High CourtsDivision Bench

C.V. George and Company vs Marshall Sons (Manufacturing) Ltd.

Madras High Court · Decided on 8 February 1983 · Citation: (1983) 2 MLJ 525

HON’BLE JUDGES
P. Venugopal, J

AI Structured Summary

Not yet generated for this judgment

Judgment

93 paragraphs · 2,293 words

P. Venugopal, J.—The defendant is the appellant and the plaintiff is the respondent in this appeal. The defendant is a contractor at Cochin

and the plaintiff is a dealer in Hot Mix plant and Mini Crushers. On 6th May, 1971, the defendant sent a letter to the plaintiff asking for quotation

for supply of one hot mix plant. The plaintiff sent a reply on 1lth May, 197l, with all the necessary details. Then the defendant again on 21st June,

1971, asked for a revised quotation from the plaintiff. The revised quotation was sent by the plaintiff on 29th July, 1971. The plaintiff''s case is that

it agreed to deliver the hot mix plant in three to four months'' time from the date of receipt of the order but subject to conditions beyond its control

the hot mix plant could not be supplied earlier than January, 1972. The defendant''s case is that as per the agreement between them, the hot mix

plant should have been supplied by the middle of September, 1971 and time was essence of the contract and the plant was supplied only on 30th

January. l972, and the delay was without any reasonable or probable cause. The further plea of the defendant is that as the hot mix plant was not

delivered within the time stipulated, it is entitled to claim damages under four counts, namely (1) Rs. 2,000 being the cost of 12 volt electrical

starter equipment with battery complete ; (2) Rs. 321.97 being the expenditure incurred towards the cost of materials and labour charges for

welding and rectification of defects before the commission of the plant: (3) Rs. 2,000 being the value of 0.75 ton of steel and (4) Rs. 8,175 being

the hire charges for hiring plant from the Cochin Corporation.

2.

The trial Court held (1) there was no agreement between the parties for delivery of the hot mix plant by the middle of September, 1971, and the

parties did not have intention of making the time essence of the contract; (2) Barring the value of 12 volt electrical starter equipment the other three

claims would amount to plea of set off or counter claim and in this view, the claim for damages in respect of hire charges, expenditure alleged to

have been incurred towards labour charges and alleged shortage in tonnage of steel cannot be gone into; and (3) even if for any reason, it is held

that the amounts claimed under these three counts did not amount to a plea of set off or counter claim, the evidence adduced, has not established

the claim made by the defendant. As regards the value of 12 volt electrical starter equipment, the Court estimated the value at Rs. 500. On these

findings, the trial Court gave a decree in favour of the plain tiff for a sum of Rs. 12,096, and interest at 6% per annum from 27th'' January, 197l, till

the date of plaint and proportionate costs. Against this decree and judgment of the trial Court, the defendant has preferred the present appeal.

3.

Relying on the two decisions of the Supreme Court in Mahabir Prashad Rungta Vs. Durga Datt, and China Cotton Exporters Vs. Beharilal

Ramcharan Cotton Mills Ltd., learned Counsel for the appellant contended that in commercial contracts time is ordinarily of the essence of

contract and under Exhibit A-2, the appellant wrote to the respondent that the machinery should be supplied by the middle of September a t the

latest and the two subsequent letters Exhibit A-6 and A-7 written by the respondent clearly indicate that it is conscious of the deadline and the time

limit fixed under Exhibit A-2 and as time was the essence of the contract, the respondent by not supplying the hot mix plant in the middle of

September, 1971, has committed breach of an important condition of the contract and u/s 59 of the Sale of Goods Act, it is open to the appellant

to treat a breach of condition as breach of warranty and set up against the respondent the breach of warranty in diminution of the price. The

learned Counsel for the appellant further contended that the appellant is entitled to claim by way of damages a total sum of Rs. 12,496 under four

counts as mentioned in paragraph 10 of the judgment of the trial Court and those amounts should go in diminution of the price claimed by the

respondent for the supply of the hot mix plant.

4.

Under Exhibit B-1, the appellant asked for quotation for supply of ones hot mix plant. The respondent replied giving its detailed quotation under

Exhibit B-1. Thereafter, the appellant asked for a revised quotation under Exhibit B-3 to which the respondent replied under Exhibit B-9. Even

before any stipulation came from the appellant regarding time of delivery the respondent under Exhibit B-9 stated that the hot mix plant will be

supplied in about three to four months time subject to conditions beyond its control. The appellant sent a reply under Exhibit A-2. With regard to

time fixed for delivery. The appellant stated under Exhibit A-2 that ''''During the discussion with Mr. C.V. George and your Manager, it was

agreed that the hot mix plant will be made ready by last week of September, whereas in your letter, you have asked for 3-4 months. This point

may be brought to the personal notice of Mr. Kelvakar and arrangements may be made to supply this plant by middle of September at the latest''''.

No reply was sent by the respondent for Exhibit A-2. An analysis of Exhibits B-1 to B-3, B-S and A-2 show (a) the respondent had to supply the

hot mix plant after it is manufactured by its associate company ; (b) even before the appellant stipulated any period for delivery, the respondent

stated in Exhibit B-9 that it would supply the hot mix plant in a bout three to four month''s time subject to conditions beyond its control; and (c)

though the appellant wanted delivery of the hot mix plant in the middle of September, 1971, the respondent did not send any reply agreeing to the

appellant''s stipulation. On the other hand, nearly a month after the time within which the appellant wanted to have the delivery of the plant (that is

middle of September, 1971), the respondent under Exhibit A-6 wrote to the appellant that it has been advised by its associates that the plant will

be ready for delivery in the middle of next month or even earlier and it has requested its associate company to expedite delivery of the machine. On

22nd November, 1971, the respondent again wrote Exhibit A-7 to the appellant stating that in view of the go slow policy adopted by the workers

in the factory for the past one month, it would not be possible for its associate company to deliver the plant by the end of November, and they

would endeavour to supply the plant by 10th December, 1971. It is significant to note that no objection or protest was sent by the appellant to

Exhibit A-6 and A-7 stating that time for performance of the contract was agreed and fixed as middle of September, 1971. On a careful perusal of

the correspondence between the parties as referred to above, it is seen that no time was fixed for performance of the contract. There was

stipulation by the respondent under Exhibit B-9 to deliver the plant in about three to four months'' time from the date of receipt of order Subject to

conditions beyond its control and a suggestion by the appellant under Exhibit A-2 that the point regarding delivery should be brought to the

personal notice of Mr. Kelvakar and arrangements may be made to supply the plant by the middle of September, 1971. Thus, it can be seen that

there was no consensus ad idem regarding the period within which the plant has to be delivered to the appellant. In the absence of any stipulation

fixing the period of delivery of the plant the contract has to be performed within a reasonable time.

5.

The next question to be considered is whether the contract was performed by the respondent within a reasonable time. As already stated, the

respondent has indicated under Exhibit B-9 that it will supply the plant in about 3 to 4 months time from the date of receipt of order subject to

conditions beyond its control. The appellant placed the order or 3lst July, 1971. Three month''s time expired on 30th December, 1971. Even

before the expiry of the period, the respondent wrote Exhibit A-6 the its associate company ha d advised that the plant will be ready for delivery in

the middle of November, and it has advised its associate company to pay special attention and expedite delivery of the plant. The respondent again

wrote under Exhibit A-7 stating that in view of the go-slow policy adopted by the workers in the factory of its associate company, there was a

delay in the manufacture of the plant and it would be supplied before 10th December, 1971. The plant was ultimately delivered to the appellant on

30th January, 1972. Having regard to the time stipulated by the respondent under Exhibit B-9 and having regard to the difficulties faced by its

associate company, the details of which are stated both in Exhibits A-6 and A-9, there is absolutely no difficulty in holding that the respondent has

performed the contract within a reasonable time.

6.

The next question is whether the appellant is entitled to claim set off for the sum of Rs. 12,496. Under the first count, the appellant has claimed

Rs. 2,000 being the cost of 12 volt electrical starter equipment with battery complete, and the trial Court has allowed a sum of Rs. 500 under this

count. The other three claims have been disallowed by the trial Court. The questions for consideration is whether these disallowed claims can be

allowed (a) u/s 59 of the Sale of Goods Act. u/s 55 of the Contract, Act, if, in case of a contract voidable on account of the promisor''s failure to

perform his promisei at the time agreed, the promisee accepts performance of such promise at any time other than that agreed, the promisee

cannot claim, compensation of the promise at the time agreed unless, at the time of such acceptance, he gives notice to the promisor of his insertion

to do so. The essential requirement of Section 55 of the Contract Act is. if the appellant wants to claim compensation for any loss occasioned by

the non-performance of the contract within the stipulated time and if the appellant accepts performance of the contract, he must issue notice to the

respondent of his intention to claim damages. It is therefore clear that if the appellant wants to claim damages by resorting to Section 55 of the

Contract Act he must issue a notice to the respondent of his intention to claim damages at the time when he accepts performance of the contract.

In the instant case, the goods were delivered to the appellant only on 30th January, 1972. Exhibit B-5 was issued by the appellant to the

respondent on 8th December, 1971, which is long prior to the date when the goods were supplied to it and the performance of the contract was

accepted by the appellant. Since Exhibit B-5 was not issued at the time when the appellant accepted the performance of the contract, the appellant

cannot resort to Section 55 of the Contract Act to sustain a claim for damages against the respondent.

7.

The next question for consideration is whether u/s 59 of the Sale of Goods Act, it is open to the appellant to treat any breach of a condition on

the part of the respondent as breach of warranty and set up against the respondent the breach of warranty in diminution of the price. We have

already held that time is not the essence of contract and there is no breach of condition on the part of the respondent. Even granting for argument''s

sake that time was essence of the contract and there was a breach of condition by the respondent, even then Section 59 of the Sale of Goods Act,

cannot be attracted, as the definition of ""condition and warranty"" in Section 12 of the Sale of Goods Act is limited to stipulations in a contract of

sale with reference to goods and stipulations with regard to time and other matters are outside the definition contained in Section 12 of Sale of

Goods Act.

8.

Learned Counsel for the appellant relied on Section 12(2) of the Sale of Goods Act and sought to contend that the stipulation regarding time for

the purpose of contract is essential to the main purpose of the contract and hence a stipulation with regard to time is also a condition with reference

to goods. Sections 13, 14 and 15 of the Sale of Goods Act dealing with condition and warranty, clearly indicate that to constitute a condition

within the meaning of Section 12 of the Sale of Goods Act the condition or stipulation must be with reference to quality of good sand any condition

with regard to time for performance of the contract, is not a condition which falls within the ambit of Section 12 of the Sale of Goods Act. Thus, in

any view of the matter, the appellant cannot, by relying on Sections 12 and 59 of the Sale of Goods Act, set up the alleged breach of warranty in

diminution or extinction of the price claimed by the respondent.

9.

In the result, the decree and judgment of the trial Court are confirmed and the appeal stands dismissed with costs.