AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
59 paragraphs · 1,453 wordsM.N. Chandrukar, C.J.—All these three revision petitions two of which are by the tenant and one by the landlord, raise a question with
regard to the correctness of the fair rent fixed in respect of premises which are situated on the Mount Road, Madras, with a built up area of
18,047 sq. ft., 13,967 sq. ft., are covered by Go-down and 4,080 sq. ft. are covered by office premises.
The original agreed rent was Rs. 3,000 per month. The landlord filed an application for fixation of fair rent claiming Rs. 18,000 per month. The
Rent Controller fixed the fair rent at Rs. 6,801 per month. Against this order both the landlord and the tenant went in appeal. The tenant''s appeal
came to be dismissed. The landlord appeal came to be allowed partly and the fair rent was fixed at Rs. 9,825 per month. Since the appellate order
was passed in two appeals, one by the tenant and the other by the landlord, two revision petitions came to be filed by the tenant being C.R.P.
Nos. 2491 and 2492 of 1983. Strictly speaking, since there is a common order, which arises out of proceedings started only on one petition, two
revision petitions do not appear to be necessary at all and it would have been perfectly permissible for the tenant to file only one civil revision
petition.
In C.R.P. No. 178 of 1984, the landlord has challenged the reduction of its claim inasmuch as the rent originally asked by it has not been fixed
as fair rent. Substantially the two points on which parties seem to be at issue relate to the cost as estimated by the Appellate Authority in respect of
basic amenities and Schedule I amenities. In respect of basic amenities, the Rent Controller had estimated the cost to be 10 per cent of the cost of
construction. This was enhanced to 15 per cent by the Appellate Authority. In respect of Schedule I amenities, the Rent Controller had arrived at
an ad hoc figure of Rs. 10,000 which was, however, enhanced by the Appellate Authority at Rs. 46,788 being 5 per cent of the cost of
construction. Now, so far as the basic amenities are concerned, which are in the nature of facilities for water supply, electrical fittings and the
drainage system, the Rent Controller has merely observed that he was inclined to award 10 per cent of the cost of construction as the value of the
amenities. Now the Rent Controller himself has come to the conclusion that the cost of construction at the rate of Rs. 32 per sq. ft. would come to
Rs. 27,750. In so far as the basic amenities are concerned the relevant provision of law is in Section 4(5)(a) of the Tamil Nadu Buildings (Lease
and Rent Control) Act, which provides that the cost of construction of the building including cost of internal water-supply, sanitary and electrical
installations shall be determined with due regard to the rates adopted for the purpose of estimation by the Public Works Department of the
Government for the area concerned. A further discretion is, however given to the Rent Controller in appropriate cases to allow or disallow an
amount not exceeding 30 per cent of the cost of construction having regard to the nature of the cost of construction. I am informed that, so far as
the Public Works Department rates are concerned, the maximum rate with regard to the basic amenities referred to in Section 4(5)(a) of the Act is
22-1/2 per cent, allocated as 7-1/2 per cent in the case of water supply, 7-1/2 per cent in the case of sanitary fittings and 7-1/2 per cent for
electrical installations. Now it is obvious that the cost of construction which is to be determined is with reference to the time of pendency of the
proceedings, because under Clause (b) of sub-Section 5(a) of Section 4 of the Act, a depreciation has to be calculated. The best method would
have been to find out what exactly is the cost which has to be incurred for purpose of making available the basic amenities. Since the statute itself
indicates that the guideline is to be the rate adopted for the purpose of estimation made by the Public Works Department, those rates will
undoubtedly be taken into account. There has to be some rational basis with regard to the percentage to be adopted even within the range
permissible by the statute before a decision is arrived at with regard to the cost in respect of the provision of the amenities. It must be remembered
that even the law contemplates fair rent to be fixed as a return on the investment made by the landlord. In a case of fixation of fair rent, judicial
notice must be taken of the fact that cost of construction and cost of materials which have to be used for the construction of a building including the
fittings for water supply, sanitary fittings as well as for making electrical installations have always been escalating and are considerably high.
Therefore, having regard to the prevailing high level of cost of materials used for construction of a house, there has to be a realistic approach in the
matter of estimating the cost of construction and the cost of making amenities available. Therefore, within the range prescribed by the statute the
percentage has to be fixed on a realistic basis. This can only be done after ascertaining the normal cost of material necessary for providing the basic
amenities. Assuming for the sake of argument that the cost of construction of a building is Rs. 1,00,000 without of course including the water
supply facilities, drainage facilities and electrical fittings, I think judicial notice can be taken of the fact that within only 10 per cent of this cost, it is
hardly possible to meet the cost of these amenities. Therefore, it cannot be said that the increase of the percentage from 10 per cent to 15 per cent
as awarded by the Appellate Authority is so excessive which should be interfered with in these revision petitions.
It is argued, on behalf of the tenant that there was no challenge in the grounds of appeal to the estimated cost of the basic amenities. Assuming
that to be so, it is quite permissible for the landlord to canvass on the material on record the question of law as to whether 10 per cent of the cost
was adequate or not.
In so far as Schedule I amenities are concerned, it must be observed straightaway that there was no justification for the Rent Controller to arrive
at an ad hoc figure of Rs. 10,000 for being added to the cost of construction. Schedule I amenities also involve capital expenditure. In the instant
case, Schedule I amenities consist of facilities like overhead water supply tank, compound wall, mosaic flooring, electrical motor, pumpset and
open space around v the structures. As already pointed out the whole basis of fixation of fair rent u/s 4 of the Act is to ensure the fair return on the
capital invested by the landlord. Therefore, even so far as Schedule I amenities are concerned, the actual capital cost incurred cannot be said to be
wholly irrelevant. Rs. 10,000 to say the least, is a ridiculous figure to cover these several facilities. Though it may be that the Appellate Authority
was not right in basing the cost of those amenities only on the basis of the extent of the area in the occupation of the tenant, it cannot be said that
the extent of the area is a relevant consideration for the purpose of ascertaining the cost incurred. The larger the plinth or the carpet area, the larger
will be the extent of the facilities and consequently higher will be the cost. In any case, the ad, hoc amount of Rs. 10,000 allowed by the Rent
Controller has no basis whatsoever. The Appellate Authority cannot be said to have erred in working out the allowance of 5 per cent in place of
the ad hoc amount of Rs. 10,000 fixed by the Rent Controller. The total cost has come to Rs. 5,77,504. Ten per cent of this would be Rs. 57,750
and roughly 5 per cent with regard to these amenities would be between Rs. 28,000 and Rs. 29,000 which cannot be said in any case to be
excessive. These were the only substantial questions argued. The other findings of the Appellate Authority are clearly findings of fact. Accordingly,
there is no reason to interfere with the order of the Appellate Authority.
Consequently, all the three revision petitions are dismissed. There will be no order as to costs.
