The petitioner produces an Affidavit-of-Service as well as the notice of service on Learned State Counsel which are not contemporaneous. The
petitioner, when the matter was first taken up today, was therefore requested to inform Learned State Counsel that the matter shall be next taken up
at 1-00 p.m. today. The petitioner informs this Court that Learned State Counsel was informed that the matter would be taken up at 1-00 p.m. today.
Mr. Biswajit De, Learned Counsel, represents the State- respondents with Ms. Rajlakshmi Ghatak, Learned Advocate. None appears for the private
respondents. The facts of this case, as presented by Learned Advocate for the petitioner, are almost of a nature that shock the conscience of this
Court. The petitioner claims to be the absolute owner of a plot of land being Dag No. 743/2110, Khatian No. 1346, J.L. No. 25, Mouza-Patghara as
well as Dag No. 783/1032 of the same Mouza under Jogeshganj Panchayat, P.S. Hemnagar Coastal Police Station, District North 24 Parganas (the
said land in issue).
The petitioner further claims that the said land in issue is a Bastu land. The petitioner works for gain in a private organisation in Kolkata and his wife
normally residing at the residence of the petitioner, as recorded above and, looks after the said land in issue. The petitioner submits that in January,
2015 when his wife visited Kolkata for her medical treatment, on returning home on the 4th of February, 2015 she found that the private respondent
nos. 8 and 9 have started construction of a house on the said land absolutely owned by the petitioner. Being shocked at the construction made on his
said land, the petitioner has been running since from the proverbial pillar to post urging the concerned authorities to take the correct steps. It has
transpired to the knowledge of the petitioner and such is stated at paragraph 10 (ten) of the writ petition that the construction is being forcefully made
on the said land in issue on the strength of a purported sanction obtained by the respondent nos. 8 and 9 under the Indira Awaas Yojana (IAY).
This Court has had the opportunity to observe in similar litigation presented earlier that it is the duty of the concerned authority while sanctioning any
plan under any welfare scheme such as the IAY, to completely verify the documents and all other particulars claimed by the proposed beneficiaries
connected to ownership of any plot of land/lands in respect of which construction is intended to be raised since, in the event, the construction is
allowed at random, the constitutionally protected Right to Property of landholders, such as the present petitioner protected by Article 300A stood to be
deeply infringed.
Therefore, on the basis of the facts so far presented before this Court, this Court is of the view that the petitioner is in requirement of an interim
protection. Accordingly, in prima facie consideration of the enormity and gravity of the deprivation suffered by the petitioner, this Court directs the
District Magistrate, North 24 Parganas and the Superintendent of Police, North 24 Paganas to take steps to ensure that the parties, particularly the
private respondent nos. 8 and 9, shall maintain status quo as on date with regard to the construction in issue until the next date of hearing. Both the
District Magistrate, North 24-Parganas and the Superintendent of Police, North 24-Parganas shall file a Report through Learned State Counsel on the
next date.
The petitioner is granted leave to implead the District Magistrate and the Superintendent of Police, North 24-Parganas as party respondents to the writ
petition. Let copies of the writ petition along with copies of this order be also served by the petitioner on the added respondents. Let a fresh copy of
the writ petition be handed over by the petitioner to Learned Counsel for the State Respondents. Let notice of this order be issued to the private
respondent nos. 8 and 9 by the petitioner, who shall file a formal proof of such communication on the next date. Let the matter next appear under the
heading “Mentioned Matters†on the 21st of June, 2018.