P.K. Misra, J.—The substantive prayer in the writ petition is to issue writ of certiorarifed mandamus for quashing the proceedings
Rco.3/02/c2 dated 27.3.2003 and directing the first respondent to issue ""C"" Form licence to the petitioner under the Tamil Nadu Cinemas
(Regulation) Act, 1955, read with Tamil Nadu Cinema (Regulation) Rules, 1957.
Petitioner is the Managing Partner of Sri Manjunatha Talkis. An application has been filed on behalf of the petitioner before the first respondent
for location of permanent cinema theatre. Initially, the first respondent issued No Objection Certificate for a period of three years for a semi-
permanent theatre. However, subsequently NOC was granted for permanent theatre and the building plan had been accordingly approved. The
petitioner, however, had not completed the building within the stipulated period. Subsequently on 4.1.1995, the petitioner filed a representation
before the Collector indicating that substantial portion of the building has been constructed and a fresh NOC may be issued. However, at that
stage, the Collector refused to grant NOC on the footing that the petitioner should have sought for extension of period as per the previous NOC.
The matter was taken to the appellate authority, who by order dated 13.2.1997 observed that NOC must be deemed to have been issued as no
order had been passed by the Collector within the stipulated period of six months. Accordingly, the order of the Collector was set aside and the
Collector was directed to reconsider the matter. Thereafter the Collector issued NOC and approved the plan by order dated 29.4.1999.
Thereafter on the basis of fresh plan, a fresh application has been filed and the Collector by proceedings dated 15.5.2001 approved the plan and
instructed the petitioner to complete the construction by 28.4.2002. The petitioner after completion of the construction, intimated the Collector by
letter dated 2.1.2002 regarding such completion and sought for issuance of ""C"" Form licence. Along with the application, the petitioner had
enclosed other certificates as required. At that stage, by letter dated 29.4.2002, the Collector directed the petitioner to obtain approval from the
Town and Country Planning authorities. In course of time the Member Secretary of the Town and Country Planning intimated that no permission
can be granted as the building had already been completed without obtaining the required permission. There was further correspondence between
the Collector and the Member Secretary of the Town and Country planning regarding requirement of such permission and ultimately the Collector
had written to the Joint Commissioner as well as to the Government recommending that since construction of the building had been initiated long
back and building had been completed, exemption may be granted. The Collector received the communication from the Government refusing to
accede to the request of the Collector. Thereafter the Collector communicated to the petitioner that no permission can be given, giving rise to the
filing of the present writ petition.
The contention of the petitioner is to the effect that at the time when the petitioner had initially applied for grant of permission, the provisions of
the Town and Country Planning Act were not attracted and only because of the subsequent amendment, the provisions of the Town and Country
Planning Act were attracted to the application for grant of permission for the construction of the building for the purpose of exhibiting cinema. It is
further contended that the Member Secretary of the Town and Country Planning has refused to give permission merely on the basis that the
building had already been completed. However, no substantial objection has been raised to the construction of the building or to the plan, which
had been duly approved by the Collector.
A counter affidavit has been filed on behalf of the first respondent indicating various developments from time to time. It has been further
indicated that in view of the correspondence between the Collector and the Government and other authorities, no permission could be granted.
Section 4 of the Tamil Nadu Cinemas (Regulation) Act, 1955 provides that the District Collector is the Licensing authority to grant licence under
the Act. Section 5 provides that licensing authority while considering the question as to whether licence should be granted or not, should have
regard to various factors indicated in Section 5(1) clauses (a) to (f). Section 5(1)(c) relates to the suitability of the place where the cinematograph
exhibition is proposed to be given. Section 5(2) provides that the licensing authority shall not grant licence unless it is satisfied that the Rules made
under the Act have been substantially complied with. Section 5-A empowers the licensing authority to permit construction and reconstruction of
buildings, installation of machinery, etc. for cinematograph exhibitions and sub-Section (1) provides that any person who intends to use any site for
constructing a building for exhibition of cinematograph film, or to use any site for constructing a building for exhibition of such film or to construct or
reconstruct any building or to install any machinery at any such place, is required to make an application to the licensing authority for permission
together with various particulars as may be prescribed. Such sub-Section specifically provides that any provision contained in the various
enactments specified shall not apply to any application made u/s 5-A. As per clause (vii), as it stood originally, the Town and Country Planning Act
is one such excluded provision which apparently had no applicability to any application for grant of permission u/s 5-A. Such provision had
continued to remain in force. However, by Tamil Nadu Act 11 of 1994, clause (vii) of Section 5-A(1) of the Tamil Nadu Cinemas (Regulation)
Act, 1955 stood deleted. In other words, after such deletion, the provisions of Town and Country Planning Act would be applicable even in
respect of application u/s 5 of the Tamil Nadu Cinemas (Regulation) Act, 1955.
In the present case, however, the application had been initially filed in the year 1979 and permission had been granted in the year 1982 and the
building plan had been approved in the year 1983. Subsequently, after completion of substantial portion of the building, fresh application had been
filed, but the Collector had rejected such application on the ground that extension of time should have been sought for. Thereafter on the basis of
the direction of the appellate authority, the Collector issued No Objection Certificate. Keeping in view the manner in which the matter had been
dealt with from time to time, in the peculiar facts and circumstances, it must be taken that in fact the grant of subsequent NOC by the Collector and
approval of the plan were in continuation of the earlier sanction. The earlier sanction had been given at a stage when the Town and Country
Planning Act was not applicable. The subsequent Act must have been taken to be revalidation of the approved plan and in continuation of the
earlier application which had been filed much prior to the deletion of Clause (vii) of Section 5-A(1). In other words, even though after Tamil Nadu
Act 11 of 1994 a fresh application under the Act may attract the applicability of Town and Country Planning Act, so far as pending applications
were concerned, such Act, namely the Town and Country Planning Act would not be applicable.
Judging the matter in the aforesaid context, it is obvious that no approval was required from the Town and Country Planning authorities and the
Collector committed illegality in refusing to consider the question of grant of ""C"" Form licence on the footing that permission has not been obtained
under the Town and Country Planning Act.
Alternative contention of the petitioner to the effect that even assuming that the Town and Country Planning Act is applicable, the authorities
under the said Act had refused to grant permission on mechanical grounds appears to be justified. It is apparent from the materials on record that
the authorities under the Town and Country Planning had refused to accord permission merely on the footing that the building had been completed.
The building had been completed on the basis of the plan approved by the Collector from time to time. The authorities under the Town and
Country Planning did not point out any substantial objection to the suitability of the site or any other relevant aspect. Merely because the building
had been completed should not have been a ground to refuse such permission. As a matter of fact, the Collector had recommended to all the
authorities that compliance with the Town and Country Planning Act may not be insisted upon and necessary exemption may be granted.
In the present case, since I have held that the Town and Country Planning Act had no application to the facts and circumstances of the case, it is
however unnecessary to delve further on this aspect.
For the aforesaid reasons, the order passed by the Collector dated 27.3.2003 is quashed and the Collector is directed to reconsider the
matter regarding issuance of ""C"" Form licence. The matter should be considered afresh, after giving opportunity of hearing to the petitioner, within
a period of two months from the date of receipt of the order. The Collector may also consider the question of issuance of temporary licence in ""E
Form.
The writ petition is accordingly allowed, subject to the directions indicated above. Consequently, WPMP.No.14258 of 2003 is closed.