AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
646 paragraphs · 7,335 wordsSr. No.,Particulars,Amount in Rs. (Crores),MoS Clause No.
1.,"Payment to TFIPL/Mittal group
towards settlement of disputes","10 (court deposit)
28.50 (by four cheques
38.50","1.1
1.1.2
2.,"License Renewal fee to DGTCP
on behalf of TFIPL/Mittal group",1.47,1.3
3.,Bank Guarantee to secure EDC,6.65,1.2.1
4.,"Bank Guarantee to secure
IDW performance",3.55,1.4
5.,"One time consultancy charges
for renewal of license",0.25,19
6.,"Transfer 50% shareholding of
Seth group in TFIPL at a price
of Rs.50,000/Â",50.00,1.5
SR. NO.,PARTICULARS,MOS CLAUSE NO.,
1,"Board Resolution to be issued by
TFIPL authorizing Seth Group to avail
the benefits under EDC relief policy
of 12.04.2012 or any other future
EDC relief policy announced by the
DTCP",1.2.1 Board Resolution,
2,"General Power of Attorney to be
issued by TFIPL in favour of FIPL
(Seth Group) by 20.05.2015 i.e.
within 15 days of execution of MoS to
enable application for Occupancy
Certificate and Completion.",53 (GPA Annexure 13),
3,"Bifurcation of license TFIPL is the
license holder in respect of 48.03
acres Sector 89 Land and has sold
development rights of 14.8 acres to
Seth Group â€
Application was to be made within 30
days for renewal for
bifurcation/recording of beneficial
interest. Mittal Group/TFIPL along
with the Seth Group was to submit
the same latest by 30.10.2015 Seth
Group has already applied in terms of
the renewal letter dated
01.10.2015 on 30.10.2015 and have
already made the payment towards
administrative charges to the DGTCP.",8,
4,"Renew the license till 2017 and as per
undertaking on 26.10.2015 to
renew till 2018.","Clause 17 and Court order dated
26.10.2015",
2.,"General Power of Attorney to be issued by TFIPL
in favour of FIPL (Seth Group) by 20.05.2015i .e.
within 15 days of execution of MoS to enable
application for Occupancy
Certificate and Completion.",,
3.,"Bifurcation of license TFIPL is the license holder
in respect of 48.03
acres Sector 89 Land and has sold
development rights of 14.8 acres to Seth Group â€
Application was to be made within 30 days for
renewal for bifurcation/recording of beneficial
interest. Mittal Group/TFIPL along
with the Seth Group was to submit
the same latest by 30.10.2015
Seth Group has already applied in terms of the
renewal letter dated
01.10.2015 on 30.10.2015 and have already made
the payment towards
administrative charges to the DGTCP.",,
4.,"Renew the license till 2017 and as per undertaking
on 26.10.2015 to renew till 2018.",,
intent and purpose of entering into the MoS which was to provide for complete severance of between the Seth Group and the Mittal Group from,,,
TFIPL and from the development of the 48.03 acres of land. It is due to the non-compliance of the obligations by the Mittal Group on the Seth Group,,,
and other stakeholders, the basic intent under the MoS has not been achieved.",,,
3.2 It is submitted on behalf of the Seth Group that the effect of the non-compliance of the obligations by the Mittal Group on the Seth Group and,,,
other stakeholders is as under:,,,
I. The basic intent under the MoS was to provide for complete severance of between the Seth Group and the Mittal Group from TFIPL and from the,,,
development of the 48.03 acres of land, which has not been achieved due to the defaults by the Mittal Group.",,,
II. The severance cannot take place without recording of change of beneficial interest in the land, which in turn cannot be done without renewal of the",,,
License and without complying with the conditions stipulated by the DGTCP.,,,
III. One of the conditions laid down by the DTCP for renewing the license was issuance of an NOC as per the requisite format. Since the NOC was,,,
conditional and not as per format, the renewal of license too has been rejected and the change in beneficial interest not being recording. This has",,,
rendered the entire settlement under the MoS as otiose and has led to parting of huge sums of money by the Seth Group without having the desired,,,
effect at all.,,,
IV. The most important consequence of all this is that because of non-renewal of license coupled with non-bifurcation of the license, the Seth Group",,,
has been unable to handover the possession to 700 flat owners of its Project ‘Ferrous City’ on the 14.80 acres of land falling in its share. It has,,,
further been unable to sell and/or utilize the unsold stock of 126 flats which can be utilized to generate funds to pay the only remaining outstanding,,,
liabilities of the Seth Group under the MoS.,,,
3.3 It is submitted that in terms of Clause 5.8 of the MoS, the Mittal Group agreed not to resign from the board of directors of TFIPL and not to",,,
transfer majority/controlling shareholding of TFIPL till renewal of licenses. However, perusal of the recent Balance Sheets of TFIPL shows that the",,,
said Balance Sheets have not been signed by the Mittal brothers namely Mr. Sumit Mittal (Contemnor No. 1) and Mr. Madhur Mittal (Contemnor No.,,,
2), but has been signed by proxies of the contemnors. This has been done in order to avoid sanctions from this Court or any other Court.",,,
3.4 Making the above submissions, it is prayed to issue the following directions:",,,
(a) Direct Mr. Sumit Mittal (Contemnor No. 1) and Mr. Mathur Mattal (Contemnor No. 2) and TFIPL to pay the entire EDC liability of TFIPL in,,,
relation to License No. 34, 35 and 36 other than the share of the EDC liability which the Seth Group has undertaken to pay.",,,
(b) Declare that Seth Group’s EDC liability was only up to an amount of Rs.25,27,92,000/- out of the total EDC liability of TFIPL, in relation to",,,
License No. 34, 35 and 36 as on 24.3.2015 together with interest accrued thereon from 24.03.2015. Out of this, Seth Group has already paid Rs.9.40",,,
crores vide DD No. 501599 dated 01.08.2016 and has also given a bank guarantee of Rs.6.65 Crores to DTCP towards its EDC liability. Seth Group,,,
is not liable to any other EDC payment in respect of License No. 34, 35 and 36.",,,
(c) Direct DTCP to bifurcate the Seth Group’s portion of the land.,,,
(d) Direct DTCP to raise a fresh demand on TFIPL for the entire outstanding liability of TFIPL and set out the payment schedule as per their,,,
applicable EDC relief policy.,,,
(e) Direct Mittal Group to renew the licenses as per their obligations set out under Clause 17, provide General Power of Attorney by TFIPL (as per",,,
clause 5.3) Board Resolution by TFIPL for availing benefit under EDC Relief Policy (as per Clause 1.2.1), NOC without any conditions (as per",,,
Clause 8) to the Seth Group.,,,
(f) Direct Mr. Sumit Mittal (Contemnor No. 1) and Mr. Mathur Mittal (Contemnor No. 2) to deposit their passports in Court and list the matter after a,,,
few weeks to determine if the Mittal Group has complied with the orders passed by this Court.,,,
It is submitted that the above prayers will not only resolve the various issues between the Mittal Group and Seth Group but will also resolve the plight,,,
of various homebuyers who are suffering because of the fraud played by the Mittal Group who are not complying with any of their obligations under,,,
the MoS and are conveniently resigning from the companies which are owned and controlled by them after siphoning off moneys paid by the Seth,,,
Group to them so that they can evade any liability.,,,
Miss Meenakshi Arora, learned senior advocate appearing on behalf of the respondent Mittal Group has submitted as under:",,,
(i) Mittal Group/TFIPL/Maximal have not committed any breach or disobedience of the terms and conditions of the MoS dated 04.05.2015;,,,
(ii) The contempt petition filed by the Seth Group is a farce, motivated and a ruse/ploy so as to create artificial/imaginary circumstances to cover up",,,
their willful and intentional acts of omission and commission of having failed to fulfill their obligations qua their allottees, who have invested in the",,,
project of the Seth Group, part of which is incomplete and the remaining unsafe for habitation as per the report of the Commission appointed by the",,,
RERA;,,,
(iii) In view of the order dated 01.10.2019 passed by RERA in Complaint No. 826/2018 â€" “Ferrous vs. Maximal†and Complaint No. 1402 of,,,
2018 â€" “Maximal vs. Maximalâ€, the present contempt petition is rendered infructuous. The alleged issues/acts of disobedience raised by Seth",,,
Group have been delineated and put to rest by the competent authority â€" RERA, Haryana. RERA, Haryana has put to rest the following issues:",,,
i) No objection to LC report filed;,,,
ii) Major violation in Zone A;,,,
iii) Grant of Occupation Certificate to the Developer in 48.038 acres of land under license No. 34-36/2007;,,,
iv) Quantification of EDC liability and Mode and manner of payment of EDC liability qua respective developers including that of FERROUS project,,,
(developed by Seth Group);,,,
v) Renewal of License qua each of developers;,,,
S. No.,Particulars,Amount (Rs. In Crores),Reply of contemnors
1.,Payment to Maximal,38.50,"Seth Group defaulted in
payment of the last
instalment compelling the
contemnors to file a
Contempt Petition before
this Court bearing No.
714/2015. It is on filing of
the Contempt Petition
that Seth Group in
obedience of MOS paid
the last instalment of
Rs.6 Crore.
2.,"License fee to DTCP,
Haryana in terms of
.clause 1.3",1.47,"I t is falsely stated that
Rs.1.47 crores was paid
by Seth Group. Seth
Group paid Rs.93.50
lakhs approximately,
proportionate to their
share of land out of
48.038 acres situated in
Sector-89, Faridabad.
Clause 1.3 relied upon is
to be read in conjunction
with clause 2 of the
MOS.
3.,"B a n k guarantee to
secure payment of EBC
(External Development
Charges)",6.65,"Seth Group in discharge
of his obligation to pay
furnished this BG, which
i s returnable to Seth
Group. This condition is
no longer applicable in
view of the order dated
01.10.2019 (RERA).
4.,"B a n k guarantee to
secure IDW (Internal
Development Work)",3.55,"Seth Group in discharge
of his obligation to
construct the project in
accordance with law
furnished this BG, which
is returnable to Seth
Group.
5.,Consultancy fee,0.25,"The license was expired
since the year 2009.
There were enumerable
formalities to be
completed for renewal of
license w.e.f. the date of
its expiry. It was
unanimously agreed to
engage the services of a
third party for the
renewal of the license.
6.,Transfer of shareholding,50.00,"I t is falsely stated that
Rs.50 Crores was paid
by Seth Group to
Maximal.
Seth Group held 500
shares in Maximal. Seth
Group opted to divert
their shareholding to exit
from the Company.
Mittal Group agreed to
acquire the shares and
paid consideration to Seth
Group.
It is therefore misleading
and outrageous to
mention that the
transferor of shares viz.,
Seth Group paid any
amount to the transferee
(Mittal Group).
7.,"T o t a l financial
commitment",100.42,"T h a t the amount
mentioned is misleading
and blatantly false.
The Seth Group in lieu of
land admeasuring 66.77
acres situated in Sector-
70, Faridabad, which was
fraudulently transferred
have paid only Rs.38.50
crores to former owner
i.e. Maximal against then
market value of the said
land which is
approximately Rs.300
crores.
8.,"Payment to DTCP,
Haryana",25.27,"In terms of clause 1.2 of
the MOS, Additional
Document filed on
21.12.2029 (IA 197372),
Seth Group undertook to
pay Rs.25.27 crores
together with interest to
DTCP, Haryana on
behalf of Maximal. In
view of the order dated
01.10.2019 (RERA) this
condition is no longer
applicable.
1.,Board Resolution,1.2.1,"A copy of the Board
Resolution dated
29.05.2015 was
forwarded to Seth Group.
Seth Group while
acknowledging the
receipt approved the
contents and sought
cooperation, if any, issue
arises in the absence of
original resolution.
The original resolution is
part of the minute book
and the extract thereof
was shared with Seth
Group on 29.05.2015.
2.,"GPA to be issued by
TFIPL in favour of FIPL",5.3,"U n d e r Clause 5.3
Additional Document
filed on 21.12.2019 (IA
197372), it was agreed
that TFIPL would
execute a registered
GPA in favour of FIPL.
Till 29.05.2015 no one
came from FIPL to get
the GPA registered.
A n email was issued
dated 29.05.2015
requiring Seth Group to
furnish a Stamp Paper
for GPA and also make
themselves available
before the office of Sub-
Registrar.
In response to the said
mail Seth Group vide
email dated 23.06.2015
informed that they do not
want to register the
GPA. This was in
contravention to the
agreed terms of MoS.
As an abundant caution
the Mittal Group on their
own took the initiative of
seeking approval of
DTCP, Haryana to
execute a registered
GPA in favour of Seth
Group to enable them to
deal with their project
without any impediment.
Since the Seth Group did
not come forward for
collection of the GPA
and its registration the
Mittal Group through
their attorney provided
Seth Group duly
executed GPA by the
executants vide letter
dated 04.07.2016.
3.,"Bifurcation of license &
Non grant of NOC by
Maximal",8,"NOC was provided by
the contemnors and filed
with DTCP, Haryana on
19.04.2016.
N O C is acknowledged
DTCP, Haryana and
found in order vide note
sheet dated 13.05.2016.
A s per “Clause-8â€,
parties agreed to jointly
apply for change of
developer i.e. from
TFIPL, to FIPL in terms
of the agreement dated
15.06.2007 and in terms
of policy of DTCP,
Haryana dated
18.02.2015.
A s per email dated
27.10.2015 the
contemnors reiterated
that filing of application is
a joint obligation and all
documents to be
submitted in that regard
with DTCP, Haryana are
ready, however, as per
conditions of policy the
new entity was also
required to submit
various information,
which the contemnors
were not aware much
less being shared with
the said information.
S e t h Group in
contravention to the joint
obligation unilaterally
applied for bifurcation of
license. The application
got rejected on
13.10.2016 for various
reasons including lack of
technical and financial
capacity of the Seth
Group. The rejection
order since not assailed,
attained finality.
Before RERA, Maximal
not only agreed to offer
their cooperation for
bifurcation of license but
submitted that all
formalities on the part of
the land owner/licensee
be dispensed with to
expedite the same. This
contention is accepted by
RERA vide order dated
01.10.2019.
4.,Renewal of license,17,"Maximal in terms of
order dated 26.10.2015
agreed to apply for
renewal of license on its
expiry.
Maximal applied for
renewal of license on
07.01.2016 as license
was expiring on
22.01.2016.
Since there was inaction
on the part of the
department, Maximal
filed a writ petition
before Chandigarh High
Court for direction
against the department.
While directing the
department the Writ
Petition was posted for
hearing on 05.07.2016.
DTCP, Haryana vide
order dated 04.07.2016
declined to renew the
license for non-
compliance of the
conditions mentioned in
“Para 3 and 4†of
the order.
The conditions mentioned
in “Para 3†were
fully complied with as
recorded in the office
note dated 25.01.2016.
However, Maximal was
prevented from filing any
appeal/challenge against
the said order dated
04.07.2016, as the Seth
Group declined to pay
EDC, which was a pre-
requisite condition and a
ground of rejection as
mentioned in
“Para4†of the order
dated 04.07.2016.
5.,"Responsibility to defend
138 proceedings",20 of MOS,"The Mittal Group and
Seth Group were
acquitted and an appeal
filed by the complainant
is pending adjudication .
developer including that of the Seth Group will be determined by DTCP, Haryana and paid to the department without the involvement of Mittal",,,
Group/Contemnors.,,,
5.3 That as per order dated 01.10.2019 passed by RERA, the following has been ordered:",,,
(a) Bifurcation/Division of licence of all the developers of 48.038 acres of land situated at Sector-89, Faridabad including that of Petitioner i.e. their",,,
entity FIPL.,,,
(b) Renewal of license for each of the developers by DTCP, Haryana on bifurcation.",,,
(c) Separate quantification of EDC and other statutory liabilities of each of the developers proportionate to their share of land.,,,
(d) Grant of occupation certificate, possession etc., as per law on removal of all unauthorized and illegal construction to be determined by DTCP,",,,
Haryana.,,,
(e) All or any formality requiring involvement of Maximal has been dispensed with.,,,
In light of the subsequent development and order dated 01.10.2019 passed by RERA, as such, the contempt petition is liable to be dismissed.",,,
Now, so far as submission on behalf of the Seth Group as regards non-payment of EDC to DTCP by Maximal, it is submitted that under the MoS",,,
dated 04.05.2015 there is no such condition and/or obligation on the part of the Maximal to pay any EDC to DTCP. It is submitted that as such the,,,
same was not even the case so prayed in the contempt petition. The contempt petition filed by the Seth Group was limited and confined to the alleged,,,
disobedience by the Maximal as follows:,,,
a) Non-issuance of GPA.,,,
b) Non-issuance of Board Resolution.,,,
c) Non-issuance of NOC for bifurcation.,,,
6.1 In fact, TFIPL/Maximal/Mittal Group in their contempt petition have subsequently pleaded disobedience of Seth Group by not paying External",,,
Development Charges (EDC) of license No. 34, 35 and 36 of 207 as determined by memo dated 27.03.2015 to Rs.25.27 crores (as on 24.03.2015)",,,
together with interest in terms of Clause 1.2.1 of the MoS and the undertaking given to this Court.,,,
6.3 That there is no condition and/or undertaking of Maximal to pay the differential amount of Rs.33.78 crores in the MoS dated 04.05.2015 and thus,,,
no mode and manner is provided in the MoS to pay the differential EDC amount i.e. 33.78 crores. This amount is payable by a separate and distinct,,,
entity TIDCO having the beneficial interest and ownership in land proportionate to which this amount is determined by the letter dated 27.03.2015,,,
issued by DTCP, Haryana. The issue regarding payment of EDC by the project developer namely viz. TIDCO of Rs.33.78 crores (determined by",,,
letter dated 27.03.2015) being the beneficial amount as attained finality. The Memo dated 27.03.2015 is the mother document which defines the,,,
obligations of each of the parties and the same came into existence by taking into consideration the MoS dated 27.03.2015. It is submitted therefore,,,
that it the MoS dated 27.03.2015 is considered as non-existent, then the MoS dated 04.05.2015 must fall.",,,
6.4 It is submitted that even otherwise the Maximal has no financial ability to pay any amounts. Maximal and other licensee divested of their right, title",,,
and interest in 48.08 acres way back in the year 2007-2008. The licensees are left with no interest in the project land. TIDCO is one of the project,,,
developers and has beneficial interest in part of the project land. Maximal as well as the Mittal Group have nowhere agreed to pay the amounts for,,,
and on behalf of the TIDCO being the beneficial owner of the project land.,,,
6.5 It is submitted that the malafides of Seth Group are apparent and writ large from the very fact that on one hand Licensee in the larger interest are,,,
wanting bifurcation of license in favour of Seth Group and other co-developers of the entire land whereas the Seth Group have taken every possible,,,
course and has left no stone unturned to negate/nullify the bifurcation of EDC Liability vide letter dated 27.03.2015 and subsequent thereto bifurcation,,,
of license vide letter dated 01.10.2015. The change of beneficial interest has been allowed by RERA vide order dated 01.10.2019 and there is no stay,,,
of the order. It is the Seth Group who has failed to honour their obligation under the MOS and is trying to negate both the letters to create an artificial,,,
and imaginary alibi for not honouring their obligations under the MOS dated 04.05.2015 of paying EDC liability of Rs.25.27 crores together with,,,
interest accrued as on date.,,,
6.6 It is submitted that as such Seth Group has not fulfilled its obligations/conditions/undertaking and paid the amount of Rs.25,27,92,000/- and",,,
therefore as such Seth Group is liable to be prosecuted and punished under the Contempt of Courts Act for which the respondents â€" Maximal/Mittal,,,
Group have filed the contempt petitions.,,,
6.7 It is submitted that therefore there is non-compliance on the part of Mittal Group, much less the willful disobedience of the MoS and the order",,,
passed by this Court and therefore it is prayed to dismiss the contempt petition filed by Seth Group.,,,
In reply, it is submitted on behalf of Seth Group that so far as the submission on behalf of Mittal Group in their defence that there are large-scale",,,
violations in the construction undertaken by the Seth Group in the portion of the license to lands falling within the Seth Group area is concerned, it is",,,
submitted that the same has no relevance to the present contempt proceedings. What Seth Group does in its own share of the land is not relevant for,,,
the MoS in the present proceedings. The Mittal Group is only raising these issues in order to sidetrack the main issue that they have been in contempt,,,
of their undertaking before this Court. It is submitted that even otherwise FIPL of the Seth Group has cured its non-compoundable violations in its,,,
construction. It is submitted that if the bifurcation of the license had taken place, the frivolous issues raised by Mittal Group would have been the",,,
exclusive liability of the Seth Group. It is submitted that in any case and as submitted hereinabove, the Mittal Group has failed to fulfill its obligation",,,
under the MoS, which subsequently became the part of the order passed by this Court and the disobedience/non-compliance is deliberate and willful",,,
and for this they are liable to be prosecuted and punished under the Contempt of Courts Act.,,,
Heard learned counsel appearing on behalf of the respective parties at length.,,,
8.1 At the outset, it is required to be noted that as such the present proceedings are filed by the respective parties to the MoS dated 04.05.2015, which",,,
subsequently was made the order passed by this Court dated 05.05.2015 to initiate appropriate proceedings against each other under the provisions of,,,
the Contempt of Courts Act. It is not in dispute that all were parties to the MoS/consent order.,,,
8.2 Before discussing the rival submissions made by the learned counsel appearing on behalf of the respective parties, the background which",,,
ultimately led to the MoS dated 04.05.2015 are required to be referred to and considered.,,,
8.3 Criminal proceedings were initiated against Ashish Seth of Seth Group and others which was the subject matter before this Court in Writ Petition,,,
(Criminal) No. 5 of 2015. The disputes involved were commercial disputes. It appears that during the course of hearing, a suggestion was given, as the",,,
controversy in the case pertained to payment of money as alleged, that the matter be sent for mediation. This Court, with the consent of the parties,",,,
sent the matter for mediation, subject to Ashish Seth depositing a sum of Rs.10 Crore before this Court. That Ashish Seth deposited the sum of Rs.10",,,
Crore. This Court requested Mr. Justice R.V. Ravindran, a former Judge of this Court, to mediate between the parties. Thereafter, learned Mediator",,,
mediated and initially submitted the interim report.,,,
The interim report of the learned Mediator reads as follows:,,,
“This Hon’ble Court by order 09.02.2015, referred the matter to mediation so as to enable the parties to arrive at a negotiated settlement.",,,
In pursuance of the above, mediation meetings were held on 14.02.2015, 16.02.2015, 17.02.2015, 18.02.2015, 10.03.2015, 15.03.2015 and 17.04.2015",,,
at New Delhi. The meetings were attended by Mr. Surender Seth and Mr. Ashish Seth with their counsel, Mr. Sachin Puri on one side, and Mr. Sunit",,,
Mittal and Mr. Mathur Mittal with their counsel Mr. Sanjay S. Chhabra on the other side.,,,
After detailed negotiations and discussions and exchange of various alternatives, parties have arrived at a broad consensus, without prejudice to their",,,
respective rights and contentions. Parties are further negotiating to give shape to the terms agreed, in a manner which will effectively express what",,,
has been agreed, and put an end to the disputes and at the same time safeguarding their respective interests.",,,
As several issues relating to legal and taxation issues require to be sorted out with the advice of experts, the parties have not been able to finalize the",,,
terms and execute the Memorandum of Settlement.,,,
On the joint request of the parties, further mediation meetings are scheduled for 11.04.2015, 12.04.2015 and 15.04.2015 for further negotiations and",,,
finalization of the draft Memorandum of Settlement.,,,
It is expected that the said process is likely to take at least two more weeks and, therefore, it is respectfully submitted that the time for completion of",,,
mediation process be extended till the end of this month.â€,,,
Thereafter, all the parties settled all the disputes and entered into the Memorandum of Settlement dated 04.05.2015. At this stage, it is required to be",,,
noted that the MoS dated 04.05.2015 was amongst (i) Shri Surender Seth; (ii) Shri Ashish Seth; (iii) M/s Ferrous Forging Limited; (iv) M/s Ferrous,,,
Alloy Forging Pvt. Ltd.; (v) M/s Ferrous Township Pvt. Ltd. And (vi) M/s Ferrous Infrastructure Pvt. Ltd. (all belonging to Seth Group) as the first,,,
party AND (i) Shri Sumit Mittal; (ii) Shri Madhur Mittal (belong to Mittal Group) as the second party AND M/s Triveni Ferrous Infrastructure Pvt.,,,
Ltd. as the third party. The preamble of the MoS reads as under:,,,
“PREAMBLE:,,,
WHEREAS TFIPL is an Infrastructure Development Company in which the Seth Group represents that it holds 50% share (i.e. FFL and FAFPL,,,
have 33% and 17% shares respectively); and Mittal Group represents that it holds the remaining 50% share;,,,
WHEREAS disputes arose among the Seth Group on the one hand and the Mittal Group on the other, with respect to lands admeasuring 37.58125",,,
acres and 29.1953 acres, situated at Sector 70, Faridabad (Haryana) on account of Mittal Group claiming that the Seth Group should pay certain",,,
amounts to TFIPL and on account of certain issues relating to management and maintenance of statutory records and books of account of TFIPL.,,,
WHEREAS the said disputes have given rise to the following legal proceedings which are either pending in Courts of Law and/or are under,,,
investigation by the Competent Authority:,,,
(a) Company Petition bearing C.P. No. 158 (ND) of 2013 filed by FAFPL and FFL against the TFIPL, Sumit Mittal, Madhur Mittal and others qua the",,,
affairs of TFIPL, pending before Company Law Board, New Delhi;",,,
(b) Complaint Case No. 613/2014 pending before the Jurisdictional Magistrate at Agra (U.P.) arising from FIR No. 513/2014 against Surender Seth,",,,
Ashish Seth and others, registered at Police Station, New Agra, Agra;",,,
(c) FIR No. 808/2014 against Surender Seth, Ashish Seth and others, registered with the Economic Offence Wing, New Delhi;",,,
(d) Crl. M.C. No. 5621/2014 on the file of Hon’ble Delhi High Court (Ashish Seth Vs. State & Another);,,,
(e) Crl. M.C. No. 5622/2014 on the file of Hon’ble Delhi High Court (Surender Seth Vs. State and Another);,,,
(f) W.P. (Crl.) No. 5/2015 on the file of Hon’ble Supreme Court of India (Ashish Seth Vs. Govt of NCT of Delhi & Others);,,,
(g) W.P. (Crl.) No. 11/2015 on the file of Hon’ble Supreme Court of India (Surender Seth Vs. Govt of NCT of Delhi & Others).,,,
WHEREAS Criminal Case No.235/2014, filed by one Mr. Hari Mohan Gupta (a witness in FIR No.513/2014) against Ashish Seth is pending before",,,
the Special Judge, Agra (U.P.) and Ashish Seth has filed a petition under Section 482 Cr.P.C. being Petition No. 134/2015, before the Hon’ble",,,
Allahabad High Court, for quashing the said proceedings.",,,
WHEREAS the Hon’ble Supreme Court of India in the proceedings mentioned at Serial No. (f) and (g) above, vide Order dated 14.01.2015",,,
referred the parties to mediation and subsequently, vide Order dated 09.02.2015 requested Justice R.V. Ravindran, former Judge of Hon’ble",,,
Supreme Court of India to act as a Mediator to assist the parties to arrive at a negotiated settlement;,,,
WHEREAS after deliberations and discussions between the two groups ove several sittings, the parties have agreed to resolve all their disputes",,,
amicable as per the terms hereinafter set out.â€,,,
Thus, the parties entered into the MoS and agreed to resolve all their disputes amicably. Therefore, as such, all the parties to the MoS dated",,,
04.05.2015 are bound to comply with the relevant terms and conditions and their respective obligations. As per the terms of the settlement agreed,,,
between the parties, there are certain obligations to be fulfilled by the respective parties, which the respective parties are bound to fulfill and comply",,,
with in its true spirit. The obligations of Seth Group are specifically mentioned in Clauses 1 to 1.5.1. The Seth Group has further agreed and,,,
undertaken to perform their part of obligations with the Mittal Group and TFIPL as mentioned in Clauses 3 to 3.14 and Clause C. Similarly, the Mittal",,,
Group and TFIPL’s obligations, representations and warranties are also specifically mentioned in Clause D, which are specifically mentioned in",,,
Clauses 5 to 5.9.,,,
As agreed between the parties and in consideration of the obligations in Clauses 1.1, 1.3 and 1.4 and on furnishing of all requisite bank guarantees as",,,
required in terms of Clause 1.2 by the Seth Group under the MoS, all FIRs, complaints and cases mentioned in Clause 6.1 to Clause 7 were required",,,
to be withdrawn/quashed/cancelled/terminated. The joint obligation of the parties are specifically mentioned in Clause F (relevant Clauses 8 & 9). As,,,
per Clause 10, TFIPL and Mittal Group confirmed that there are no outstanding claims of Seth Group or any of its constituents under the agreement",,,
dated 15.07.2007 in respect of FSI admeasuring 11,28,204 Sq Ft. including FSI for EWS calculated on a total area of 14.80 acres on the land situated",,,
in Sector 89 Faridabad under License Nos. 34, 35 and 36 of 2007 granted in the name of TFIPL and others. Clause 12 which is an important and",,,
relevant clause reads as under:,,,
“12. It is hereby confirmed that other than the payment of the EDC amount required to be made under Clause 1.2.1 and under Clause 3.8 above,",,,
Seth Group shall not be liable for any other EDC payment under License Nos. 34, 35 and 36 of 2007 either on renewal and/or upon bifurcation of",,,
License Nos. 34, 35 and 36 of 2007, except to the extent of Rs.25,27,92,000/- together with interest accrued thereon from 24.03.2015, imposed by",,,
DTCP, Haryana. It is further clarified that the liability to pay EDC of Seth Group in a sum of Rs.25,27,92,000/- against the total EDC liability of",,,
Rs.59.05 crores as on 24.03.2015, shall not be varied subject, however, to the condition that in the event of the total liability, which has been assessed",,,
at Rs.59.05 crores as on 23.04.2015, being revised from Rs.59.05 crores, to any higher amount as on 24.03.2015, on account of revised calculation or",,,
similar reason. In such eventuality, the Seth Group will bear the proportionate increase in regard to the amount in excess of Rs.59.05 crores.â€",,,
Clause G is specifically with respect to renewal of licenses, more particularly, license Nos. 34, 35 and 36 of 2007. The relevant clauses with respect to",,,
renewal of licenses are Clauses 17, 18 and 19, which read as under:",,,
Mittal Group shall apply for renewal of license by 23.06.2015 subject to compliance of clause 1.2 (to the extent of providing Bank Guarantee), 1.3",,,
& 1.4 by the Seth Group. The Seth Group have provided documents/undertakings with respect to the lands falling to share of the Seth Group under,,,
Agreement dated 15.06.2007, i.e. (i) Status of construction/allotment of EWS Flats, and (ii) Service Plan status, its drawing, estimates and its approval",,,
from HUDA, Chandigarh annexed as Annexure-16, to enable Mittal Group to apply for renewal of license. Seth Group does not have any further",,,
document in this regard, however, it is clarified that in case any indemnity, undertaking, letter and/or similar document is required to be executed after",,,
filing of the application for renewal of license, pertaining to the lands falling in the share of Seth Group under Agreement dated 15.06.2007, Seth Group",,,
shall do the needful at the earliest if so requested by Mittal Group.,,,
On application made for renewal of license in terms of clause 17, Mittal Group will secure renewal of license within 90 days. All administrative",,,
and miscellaneous charges, compounding fee, penalties and other charges levied and payable by PAL, ORS and Heritage for renewal of license shall",,,
be paid by the Mittal Group. All such charges in respect of FIPL agreement shall be exclusively paid/borne by Seth Group by similarly paying to,,,
TFIPL immediately on being demanded.,,,
Seth Group shall pay a sum of Rs.25,00,000/- (Twenty Five Lacs only) to Mittal Group for hiring/engaging consultancy services for renewal of",,,
License Nos. 34, 35 & 36 of 2007 in favour of TFIPL at the time of filing of the application for renewal of license by the Mittal Group.â€",,,
As per Clause 27, with the execution of the said MoS and subject to compliance of undertaking and fulfillment of all obligations of the Seth Group and",,,
Mittal Group/TFIPL as undertaken in the MoS, it was agreed between the parties that all pending disputes amongst the parties. shall stand resolved",,,
and TFIPL and/or Mittal Group have no claim of any nature against the Seth Group and similarly Seth Group shall have no claim of any nature against,,,
the TFIPL and/or Mittal Group. The MoS further provides the consequences of breach/non-payment of the amounts. The relevant clauses are,,,
Clauses 36, 37 and 38, which read as under:",,,
“36. In the event of any default by Seth Group of their obligations and warranties, the Mittal Group and TFIPL will be entitled to initiate legal",,,
proceeding for enforcing performance of the obligations/warranties given by Seth Group, including initiation of contempt proceedings against the Seth",,,
Group in accordance with law.,,,
In case there is a default in payment as agreed in Clause Nos. 1.1, 1.3 & 1.4 of furnishing of all requisite Bank Guarantees as required in terms of",,,
clause 1.2 by the Seth Group, the Mittal Group and TFIPL will also be entitled to approach the Hon’ble Supreme Court for revival of the",,,
complaints/FIRs stated at serial Nos. (b) & (c) of the list of cases mentioned in the preamble above. Provided however, on Mittal Group and TFIPL",,,
obtaining performance of the obligations, the revised criminal proceedings and contempt proceedings, if any, shall be terminated.",,,
In the event of any default by Mittal Group of their obligations and warranties, the Seth Group will be entitled to initiate legal proceeding for",,,
enforcing performance of the obligations/warranties given by the Mittal Group, including initiation of contempt proceedings against the Mittal Group in",,,
accordance with law.â€,,,
This MoS was placed before this Court in the aforesaid Writ Petition and this Court recorded the settlement in entirety and as agreed between the,,,
parties and as prayed, the MoS dated 04.05.2015 became a part of the order and this Court directed the parties to adhere to the terms and conditions",,,
of the settlement and the undertakings given therein. This Court specifically further observed that every facet of it shall tantamount to an order of this,,,
Court and in case of failure the parties shall be at liberty to move this Court for an appropriate direction. Thus, as per the MoS and even as per the",,,
order passed by this Court dated 05.05.2015, all the parties to the MoS shall have to comply with and/or fulfill their respective obligations as mentioned",,,
in the MoS dated 04.05.2015. As observed hereinabove, the disputes were commercial disputes and therefore all the parties to the disputes agreed to",,,
resolve all their disputes, which culminated into the MoS and thereafter the order passed by this Court.",,,
The entire object and purpose of entering into the settlement was to resolve all the disputes between the parties. Therefore, it is the duty of the",,,
Court that the settlement entered into between the parties and the consent order passed by this Court should be given effect to in its letter and spirit.,,,
All the parties to the consent terms are required to fully comply with the terms of settlement/consent terms and the consent order. One party cannot,,,
be permitted to say that that portion of the settlement which is in their favour be executed and/or complied with and not the other terms of the,,,
settlement/consent terms/consent order.,,,
9.1 From the facts narrated hereinabove and even otherwise considering the relevant clauses of the MoS and the obligations to be fulfilled by the,,,
respective parties to the MoS, it appears that Seth Group have fully complied with their obligations, except deposit of the total amount of Rs.25.27",,,
crores - payment to DTCP towards initial liability of Rs.59.05 crores of TFIPL. It appears that Seth Group have already paid Rs.9.40 crores against,,,
the total libaiility of Rs.25.27 crores towards EDC liability against the total liability of Rs.59.05 crores of TFIPL as per Clause 1.2. It appears that the,,,
balance amount is not deposited by the Seth Group as the Mittal Group have not fulfilled their obligations under the MoS. It is stated at the bar that the,,,
Seth Group is always ready and willing to fulfill their obligations in terms of the MoS, i.e. their liability as per Clause 1.2, subject to Mittal Group fulfill",,,
its obligations. From the material on record, it appears that the Mittal Group have not fulfilled their obligations as per Clause 1.2, Clause 5.3 and Clause",,,
Neither the Mittal Group nor TFIPL have deposited the balance amount to be paid towards EDC liability of Rs.59.05 crores (deducting Rs.25.27,,,
crores to be paid by the Seth Group as per Clause 1.2). It is the case on behalf of the Mittal Group that it is the liability of the TIDCO and not the,,,
Mittal Group and in the MoS there is no specific term and the obligation that the said amount is to be paid by the Mittal Group. It is required to be,,,
noted that all the terms and conditions/obligations of the Seth Group, Mittal Group and TFIPL are required to be read conjointly. The license Nos. 34,",,,
35 and 36 of 2007 are required to be transferred in favour of Seth Group. It appears that TFIPL acquired some land at Sector 70 and some 48.03,,,
acres of land at Sector 89, Faridabad. TFIPL also availed licenses Nos. 34, 35 and 36 from the competent authorities in the year 2007 in respect of",,,
land bearing at Sector 89 with an intent to develop the Sector 89 land. Subsequently, however , both the parties â€" Seth Group and Mittal Group",,,
agreed that it would be the best that the development of the said land be divided and carried out separately and thereupon the development rights in,,,
the Sector 89 land parcel of 48.03 acres of land belonging to TFIPL was sold in the manner mentioned as under:,,,
Â,,,
TFIPL,,,
48.03 acres,,,
↓,,,
TIDCO ORS Limited FIPL Heritage Pal,,,
(in 5.5 acres 14.80 acres 2.8 acres Infrastructure,,,
liquidation) (third party) (Seth Group) (third party) 10.48 acres,,,
14.80 acres Ferrous City (third party),,,
(Mittal Group) Project,,,
 The liability of Rs.59.05 crores was with respect to the entire land â€" 48.03 acres at Sector 89, Faridabad. Therefore, the liability of the Seth",,,
Group would be with respect to their share out of 48.03 acres which, as agreed between the parties, would come to Rs.25.27 crores and therefore the",,,
balance is naturally required to be paid by Mittal Group/TFIPL. Unless and until the entire amount is deposited with the DTCP towards EDC, the",,,
aforesaid licenses cannot be renewed and after renewal they are required to be bifurcated and transferred. As the Mittal Group has refused to deposit,,,
the balance amount of EDC (after deducting Rs.25.27 crores which is the liability of Seth Group as per Clause 1.2), the licenses are not being",,,
renewed thereafter. If the contention and the submission on behalf of the Mittal Group is accepted, in that case, the entire MoS would be unworkable",,,
and the purpose and object of the MoS to resolve all the disputes would be frustrated. As the Mittal Group has not fulfilled its obligations it appears,,,
that the Seth Group has not deposited the balance amount of EDC liability. At this stage, it is required to be noted that as per Clause 5.8 Mittal Group",,,
shall not resign from the Board of Directors of TFIPL and shall not transfer majority/controlling shareholding in TFIPL till renewal of licenses. As per,,,
the case of Seth Group, Mittal Group have retired from the Directorship of TFIPL and the balance sheet since then is being signed by the proxies.",,,
9.2 As observed hereinabove, as per the MoS dated 04.05.2015 and even as per the order passed by this Court 05.05.2015, all the parties to the MoS",,,
are bound to fulfill their respective obligations. As observed hereinabove, Seth Group have fulfilled their obligations, except the payment of DTCP i.e.",,,
Rs.25.27 crores as per Clause 1.2 of the MoS (except Rs.9.49 crores which is paid).,,,
Having heard the learned counsel for the respective parties and considering the material on record, we are of the opinion that the respondent",,,
Mittal Group in Contempt Petition No. 34 of 2016 have deliberately and willfully not fulfilled their obligations which they are required to fulfill under the,,,
MoS dated 04.05.2015 and as such they have rendered themselves liable for the action under the Contempt of Courts Act. However, before taking",,,
any further action, we propose to give further two months’ time to the respondents, namely, Shri Sumit Mittal, Shri Mathur Mittal and TFIPL to",,,
fulfill their part of obligations under the MoS dated 04.05.2015, more particularly,",,,
(i) To pay the entire EDC liability of TFIPL with interest in relation to license Nos. 34, 35 and 36 other than the share of the EDC liability which the",,,
Seth Group has undertaken to pay as per Clause 1.2 of the MoS;,,,
(ii) As per Clause 1.2, EDC liability of the Seth Group is to the extent of Rs.25,27,92,000/-, out of the total EDC liability of TFIPL in relation License",,,
Nos. 34, 35 and 36 as on 24.03.2015 together with interest accrued thereon from 24.03.2015. Therefore, the Seth Group shall make the entire",,,
payment of Rs.25,27,92,000/- along with the interest accrued thereon from 24.03.2015 towards their EDC liability in respect of License Nos. 34, 35",,,
and 36 of 2007;,,,
(iii) The Mittal Group is hereby further directed to renew the license Nos. 34, 35 and 36 of 2007; to execute GPA by TFIPL (as per Clause 5.3),",,,
Board Resolution by TFIPL for availing benefit under EDC Relief Policy (as per Clause 1.2.1), NOC without any conditions (as per Clause 8) to the",,,
Seth Group.,,,
(iv) Thereafter, the DTCP to bifurcate the Seth Group’s portion of the land in accordance with law and as per the policy and/or the rules and",,,
regulations, if any. It is also observed that it will be open to the respective parties to avail the benefit of the applicable EDC Relief Policy, which may",,,
be considered by the DTCP in accordance with the applicable EDC Relief Policy, if any.",,,
10.1 The aforesaid entire exercise shall be completed within a period of two months from the date of lifting of lockdown in the concerned area, failing",,,
which, as observed hereinabove, this Court shall proceed to pass appropriate further order/orders under the Contempt of Courts Act for non-",,,
fulfillment of the obligations by the respondents â€" Shri Sumit Mittal, Shri Madhur Mittal and TFIPL. As observed hereinabove, this Court has",,,
deferred to pass further orders against the contemnors - Mittal Group and TFIPL to enable them to give them further opportunity.,,,
In view of the above discussion and for the reasons stated above, we see no substance in Contempt Petition (C) No. 257 of 2016 and Contempt",,,
Petition (C) No. 889 of 2017 filed by the Mittal Group against the Seth Group. Under the circumstances, Contempt Petition (C) No. 257 of 2016 and",,,
Contempt Petition (C) No. 889 of 2017 deserve to be dismissed and are accordingly dismissed. List Contempt Petition (C) No.34/2016 in Writ Petition,,,
(Crl.) No. 5 of 2015 before this Bench immediately after three months.,,,
