AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
45 paragraphs · 509 wordsHeard counsel for the parties.
Petitioner has approached this Court with a prayer to direct the
respondents to forthwith determine Agreement No. 10F2-2007-08, entered
into with the respondents for execution of repair and maintenance of a road
Kharka to Kotang via Patgachha having a stretch of 4 Kms. The petitioner
was successful in the NIT and was allotted the work vide letter no. 201 dated
20th February, 2008. He was under stipulation to complete the work by 25 th
March, 2008. Petitioner has, however, made representations before the
respondents raising issues relating to non-completion of the work for
reasons beyond his control such as non-payment of running bills due to non-
availability of funds; non-availability of raw materials and attack by Maoist
Extremists in the area where the work was being executed. Since the
respondents department failed to act as per the request made, petitioner has
been compelled to move this Court.
As per the stand of the respondent State brought on record
through an affidavit filed by respondent no. 4, petitioner has not raised any
such issues regarding payment of advance bill and supply of material before
the Executive Engineer, Rural Engineering Organization (Works) Division,
Gumla. Reference has been made to the various clauses of the agreement
in that regard. Counsel for the respondents further submits that repeated
extensions were also granted to the petitioner to complete the work.
Counsel for the petitioner has also referred to the
correspondences undertaken between the Executive Engineer and the
Assistant Engineer of Works Division as also with the Superintending
Engineer of the Rural Works Circle, Ranchi on the question of execution of
the work by the petitioner vide Annexure- 4 and 5, letters dated
18th January, 2010 and 25th January, 2010. It is submitted that the lack of
allotment for execution of the work and payment in lieu thereof is evident
from the bare perusal of the these correspondences.
I have considered the submissions of the parties in the light of the
relevant material facts noticed herein above.
On being asked, learned counsel for the parties have informed
that despite almost eight years of execution of the agreement and the non-
execution of the work for one reason or the other over which parties have
traversed allegations against each other, the agreement has not yet been
determined. There is no reason why the competent authority/ respondent no.
4 would not take a final decision on the question of determination of
Agreement No. 10F2-2007-08 executed with the petitioner in such state of
facts. However, let it be also made clear that this Court has in no way made
any comments on the merits of the allegations between the parties or the
fault or liability of either of them. Accordingly a decision is required to be
taken in that regard by the competent authority/respondent no. 4 within a
period of eight weeks from the date of receipt of a copy of this order in which
petitioner if asked to participate shall co-operate. Writ petition stands
disposed of.
