High CourtsSingle Bench(2018) 02 PAT CK 0109

Chandrika Roy And Ors vs State Of Bihar Through The Principal And Ors

Patna High Court · Decided on 28 February 2018 · Citation: (2018) 2 PLJR 580

HON’BLE JUDGES
Sudhir Singh, J
RESULT
Disposed Of
CASE NUMBER
Civil Writ Jurisdiction Case No. 14930, 14975 Of 2017

AI Structured Summary

Not yet generated for this judgment

Judgment

169 paragraphs · 2,832 words

These two writ applications have been filed, challenging the letters dated 20.09.2017 issued individually to the petitioners by the Estate Officer,

Building Construction Department, Government of Bihar, having the same purport as to vacate and handover the quarters to the Building Construction

Department, which were allotted earlier on 11.12.2015 under Central Pool to the petitioners in the capacity of Minister of the Government of Bihar, as

they do not hold now the office of the Minister, and the permissible period of one month as being prescribed under Patna Central Pool Rules, 1986,

since the cessation of their ministership had already been elapsed. The petitioners have also sought for an alternative relief, seeking direction upon the

respondents for allotments of quarter under Legislative Pool as per their entitlement in terms of the provisions of rule 13 of the Bihar Legislative

Assembly Members Residence Allotment Rules, 2000, with ad-interim protection as to restrain the Building Construction Department from taking any

further step in pursuance to the said letters dated 20.09.2017 until the allotment of quarters are made to the petitioners as per their entitlement.

The brief facts lie within a narrow compass. All the petitioners in both the writ applications were earlier holding the office of the Minister in the

Government of Bihar, and the quarters in question were allotted to them on 11.12.2015 under the Central Pool in the capacity of Minister by the

Building Construction Department, Government of Bihar. Afflux of time, changed the political Scenario in the State of Bihar and a New Coalition

Government came to be formed in the State. The petitioners by virtue of cessation of their ministership, no longer remained in that capacity thus the

letters dated 20.09.2017, made to challenge hereunder, came to be issued as to vacate and handover the quarters in question, to the Building

Construction Department. Now the petitioners are Members of Bihar Legislative Assembly and quarters are allotted to them under the Legislative

Pool in terms of “ Bihar Legislative Assembly Members Residence Allotment Rules, 2000â€. The Building Construction Department has already

made allotment of the quarters in question under Patna Central Pool Rules, 1986, to the various Ministers of the New Coalition Government of the

State of Bihar.

The Respondent Estate Officer, Building Construction Department, issued respective letters to the petitioners bearing different Letter No.(s) dated

20.09.2017 of the same purport for vacating the quarters and handing over its possession to the said department. Thereafter, vide Memo No. 8332-65

dated 26.09.2017, quarters being allotted to the petitioners under the Legislative Pool by the Secretariat of Bihar Legislative Assembly.

These petitioners made representations before the various authorities, raising their grievances that allotment of quarters to them under Legislative Pool

by the Under Secretary, Bihar Legislative Assembly, have not been made as per their entitlement and seniority. They also made request to the

authorities concerned as to make transfer of such quarters being in their occupation, under the Assembly Pool from the Central Pool, so that those

may be allotted to the petitioners. While making such request regarding transfer of quarters for one pool to another, these petitioners set out some

illustrations about the transfer of such quarters from Central Pool to the Legislative Pool being made earlier by the Building Construction Department

in case of some erstwhile Ministers, who were allowed by the respondents to continue in occupation of such quarters, which were allotted to them

under Central Pool in the capacity of Minister and by virtue of transfer, the same converted into Legislative Pool.

The petitioners setting out such practice adopted earlier by the Building Construction Department have made their claim to hold the quarters in

question by way of transfer from Central Pool to the Legislative Pool or till the allotment of quarters are made by the Secretariat of Bihar Legislative

Assembly as per their entitlement and seniority. The representations of the petitioners had been sent by the Secretary of the Bihar Legislative

Assembly to the Principal Secretary, Building Construction Department, Government of Bihar, for needful and necessary action.

A counter affidavit has been filed by the respondent no.3 i.e. Bihar Legislative Assembly contending therein that after coming into force of

Notification No. 74 dated 16.01.2013 contained in Annexure-A/R 3, rule 13 of Bihar Legislative Assembly Members Residence Allotment Rules,

2000, has become inoperative by virtue of the amendment brought under Bihar Vidhan Mandal (Salary, Allowance and Pension of Members) Rules

2006. By the said notification dated 16.01.2013, a sum of Rs. 28,250/- has been made payable to the Members of Bihar Legislative Assembly towards

House Rent and other miscellaneous expenses i.e. Electricity Bill, Water supply, Sanitation etc. The respondents also refuted the allegations of the

petitioners about non- adherence of rule 13 of said “Rule 2000†in the matter of allotment of quarters under the Legislative Pool and thereby the

allotment being not made as per their entitlement and seniority. By way of a supplementary counter affidavit, the Bihar Legislative Assembly

contended that the quarters under Legislative Pool as per entitlement of the writ petitioners are not vacant, and in future, if such quarters are found

vacant, in that case those shall be allotted to the petitioners on priority basis. It was also contended that on account of demolition of quarters in order to

make new construction, there being scarcity of such type of quarters for which the petitioners are entitled to and have claimed for.

The respondent nos. 1 and 2 i.e., the Building Construction Department has also filed a counter affidavit contending that since the petitioners are no

longer Minister of the State Government, so they have to vacate the quarters, which are earmarked under Central Pool for Ministers of the State

Government. The Building Construction Department also contended that the allotment of quarters to the Members of Legislative Assembly alike the

petitioners are not made by it, therefore, it has no obligation to consider the grievance of the petitioners relating to allotment of quarters being not made

as per their entitlement and seniority under Assembly Pool. It was also contended that the quarters in question are of Central Pool of the Building

Construction Department and they have already been allotted to the Minister of New Coalition Government.

The petitioners filed a rejoinder to the counter affidavit of the respondent nos. 1 and 2, stating that they are entitled for “Eâ€​-Type quarters in terms

of the provisions contained in rule 13 of the Bihar Legislative Assembly Members Residence Allotment Rules, 2000, and they are residing in the same

type of quarters. The petitioners further contended that if there has been any scarcity of “ D†and “E†Types quarters, that is solely on

account of arbitrary and illegal allotment made by the respondents to such persons who are not even entitled as such and a large number of “ Eâ€

Type quarters are still laying vacant and have not been allotted to anyone. The petitioners have also filed a supplementary affidavit, contending therein

that in terms of the provisions contained under rule 4 of the Bihar Government Quarters Allotment Administrative Pool Rules, 1996, the State

Government can make transfer the quarters of Administrative Pool to the Patna High Court, Patna, Bihar Legislative Assembly and Bihar Legislative

Council, so that the same may be allotted to the Judges of the High Court, members of Legislative Assembly and the Legislative Council. The

petitioners have made specific averments in paragraph no.8 of the supplementary affidavit, which reads thus:

“8. That the highhandedness and illegal dispossession on the part of the concerned respondent authorities under the State Government would also

be manifest from the fact that a number of quarters belonging to category D and category E have been allotted to Members who are otherwise not

entitled for allotment of such quarters as residence in terms of the provisions contained under rule 13 of the aforesaid Bihar Legislative Assembly

Members Residence Allotment Rules, 2000, description in relation to whom are as follows:

Sl.No. Name Quarters No.

1.

Sri Vidya Sagar Nishad. 12,Veer Chand Patel Path.

2.

Sri Meva Lal Chaudhary. B-3/21, Bailey Road.

3.

Sri Sunil Chaudhary. 3/1, Bailey Road.

4.

Sri Anand Kumar Singh. 1, Mall Road.

5.

Sri Subhash Singh. 21,Harding Road.

6.

Sri Narendra Kr. Singh. 21-M, Strand Road.

7.

Sri Sanjay Singh, M.L.C. 22-M, Strand Road.

8.

Sri Sanjay Singh Gandhi, MLC. 7,Strand Road.

9.

Sri Samir Kumar Mahaseth. 5,Veerchand Patel Path.

10.

Sri Ashok Kumar Singh. 14, Veerchand Patel Path.

11.

Sri Ramvachan Rai. 7-M, Strand Road.

12.

Smt. Reena Yadav. 31/10, Bailey Road.

13.

Sri Rajnish Kumar. 24/10, Bailey Road.

14.

Sri Ranvir Nandan. 36, Harding Road.

15.

Sri Sanjay Jha . 8-M, Strand Road.

16.

Sri Gayanendra Kr. Gyanu. 23, Bailey Road.

The petitioners have also contended towards provisions contained under rule 13 of the Bihar Legislative Assembly Members Residence Allotment

Rules, 2000, which stipulates about entitlement of a person for allotment of “D†and “ E†Types of quarters. It has been stated that by the

impugned letters dated 20.09.2017, the petitioners have been asked to vacate and handover the possession of the quarters in question to the Building

Construction Department, whereas a large number of persons, who are not even entitled to, have been in possession of the quarters belonging to

“D†and “E†Type, but the Department never intend ed to get such quarters vacated from occupation of such disentitled persons. The

petitioners also raised the issue that a number of quarters of “E†Type are laying vacant and the Department has not taken any steps towards the

allotment of such quarters in favour of the persons i.e. Ministers of the New Coalition Government instead of asking the petitioners as to vacate and

handover the quarters. In paragraph 14 of the supplementary affidavit of the petitioners detail of “ E†Type of quarter have been given, which are

still laying vacant, and further stated that the same may be allotted to the Ministers of the newly formed government but in garb of allotment of

quarters of the Central Pool to the newly appointed Ministers, the Building Construction Department has issued impugned letters dated 20.09.2017.

The Building Construction Department in reply to the paragraph no. 8 of the supplementary affidavit of the petitioners, stated that the allotment as

depicted in the said paragraph no. 8 has not been made by the Building Construction Department, and Rule 13 of the Bihar Legislative Assembly

Members Residence Allotment Rules, 2000, has to be followed and implemented by the Bihar Legislative Assembly not by the Building Construction

Department of the State Government.

The respondent no.3 filed a supplementary counter affidavit in reply to the contentions made by the petitioners. There is almost reiteration of the plea

taken in the counter affidavit. In the said affidavit it has been contended that out of 16 persons named by the petitioners, only 9 (nine) are members of

Legislative Assembly and among them Sri Vidya Sagar Nishad at serial no.1 and Sri Sameer Kumar Mahaseth at serial no. 9 have been allotted their

respective quarters, as the Building Construction Department made recommendation in favour of them. In respect of allotment of quarters to the

remaining persons named in paragraph 8 of the supplementary affidavit, there has been various stand taken by the respondent Bihar Legislative

Assembly but nowhere there being contention that such persons have been entitled to the Quarters of “Dâ€​ and “Eâ€​ Types in terms of Rule 13

of the Bihar Legislative Assembly Members Residence Allotment Rules, 2000.

For the sake of convenience and clarity the relevant rules of the Bihar Legislative Assembly Members Residence Allotment Rules are reproduced

hereunder:

“13. :-

() - ( “ â€​)

()

//

â€" “ â€

/

- “ â€​ ।

- ' â€​ /“

- “ â€​

,

-, , -

:

- â€​ / ;

,

. ,

/“ ;

 ( )

14.

-

â€" “ â€

15.

()

()

16.

() ,

() 13 , , ,

() ,

। â€​

Taking into consideration the facts and circumstances in totality as referred above, especially the plea taken by the petitioners that they are entitled for

“ E†Type of Quarter under the Legislative Pool, whereas allotment of quarters by the Secretariat of Bihar Legislative Assembly under the

Legislative Pool, have not been done as per their entitlement and seniority, therefore, they should be allowed to remain in occupation of the quarters in

question, so long as the allotment of quarters be made under the Legislative Pool as per their entitlement in terms of the provisions contained under

Rule 13 of Bihar Legislative Assembly Members Residence Allotment Rules, 2000. I may also take notice of the alternative plea taken by the

petitioners that the quarters in question earlier allotted to them under the Central Pool may be transferred under the Legislative Pool, and in support of

such plea they have set out some illustrations. On the basis of the plea and submissions as noticed above, the petitioners have made prayer as to allow

them to continue in occupation of the quarters in question and also to quash the letters dated 20.09.2017 issued individually to the petitioners by the

Estate Officer, Building Construction Department, Government of Bihar.

In view of the undisputed fact that the petitioners are no longer remained in capacity of Ministers of the Government of Bihar and the quarters in

question earlier allotted to them under the Central Pool by the Building Construction Department have already been allotted to the Ministers of New

Coalition Government and the permissible period of one month prescribed under Patna Central Pool Rules 1986, since the cessation of their

ministership has also been elapsed, therefore, in my considered opinion, the petitioners have no vested or residuary right to remain in occupation of the

Quarters earlier allotted them under the Central Pool in capacity of the Minister of the State Government.

Therefore, the letters dated 20.09.2017 issued individually to the petitioners by the Estate Officer, Building Construction Department, Government of

Bihar, do not require any interference of this Court. However, the petitioners shall be granted 15 days further time by the Building Construction

Department, Government of Bihar, as to vacate the said quarters in question and it shall be incumbent also upon the petitioners to vacate and handover

the quarters within the said period.

Now coming to the next issue and taking note of the plea advanced by the petitioners that a large number of persons who are not even entitled to,

have been in possession of the quarters of “ D†and “E†Types under Legislative Pool on the basis of arbitrary allotment made by the

respondents. In support of the said plea, the petitioners have brought the names of the persons on record who are disentitled under relevant rules to

remain in occupation of the same. I find no specific rebuttal in respect of the contention of the petitioners regarding such arbitrary allotment being

made in de hors of the relevant Rules either by the respondent Building Construction Department or by the Bihar Legislative Assembly. Therefore, in

the ends of justice, the Secretary, Bihar Legislative Assembly is directed to find out such illegal allotment of quarters being made under Legislative

Pool to the persons, who are disentitled for the same and thereafter take necessary steps in accordance with law as to get such quarters vacated in

order to make allotment of the same to the petitioners as per their entitlement. It is made clear that the said exercise must be completed within 60 days

from today. The petitioners will be at liberty to make representation before the concerned authority indicated above, if so advised.

It is also observed that while finding out the issue of disentitlement, unauthorized occupation and illegal allotment in terms of the relevant rules, the

Secretary, Bihar Legislative Assembly shall examine the respective entitlement of the occupants/allottees with reference to the types of quarter. It is

also made clear that inter-se entitlement of the members of Legislative Assembly, who are entitled for the same type of quarter under the relevant

rules, cannot be a subject of such exercise as directed above by this Court for the simple reason that the individual claim of the petitioners regarding

allotment of quarters under Assembly Pool as per their entitlement under the relevant rules has accrued incidentally, on account of cessation of their

ministership with the formation of a New Coalition Government, therefore, this Court deems necessary to restrict the directions made herein above as

not to examine the inter se entitlement of the petitioners with others members of Bihar Legislative Assembly who being entitled for the same type of

quarter under the Assembly Pool, otherwise there would be a possibility to vitiate the earlier allotments of quarter made to the entitled persons even,

which might have been done taking stock of prevalent situation of the relevant time.

In terms of the aforesaid observations and directions, both the writ applications are therefore, accordingly, disposed of.