalty"" comprehensively applies to every covenant involving a penalty whether it

is for payment on breach of contract of money or delivery of property in future, or for forfeiture of right to money or other property already delivered.

Duty not to enforce the penalty clause but only to award reasonable compensation is statutorily imposed upon courts by Section 74. In all cases,.

therefore, where there is a stipulation in the nature of penalty for forfeiture of an amount deposited pursuant to the terms of contract which expressly

provides for forfeiture, the court has jurisdiction to award such sum only as it considers reasonable but not exceeding the amount specified in the

contract as liable to. forfeiture."", and that, ""There is no. ground for holding that the expression ""contract contains any other stipulation by way of

penalty"" is limited to cases of stipulation in the nature of an agreement to. pay money or deliver property on breach and does not comprehend

covenants under which amounts paid or property delivered under the contract, which by the terms of the contract expressly or by clear implication are

liable to be forfeited."" 5. Forfeiture of earnest money under a contract for sale of property-movable or immovable--if the amount is reasonable, does

not fall within s. 74. That has been decided in several cases: Kunwar Chiranjit Singh v. Hat Swarup (t); Roshan Lal v. The Delhi Cloth and General

Mills Company Ltd., Delhi(2); Muhammad Habibullah v. Muhammad Shafi(3); Bishan Chand v. Radha Kishan Das(4); These cases are easily

explained, for forfeiture of a reasonable amount paid as earnest money does not amount to. imposing a penalty. But if forfeiture is of the nature of

penalty, s. 74 applies. Where under the terms of the contract the party in breach has undertaken to pay a sum of money or to forfeit a sum of money

which he has already paid to the party complaining of a breach of contract, the undertaking is of the nature of a penalty.â€​

15.

Reliance is further placed upon the judgment of the Hon’ble Supreme Court in Saurabh Prakash vs. DLF Universal Ltd. (2007) 1 SCC 228

and Yogesh Mehta vs. Custodian Appointed under the Special Court and others (2007) 2 SCC 624, wherein the ratio laid down in (1969) Maula Bux

(supra) has been reiterated.

16.

We have gone through the aforesaid decisions of the Hon’ble Supreme Court in Maula Bux case (supra) and find that the ratio laid down

therein is not at all applicable to the facts of the present case for the simple reason that the said case did not relate to earnest money and, therefore,

the observations made therein that the forfeiture of earnest money under a contract if unreasonable does not fall within Section 74 and would fall

within Section 74 only if earnest money is considered as a penalty is not a matter that directly arose for decision in that case. This was so held by the

Hon’ble Supreme Court in Kailash Nath Associates vs. Delhi Development Authority and another (2015) 4 SCC 136 and it is apt to reproduce the

relevant observations which read thus: “35. Similarly, in Maula Bux v. Union of India (UOI), 1970 (1) SCR 928, it was held: ""35. Forfeiture of

earnest money under a contract for sale of property- movable or immovable-if the amount is reasonable, does not fall within Section 74. That has been

decided in several cases :Kunwar Chiranjit Singh v. Har Swarup, A.I.R.1926 P.C.1; Roshan Lal v. The Delhi Cloth and General Mills Company Ltd.,

Delhi, I.L.R. All.166; Muhammad Habibullah v. Muhammad Shafi, I.L.R. All. 324; Bishan Chand v. Radha Kishan Das, I.D. 19 All. 49. These cases

are easily explained, for forfeiture of a reasonable amount paid as earnest money does not amount to imposing a penalty. But if forfeiture is of the

nature of penalty, Section 74 applies. Where under the terms of the contract the party in breach has undertaken to pay a sum of money or to forfeit a

sum of money which he has already paid to the party complaining of a breach of contract, the undertaking is of the nature of a penalty. Counsel for

the Union, however, urged that in the present case Rs. 10,000/- in respect of the potato contract and Rs. 8,500 in respect of the poultry contract were

genuine pre-estimates of damages which the Union was likely to suffer as a result of breach of contract, and the plaintiff was not entitled to any relief

against forfeiture. Reliance in support of this contention was placed upon the expression (used in Section 74 of the Contract Act), ""the party

complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has

broken the contract reasonable compensation"". It is true that in every case of breach of contract the person aggrieved by the breach is not required to

prove actual loss or damage suffered by him before he can claim a decree, and the Court is competent to award reasonable compensation in case of

breach even if no actual damage is proved to have been suffered in consequence of the breach of contract. But the expression ""whether or not actual

damage or loss is proved to have been caused thereby"" is intended to cover different classes of contracts which come before the Courts. In case of

breach of some contracts it may be impossible for the Court to assess compensation arising from breach, while in other cases compensation can be

calculated in accordance with established rules. Where the Court is unable to assess the compensation, the sum named by the parties if it be regarded

as a genuine pre-estimate may be taken into consideration as the measure of reasonable compensation, but not if the sum named is in the nature of a

penalty. Where loss in terms of money can be determined, the party claiming compensation must prove the loss suffered by him. In the present case, it

was possible for the Government of India to lead evidence to prove the rates at which potatoes, poultry, eggs and fish were purchased by them when

the plaintiff failed to deliver ""regularly and fully"" the quantities stipulated under the terms of the contracts and after the contracts were terminated.

They could have proved the rates at which they had to be purchased and also the other incidental charges incurred by them in procuring the goods

contracted for. But no such attempt was made.

36.

In Shree Hanuman Cotton Mills and Anr. v. Tata Aircraft Limited, (1969) 3 SC 522 it was held:""From a review of the decisions cited above, the

following principles emerge regarding ""earnest"":

(1) It must be given at the moment at which the contract is concluded.

(2) It represents a guarantee that the contract will be fulfilled or, in other words, 'earnest' is given to bind the contract.

(3) It is part of the purchase price when the transaction is carried out.

(4) It is forfeited when the transaction falls through by reason of the default or failure of the purchaser.

(5) Unless there is anything to the contrary in the terms of the contract, on default committed by the buyer, the seller is entitled to forfeit the earnest.

The learned Attorney General very strongly urged that the pleas covered by the second contention of the appellant had never been raised in the

pleadings nor in the contentions urged before the High Court. The question of the quantum of earnest deposit which was forfeited being unreasonable

or the forfeiture being by way of penalty, were never raised by the appellants. The Attorney General also pointed out that as noted by the High Court

the appellants led no evidence at all and, after abandoning the various pleas taken in the plaint, the only question pressed before the High Court was

that the deposit was not by way of earnest and hence the amount could not be forfeited. Unless the appellants had pleaded and established that there

was unreasonableness attached to the amount required to be deposited under the contract or that the clause regarding forfeiture amounted to a

stipulation by way of a penalty, the respondents had no opportunity to satisfy the Court that no question of unreasonableness or the stipulation being by

way of penalty arises. He further urged that the question of unreasonableness or otherwise regarding earnest money does not at all arise when it is

forfeited according to the terms of the contract. In our opinion the learned Attorney General is well founded in his contention that the appellants raised

no such contentions covered by the second point, noted above. It is therefore unnecessary for us to go into the question as to whether the amount

deposited by the appellants, in this case, by way of earnest and forfeited as such, can be considered to be reasonable or not. We express no opinion on

the question as to whether the element of unreasonableness can ever be considered regarding the forfeiture of an amount deposited by way of earnest

and if so what are the necessary factors to be taken into account in considering the reasonableness or otherwise of the amount deposited by way of

earnest. If the appellants were contesting the claim on any such grounds, they should have laid the foundation for the same by raising appropriate

pleas and also led proper evidence regarding the same, so that the respondents would have had an opportunity of meeting such a claim.

37.

And finally in ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, it was held: (SCC Pp 740-43, paras 64 & 67-68) ""64. It is apparent from the

aforesaid reasoning recorded by the Arbitral Tribunal that it failed to consider Sections 73 and 74 of the Indian Contract Act and the ratio laid down in

Fateh Chand case [AIR 1963 SC 140: (1964) 1 SCR 515 at p. 526] wherein it is specifically held that jurisdiction of the court to award compensation

in case of breach of contract is unqualified except as to the maximum stipulated; and compensation has to be reasonable. Under Section 73, when a

contract has been broken, the party who suffers by such breach is entitled to receive compensation for any loss caused to him which the parties knew

when they made the contract to be likely to result from the breach of it. This section is to be read with Section 74, which deals with penalty stipulated

in the contract, inter alia (relevant for the present case) provides that when a contract has been broken, if a sum is named in the contract as the

amount to be paid in case of such breach, the party complaining of breach is entitled, whether or not actual loss is proved to have been caused,

thereby to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named. Section 74 emphasizes

that in case of breach of contract, the party complaining of the breach is entitled to receive reasonable compensation whether or not actual loss is

proved to have been caused by such breach. Therefore, the emphasis is on reasonable compensation. If the compensation named in the contract is by

way of penalty, consideration would be different and the party is only entitled to reasonable compensation for the loss suffered. But if the

compensation named in the contract for such breach is genuine pre-estimate of loss which the parties knew when they made the contract to be likely

to result from the breach of it, there is no question of proving such loss or such party is not required to lead evidence to prove actual loss suffered by

him. … 67........In our view, in such a contract, it would be difficult to prove exact loss or damage which the parties suffer because of the breach

thereof. In such a situation, if the parties have pre-estimated such loss after clear understanding, it would be totally unjustified to arrive at the

conclusion that the party who has committed breach of the contract is not liable to pay compensation. It would be against the specific provisions of

Sections 73 and 74 of the Indian Contract Act. There was nothing on record that compensation contemplated by the parties was in any way

unreasonable. It has been specifically mentioned that it was an agreed genuine pre-estimate of damages duly agreed by the parties. It was also

mentioned that the liquidated damages are not by way of penalty. It was also provided in the contract that such damages are to be recovered by the

purchaser from the bills for payment of the cost of material submitted by the contractor. No evidence is led by the claimant to establish that the

stipulated condition was by way of penalty or the compensation contemplated was, in any way, unreasonable. There was no reason for the Tribunal

not to rely upon the clear and unambiguous terms of agreement stipulating pre-estimate damages because of delay in supply of goods. Further, while

extending the time for delivery of the goods, the respondent was informed that it would be required to pay stipulated damages.

68.

From the aforesaid discussions, it can be held that:

(1) Terms of the contract are required to be taken into consideration before arriving at the conclusion whether the party claiming damages is entitled

to the same.

(2) If the terms are clear and unambiguous stipulating the liquidated damages in case of the breach of the contract unless it is held that such estimate

of damages/compensation is unreasonable or is by way of penalty, party who has committed the breach is required to pay such compensation and that

is what is provided in Section 73 of the Contract Act.

(3) Section 74 is to be read along with Section 73 and, therefore, in every case of breach of contract, the person aggrieved by the breach is not

required to prove actual loss or damage suffered by him before he can claim a decree. The court is competent to award reasonable compensation in

case of breach even if no actual damage is proved to have been suffered in consequence of the breach of a contract.

(4) In some contracts, it would be impossible for the court to assess the compensation arising from breach and if the compensation contemplated is not

by way of penalty or unreasonable, the court can award the same if it is genuine pre-estimate by the parties as the measure of reasonable

compensation.

38.

It will be seen that when it comes to forfeiture of earnest money, in Fateh Chand's case, counsel for the appellant conceded on facts that

Rs.1,000/-deposited as earnest money could be forfeited. (See: 1964 (1) SCR Page 515 at 525 and 531).

39.

Shree Hanuman Cotton Mills & Another which was so heavily relied by the Division Bench again was a case where the appellants conceded that

they committed breach of contract. Further, the respondents also pleaded that the appellants had to pay them a sum of Rs.42,499/- for loss and

damage sustained by them. (See: 1970 (3) SCR 127 at Page 132). This being the fact situation, only two questions were argued before the Supreme

Court: (1) that the amount paid by the plaintiff is not earnest money and (2) that forfeiture of earnest money can be legal only if the amount is

considered reasonable. (at page 133). Both questions were answered against the appellant. In deciding question two against the appellant, this Court

held:- ""But, as we have already mentioned, we do not propose to go into those aspects in the case on hand. As mentioned earlier, the appellants never

raised any contention that the forfeiture of the amount amounted to a penalty or that the amount forfeited is so large that the forfeiture is bad in law.

Nor have they raised any contention that the amount of deposit is so unreasonable and therefore forfeiture of the entire amount is not justified. The

decision in Maula Bux's [1970]1SCR928 had no occasion to consider the question of reasonableness or otherwise of the earnest deposit being

forfeited. Because, from the said judgment it is clear that this Court did not agree with the view of the High Court that the deposits made, and which

were under consideration, were paid as earnest money. It is under those circumstances that this Court proceeded to consider the applicability of

Section 74 of the Contract Act.

40.

From the above, it is clear that this Court held that Maula Bux's case was not, on facts, a case that related to earnest money. Consequently, the

observation in Maula Bux that forfeiture of earnest money under a contract if reasonable does not fall within Section 74, and would fall within Section

74 only if earnest money is considered a penalty is not on a matter that directly arose for decision in that case. The law laid down by a Bench of 5

Judges in Fateh Chand's case is that all stipulations naming amounts to be paid in case of breach would be covered by Section 74. This is because

Section 74 cuts across the rules of the English Common Law by enacting a uniform principle that would apply to all amounts to be paid in case of

breach, whether they are in the nature of penalty or otherwise. It must not be forgotten that as has been stated above, forfeiture of earnest money on

the facts in Fateh Chand's case was conceded. In the circumstances, it would therefore be correct to say that as earnest money is an amount to be

paid in case of breach of contract and named in the contract as such, it would necessarily be covered by Section 74.â€​

17.

At this stage, it needs to be observed that the instant is not a simple case of tender, but it relates to procurement of pulses under the State Special

Subsidized Scheme, which in turn, thereafter are distributed under the Public Distribution System (PDS) to the Below Poverty Line (BPL), Antodaya

families apart from others. Therefore, it is of utmost importance that there is timely supply of the pulses in terms of the tender or else, there will be no

pulses for distribution under the Public Distribution System more especially the far flung and tribal areas of the State. Now, in case there is absence of

any term stipulating forfeiture of the earnest money that may lead to situations where even those who do not have the capacity or intention of entering

into a contract venture into the bidding process for at times extraneous reasons. The purpose of such a clause providing for forfeiture of the earnest

money was clearly to see that only genuine bids are received.

18.

As a matter of fact, somewhat identical issue, as is involved in the present case, came up before three Judges Bench of the Hon’ble Supreme

Court in National Thermal Power Corporation Limited vs. Ashok Kumar Singh and others (2015) 4 SCC 252, wherein it was held that the forfeiture of

earnest money when it is made for breach of auction/tender condition a pre-contractual stage when no contract has yet come into existence, does not

infringe any statutory right under the Contract Act, 1872 since the earnest/ security is given and taken in such cases only to ensure that a contract

comes into existence. It was further held that even though the tenderer has a right to withdraw his offer, but he will have no right to claim refund of

earnest money if such offer is subjected to the condition that earnest money will be forfeited, if the order is withdrawn. It is apt to reproduce the

relevant observations as contained in paras 6 to 13 which read thus:“6. Condition No. 2 of Special Conditions of Contract may be extracted. It

reads: ""2. The earnest money shall be forfeited on the following grounds:

(a) On revocation of the tender or,

(b) On refusal to enter into a Contract afterward to a Contractor or,

(c) If the work is not commenced after the work is awarded to a Contractor."" A plain reading of the above would show that one of the Special

Conditions of Contract, subject to which the intending bidders could submit their bids, was that the earnest money accompanying the bid shall be

forfeited in any one of the three contingencies referred to in Condition No. 2 (supra). One of these contingencies was revocation of the tender, which

would in the context in which the special provision is made imply any withdrawal of the bid/tender by the bidder concerned.

7.

The High Court appears to have confused revocation of the tender with revocation of the tender notice. The expression ""revocation of tender"" does

not obviously refer to revocation by the appellant-corporation, who had issued the tender notice. There is a clear difference between revocation of a

'tender' and revocation of the 'tender notice'. While revocation of the tender notice is the prerogative of the appellant-corporation, revocation of the

'tender' could be only by the bidder/tenderer concerned. The expression ""revocation"" may have been loosely used by the corporation, but, in the

context in which the same appears in the Special Conditions of Contract only means withdrawal/cancellation/ recall of the bid or tender submitted by

the bidder. In any such event, the earnest money deposited by the bidder would be liable to the forfeited is the plain and the simple meaning of the

Condition No. 2 extracted above. The High Court was in manifest error in holding that the forfeiture did not fall within the purview of Condition No. 2.

8.

It was next argued on behalf of the respondent that the provision empowering the appellant to forfeit earnest money upon withdrawal of offer even

before such offer was opened/accepted by the authority inviting the same will be impermissible in law. The financial bid in the instant case, it was

contended, had not been opened by the appellant-corporation although the technical bid was opened and had been found to be compliant. The

respondent could even so, at any time, before acceptance of the offer withdraw his bid. Inasmuch as respondent had done so, he was well within his

rights to demand refund of earnest money accompanying the bids. The forfeiture of the amount was illegal and the High Court justified in holding that

the respondent entitled to a refund.

9.

On behalf of the appellant-corporation it was contended that the submission of the bid itself was subject to the condition that it shall be accompanied

by an earnest money deposit which was liable to be forfeited in the event of the withdrawal of the bid. Opening of the bid or acceptance thereof in

terms of Section 5 of the Contract Act, 1872 was, in that view, wholly immaterial and irrelevant to the validity of the forfeiture ordered by the

appellant-corporation. Reliance in support of the submission was placed by Mr. Dhingra upon the decisions of this Court in National Highways

Authority of India v. Ganga Enterprises and another (2003) 7 SCC 410; State of Maharashtra and others v. A.P. Paper Mills Ltd. (2006) 4 SCC 209;

and State of Haryana and others v. Malik Traders (2011) 13 SCC 200.

10.

In Ganga Enterprises case (supra) this Court was examining a similar question. The argument in that case, as is the position even before us, was

that withdrawal of an offer before it was accepted could not result in forfeiture of the earnest money/security money given by the bidder. Repelling

that contention this Court held that while a person may have a right to withdraw his offer at any time before the acceptance is conveyed to him if the

offer is itself subject to the condition that the earnest money will be forfeited for not entering into contract or if some other act is not performed, then,

even though he may have a right to withdraw his offer he will have no right to claim the refund of the earnest money. Forfeiture of the earnest money,

in any such case, does not, observed this Court, infringe any statutory right under the Contract Act, 1872 for earnest/security is given and taken in

such cases only to ensure that a contract comes into existence. What is important is that this Court recognised that absence of any term stipulating

forfeiture of the earnest money may lead to situations where even those who do not have the capacity or intention of entering into a contract venture

into the bidding process for at times extraneous reasons. The purpose of such a clause providing for forfeiture of the earnest money clearly was to see

that only genuine bids are received. This Court observed: ""9.... ... ...The Indian Contract Act merely provides that a person can withdraw his offer

before its acceptance. But withdrawal of an offer, before it is accepted, is a completely different aspect from forfeiture of earnest/security money

which has been given for a particular purpose. A person may have a right to withdraw his offer but if he has made his offer on a condition that some

earnest money will be forfeited for not entering into contract or if some act is not performed, then even though he may have a right to withdraw his

offer, he has no right to claim that the earnest/security be returned to him. Forfeiture of such earnest/security, in no way, affects any statutory right

under the Indian Contract Act. Such earnest/security is given and taken to ensure that a contract comes into existence. It would be an anomalous

situation that a person who, by his own conduct, precludes the coming into existence of the contract is then given advantage or benefit of his own

wrong by not allowing forfeiture. It must be remembered that, particularly in government contracts, such a term is always included in order to ensure

that only a genuine party makes a bid. If such a term was not there even a person who does not have the capacity or a person who has no intention of

entering into the contract will make a bid. The whole purpose of such a clause i.e. to see that only genuine bids are received would be lost if forfeiture

was not permitted.

11.

In A.P. Paper Mills (supra) this Court was dealing with almost similar situation where according to Clause 5 of the tender notice the tenderer

would withdraw the tender only on the pain of forfeiture of the earnest money. While refusing to interfere with the forfeiture of the earnest money this

Court observed: (SCC p.23, para 13) “13. ….. But it is a case of withdrawal of tender and the effect of it is to be considered. Since the tender is

valid for a period of 45 days and withdrawal is before expiry of the period the earnest money is to be forfeited. The stand of the respondent that

because of delay in declaration of the final sale results there was no bar on withdrawal of the tender is clearly untenable. Once the tender is

withdrawn the result is that the tenderer who withdraws the tender cannot take the stand that since the final sale result has not been declared there is

no bar on the withdrawal.

12.

Reference may also be made to a decision of this Court in Malik Traders (supra). Even in this case this Court was dealing with the effect of

withdrawal of a bid before acceptance in the context of Section 5 of the Contract Act, 1872. Rejecting the submission that the bid can be withdrawn

without any forfeiture in view of Section 5 of the Contract Act, this Court observed: ""11…..Thus, even though under Section 5 of the Act a proposal

may be revoked at any time before the communication of its acceptance is complete as against the proposer, the respondent was bound by the

agreement contained in its offer/bid to keep the bid open for acceptance up to 90 days after the last date of receipt of bid and if the respondent

withdrew its bid before the expiry of the said period of 90 [pic]days the respondent was liable to suffer the consequence (i.e. forfeiture of the full

value of bid security) as agreed to by the respondent in Para 10 of the offer/bid. Under the cover of the provisions contained in Section 5 of the Act,

the respondent cannot escape from the obligations and liabilities under the agreements contained in its offer/bid.

12.

The right to withdraw an offer before its acceptance cannot nullify the agreement to suffer any penalty for the withdrawal of the offer against the

terms of agreement. A person may have a right to withdraw his offer, but if he has made his offer on a condition that the bid security amount can be

forfeited in case he withdraws the offer during the period of bid validity, he has no right to claim that the bid security should not be forfeited and it

should be returned to him. Forfeiture of such bid security amount does not, in any way, affect any statutory right under Section 5 of the Act. The bid

security was given by the respondent and taken by the appellants to ensure that the offer is not withdrawn during the bid validity period of 90 days and

a contract comes into existence. Such conditions are included to ensure that only genuine parties make the bids. In the absence of such conditions,

persons who do not have the capacity or have no intention of entering into the contract will make bids. The very purpose of such a condition in the

offer/bid will be defeated, if forfeiture is not permitted when the offer is withdrawn in violation of the agreement.

13.

The upshot of the above discussion is that it is no longer possible for the respondents to contend that the right to withdraw the bid in terms of

Section 5 of the Contract Act, 1872 would entitle them to withdraw without suffering forfeiture of the earnest money even in cases where the

submission and receipt of bids is itself subject to the condition that in the event of a withdrawal of the bid the earnest money stand forfeited. Inasmuch

as the High Court remained totally oblivious of the true legal position while directing refund of the earnest money, it committed an error.â€​

19.

Therefore, we find no difficulty in upholding the action of the respondents whereby they have issued show cause notice and the petitioner has been

asked to show cause as to why its EMD amounting to `25 lacs may not be forfeited. However, as regards, the show cause notice for blacklisting, we

have strong reservations for the same. At this stage, it would be apposite to reproduce the relief born of the show  cause notice, which reads thus:

“…..In view of above, you are hereby informed through this Show Cause Notice, as to why your EMD amounting to Rs.25.00 lakhs may not be

forfeited apart from blacklisting you. Your reply to this Show Cause Notice must reach this office within 15 days from the issue of this Show Cause

Notice else it will be presumed that you have nothing to say in this regard and necessary action as per the terms and conditions of the tender

document will be initiated against you.â€​

20.

It is more than settled that the fundamental purpose behind the serving of show cause notice is to make the noticee understand the precise case

set up against him which he has to meet. Therefore, this not only requires the statement of imputations detailing out the alleged breaches and defaults

one has committed, so that he gets an opportunity to rebut the same, but another requirement is the nature of the action, which is proposed to be taken

for such a breach, that has to be clearly set out so that the noticee is able to point out that proposed action is not warranted in the given case, even if

the defaults/breaches complained of are not satisfactorily. When it comes to black listing, this requirement becomes all the more imperative, having

regard to the fact that it is the harshest possible action.

21.

While taking the aforesaid view, we draw support from the judgement of the Hon’ble Supreme Court in Gorkha Security Services vs.

Government (NCT of Delhi) and others (2014) 9 SCC 105, wherein it was observed as follows:- “Necessity of serving show cause notice as a

requisite of the Principles of Natural Justice:

16.

It is a common case of the parties that the blacklisting has to be preceded by a show cause notice. Law in this regard is firmly grounded and does

not even demand much amplification. The necessity of compliance with the principles of natural justice by giving the opportunity to the person against

whom action of blacklisting is sought to be taken has a valid and solid rationale behind it. With blacklisting many civil and/ or evil consequences follow.

It is described as “civil death†of a person who is foisted with the order of blacklisting. Such an order is stigmatic in nature and debars such a

person from participating in Government Tenders which means precluding him from the award of Government contracts.

17.

Way back in the year 1975, this court in the case of M/s. Erusian Equipment & Chemicals Ltd. v. State of West Bengal & Anr. (1975) 1 SCC 70 ,

highlighted the necessity of giving an opportunity to such a person by serving a show cause notice thereby giving him opportunity to meet the

allegations which were in the mind of the authority contemplating blacklisting of such a person. This is clear from the reading of Para Nos. 12 and 20

of the said judgment. Necessitating this requirement, the court observed thus: “12. Under Article 298 of the Constitution the executive power of the

Union and the State shall extend to the carrying on of any trade and to the acquisition, holding and disposal of property and the making of contracts for

any purpose. The State can carry on executive function by making a law or without making a law. The exercise of such powers and functions in trade

by the State is subject to Part III of the Constitution. Article 14 speaks of equalitybefore the law and equal protection of the laws. Equality of

opportunity should apply to matters of public contracts. The State has the right to trade. The State has there the duty to observe equality. An ordinary

individual can choose not to deal with any person. The Government cannot choose to exclude persons by discrimination. The order of blacklisting has

the effect of depriving a person of equality of opportunity in the matter of public contract. A person who is on the approved list is unable to enter into

advantageous relations with the Government because of the order of blacklisting. A person who has been dealing with the Government in the matter

of sale and purchase of materials has a legitimate interest or expectation. When the State acts to the prejudice of a person it has to be supported by

legality.

20.

Blacklisting has the effect of preventing a person from the privilege and advantage of entering into lawful relationship with the Government for

purposes of gains. The fact that a disability is created by he order of blacklisting indicates that the relevant authority is to have an objective

satisfaction. Fundamentals of fair play require that the person concerned should be given an opportunity to represent his case before he is put on the

blacklistâ€​.

18.

Again, in Raghunath Thakur v. State of Bihar and Ors. (1989) 1 SCC 229 the aforesaid principle was reiterated in the following manner:- 4.

Indisputably, no notice had been given to the appellant of the roposal of blacklisting the appellant. It was contended on behalf of the State Government

that there was no requirement in the rule of giving any priornotice before blacklisting any person. Insofar as the contention that there is no requirement

specifically of giving any notice is concerned, the respondent is right. But it is an implied principle of the rule of law that any order having civil

consequence should e passed only after following the principles of natural justice. It has to be realised that blacklisting any person in respect of

business ventures has civil consequence for the future business of the person concerned in any event. Even if the rules do not express so, it is an

elementary principle of natural justice that parties affected by any order should have right of being heard and making representations against the order.

In that view of the matter, the last portion  of the order insofar as it directsblacklisting of the appellant in respect of future contracts, cannot be

sustained in law. In the premises, that portion of the order directing that the appellant be placed in the blacklist in respect of future contracts under the

Collector is set aside. So far as the cancellation of the bid of the appellant is concerned, that is not affected. This order will, however, not prevent the

State Government or the appropriate authorities from taking any future steps for blacklisting the appellant if the Government is so entitled to do in

accordance with law i.e. after giving the appellant due notice and an opportunity of making representation. After hearing the appellant, the State

Government will be at liberty to pass any order in accordance with law indicating the reasons therefor. We, however, make it quite clear that we are

not expressing any opinion on the correctness of otherwise of the allegations made against the appellant. The appeal is thus disposed of.â€​

19.

Recently, in the case of Patel Engineering Ltd. v. Union of India and Anr. (2012) 11 SCC 257 speaking through one of us (Jasti Chelameswar,J.)

this Court emphatically reiterated the principle by explaining the same in the following manner: “ “13. The concept of “blacklisting†is

explained by this Court in Erusian Equipment & Chemicals Ltd. v. State of W.B. as under:

‘20. Blacklisting has the effect of preventing a person from the privilege and advantage of entering into lawful relationship with the Government for

purposes of gains.’ 14. The nature of the authority of the State to blacklist the persons was considered by this Court in the abovementioned case

and took note of the constitutional provision (Article 298), which authorises both the Union of India and the States to make contracts for any purpose

and to carry on any trade or business. It also authorises the acquisition, holding and disposal of property. This Court also took note of the fact that the

right to make a contract includes the right not to make a contract. By definition, the said right is inherent in every person capable of entering into a

contract. However, such a right either to enter or not to enter into a contract with any person is subject to a constitutional obligation to obey the

command of Article 14. Though nobody has any right to compel the State to enter into a contract, everybody has a right to be treated equally when the

State seeks to establish contractual relationships. The effect of excluding a person from entering into a contractual relationship with the State would be

to deprive such person to be treated equally with those, who are also engaged in similar activity.

15.

It follows from the above judgment in Erusian Equipment case that the decision of the State or its instrumentalities not to deal with certain persons

or class of persons on account of the undesirability of entering into the contractual relationship with such persons is called blacklisting. The State can

decline to enter into a contractual relationship with a person or a class of persons for a legitimate purpose. The authority of the State to blacklist a

person is a necessary concomitant to the executive power of the State to carry on the trade or the business and making of contracts for any purpose,

etc. There need not be any statutory grant of such power. The only legal limitation upon the exercise of such an authority is that the State is to act

fairly and rationally without in any way being arbitraryâ€"thereby such a decision can be taken for some legitimate purpose. What is the legitimate

purpose that is sought to be achieved by the State in a given case can vary depending upon various factors.â€​

20.

Thus, there is no dispute about the requirement of serving show cause notice. We may also hasten to add that once the show cause notice is given

and opportunity to reply to the show cause notice is afforded, it is not even necessary to give an oral hearing. The High Court has rightly repudiated

the appellant's attempt in finding foul with the impugned order on this ground. Such a contention was specifically repelled in Patel Engineering (supra).

Contents of Show Cause Notice

21.

The Central issue, however, pertains to the requirement of stating the action which is proposed to be taken. The fundamental purpose behind the

serving of Show Cause Notice is to make the noticee understand the precise case set up against him which he has to meet. This would require the

statement of imputations detailing out the alleged breaches and defaults he has committed, so that he gets an opportunity to rebut the same. Another

requirement, according to us, is the nature of action which is proposed to be taken for such a breach. That should also be stated so that the noticee is

able to point out that proposed action is not warranted in the given case, even if the defaults/ breaches complained of are not satisfactorily explained.

When it comes to black listing, this requirement becomes all the more imperative, having regard to the fact that it is harshest possible action.

22.

The High Court has simply stated that the purpose of show cause notice is primarily to enable the noticee to meet the grounds on which the action

is proposed against him. No doubt, the High Court is justified to this extent. However, it is equally important to mention as to what would be the

consequence if the noticee does not satisfactorily meet the grounds on which an action is proposed. To put it otherwise, we are of the opinion that in

order to fulfil the requirements of principles of natural justice, a show cause notice should meet the following two requirements viz:

i) The material/ grounds to be stated on which according to the Department necessitates an action;

ii) Particular penalty/action which is proposed to be taken. It is this second requirement which the High Court has failed to omit. We may hasten to

add that even if it is not specifically mentioned in the show cause notice but it can be clearly and safely be discerned from the reading thereof, that

would be sufficient to meet this requirement.†“27. We are, therefore, of the opinion that it was incumbent on the part of the Department to state

in the show cause notice that the competent authority intended to impose such a penalty of blacklisting, so as to provide adequate and meaningful

opportunity to the appellant to show cause against the same. However, we may also add that even if it is not mentioned specifically but from the

reading of the show cause notice, it can be clearly inferred that such an action was proposed, that would fulfill this requirement. In the present case,

however, reading of the show cause notice does not suggest that noticee could find out that such an action could also be taken. We say so for the

reasons that are recorded hereinafter.†“29. No doubt, rules of natural justice are not embodied rules nor can they be lifted to the position of

fundamental rights. However, their aim is to secure justice and to prevent miscarriage of justice. It is now well established proposition of law that

unless a statutory provision either specifically or by necessary implication excludes the application of any rules of natural justice, in exercise of power

pre-judicially affecting another must be in conformity with the rules of natural justice.†“31. When it comes to the action of blacklisting which is

termed as 'Civil Death' it would be difficult to accept the proposition that without even putting the noticee to such a contemplated action and giving him

a chance to show cause as to why such an action be not taken, final order can be passed blacklisting such a person only on the premise that this is one

of the actions so stated in the provisions of NIT.â€​

22.

In view of the law propounded by the Hon’ble Supreme Court in the aforesaid decision, the show cause notice to the petitioner wit h respect

to blacklisting of its firm cannot be countenanced. The mere fact that the petitioner could have blacklisted in terms of condition No. 2(2) of the

agreement entered into between the parties, does not meet the mandatory requirement of the show cause notice in which it ought to have been either

specifically mentioned or could clearly and safely be discerned from the reading thereof that would be sufficient to meet the requirement and the

petitioner could thereafter be black-listed. Therefore, in absence of any specific stipulation in the show cause notice, the same cannot withstand

judicial scrutiny and to that extent the same is quashed and set - aside. However, this would not preclude the respondent No.2 from issuing a fresh

show cause notice to the petitioner in terms and in accordance with law.

23.

Consequently, the writ petition is partly allowed to the aforesaid extent. However, it is once again made clear that it would be open to the

respondents to take action against the petitioner after complying with the necessary procedure and formalities as delineated above. The parties are left

to bear their own costs. Pending application, if any, stands disposed of.