High CourtsSingle Bench

DSIIDC vs M/S. H.R. Builders

Delhi High Court · Decided on 11 August 2021 · Citation: (2021) 08 DEL CK 0125

HON’BLE JUDGES
Vibhu Bakhru, J
ACTS & SECTIONS REFERRED
Constitution Of India, 1950 — Article 227 · Arbitration And Conciliation Act, 1996 — Section 23(3), 34
RESULT
Dismissed
CASE NUMBER
Original Miscellaneous Petition (COMM) No. 312 Of 2018, Miscellaneous Application No. 9696 Of 2018, 8035 Of 2021
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

325 paragraphs · 5,307 words

,,,,,

Vibhu Bakhru, J",,,,,

1.

The petitioner (hereinafter “DSIIDCâ€) has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter",,,,,

the “A&C Actâ€) impugning an arbitral award dated 13.04.2018 (hereafter the “impugned awardâ€) rendered by an Arbitral Tribunal,,,,,

comprising of a Sole Arbitrator.,,,,,

2.

The impugned award was rendered in the context of disputes that have arisen between the parties in connection with a contract awarded to HRB,,,,,

for refurbishment and upgradation of twenty-five government schools. The Arbitral Tribunal has rendered a net award of Rs. 3,04,91,623/- along with",,,,,

interest, in favour of HRB.",,,,,

3.

Briefly stated, the relevant facts that are necessary to address the controversy are as under:",,,,,

4.

The Government of NCT of Delhi launched a project for refurbishment and upgradation of 198 schools run by the Government of NCT of Delhi.,,,,,

The respondent (hereinafter “DSIIDCâ€​) was entrusted with implementation of a part of the project covering twenty-five schools.,,,,,

5.

On 08.07.2009, DSIIDC invited tenders for entire works (both civil and electrical) to be executed in respect of twenty-five schools being a part of",,,,,

the project entrusted to DSIIDC. HRB submitted its bid for executing the aforesaid works. After negotiations, DSIIDC accepted HRBâ€s offer to",,,,,

execute the said works for a total consideration of Rs. 35,46,00,174/-. On 18.08.2009, DSIIDC issued a Letter of Acceptance (LoA) awarding the",,,,,

work of “Integrated Infrastructure Development of Delhi Govt. Schools†under the sub-head “Improvement and Upgradation of 25,,,,,

Government Schools Buildings in North West “Aâ€​ District (Composite Work)â€​.,,,,,

6.

The work was to commence on 28.09.2009 and it was stipulated that the work would be completed on or before 27.09.2010.,,,,,

7.

Thereafter, on 30.09.2009, the parties entered into a formal agreement (hereinafter “the Agreementâ€​) for execution of the works.",,,,,

8.

DSIIDC did not handover the work of twenty-five schools as agreed to under the Agreement but handed over work pertaining to only twenty-three,,,,,

schools. There were considerable delays in completion of the works contracted to HRB and, the same were finally completed on 18.01.2012; that is,",,,,,

after a delay of 478 days.,,,,,

9.

DSIIDC withheld part payments of the Final Bill and also made certain recoveries from the amount payable to HRB. According to DSIIDC, HRB",,,,,

had defaulted in performance of its obligations under the Agreement within the stipulated time. HRB disputed the same. According to HRB, the delay",,,,,

in execution of the works was due to various reasons attributable to DSIIDC and it was not responsible for any delay.,,,,,

10.

DSIIDC also claimed that the works executed were faulty and sought to recover damages from HRB. HRB, on the other hand, claimed that it",,,,,

was not only entitled to the payments withheld by DSIIDC but was also entitled to compensation on account of escalation and prolongation of works,,,,,

as well as profits for the works reduced from the scope of the Agreement (work relating to two schools which were not handed over to HRB).,,,,,

11.

In view of the aforesaid disputes, HRB invoked the Arbitration Clause to refer the disputes to arbitration and requested that the Arbitral Tribunal",,,,,

be constituted to adjudicate the disputes. On 24.10.2016, the Chief Engineer of DSIIDC appointed Sh. O.P. Bhatia, Former Additional DG (Works",,,,,

Special), CPWD as the Sole Arbitrator to adjudicate the subject disputes.",,,,,

12.

HRB filed its Statement of Claims before the Arbitral Tribunal. DSIIDC filed its Statement of Defence as well as counter claims amounting to Rs.,,,,,

20,05,00,000/-. One of the claims (Claim No.1) preferred by HRB was greater in value than as indicated by HRB in its request for arbitration, which",,,,,

was subsequently referred by Chief Engineer of DSIIDC to the Arbitral Tribunal. In its request for arbitration, HRB had, inter alia, claimed Rs.",,,,,

53,90,498/- as payment due under the Final Bill. However, in its Statement of Claims, HRB made a claim of Rs. 1,40,94,470/- as due and payable",,,,,

under the Final Bill.,,,,,

13.

In addition, HRB also claimed Rs. 5,00,000/- as costs of arbitration (Claim No.9). The said claim was also not included in the claims that were",,,,,

initially made by HRB in its request for arbitration before the concerned authorities of DSIIDC. Consequently, this claim was also not included in the",,,,,

disputes referred by the Chief Engineer, DSIIDC to the Arbitral Tribunal.",,,,,

14.

In view of the above, on 29.03.2017, HRB sent a letter to the Chief Engineer, DSIIDC requesting it to modify the amount of Claim No.1 from Rs.",,,,,

53,90,498/- to Rs. 1,40,94,470/- and, to also refer the claim relating to costs of the arbitral proceedings quantified at Rs. 5,00,000/-, to the Arbitral",,,,,

Tribunal.,,,,,

15.

In response to the aforesaid request, the Chief Engineer, DSIIDC sent a letter dated 27.06.2017 to the Arbitral Tribunal forwarding HRBâ€s",,,,,

communication requesting that its claim for the enhanced value and its claim for costs be referred to the Arbitral Tribunal and, requested the Arbitral",,,,,

Tribunal to peruse the same and give its “decision/observationsâ€​.,,,,,

16.

The Arbitral Tribunal responded to the said communication vide an e-mail dated 28.06.2017 confirming that the arbitral award would not exceed,,,,,

the amount of claims referred.,,,,,

17.

In view of the above, on 26.08.2017, HRB filed an application under Section 23(3) of the A&C Act praying that it may be permitted to amend",,,,,

Claim No.1 and also claim costs for the arbitration proceedings. On 05.09.2017, DSIIDC filed a reply to the said application opposing the same.",,,,,

18.

The said application was disposed of by the Arbitral Tribunal by an order dated 27.09.2017 allowing HRB to pursue its claim for costs but denying,,,,,

its prayer for considering its Claim No.1 at the enhanced value.,,,,,

19.

Aggrieved by the same, HRB preferred a petition before this Court under Article 227 of the Constitution of India [being CM(M) No.1458/2017",,,,,

captioned “M/s HR Builders vs. DSIIDCâ€]. While the said petition was pending, the Arbitral Tribunal rendered the impugned award.",,,,,

Consequently, on 10.07.2018, HRB withdrew its said petition [CM(M) No.1458/2017] with liberty to agitate its grievance by this petition under Section",,,,,

34 of the A&C Act.,,,,,

20.

Thereafter, HRB filed a petition under section 34 of the A&C Act [OMP (COMM) 324/2018]. The said petition was heard along with the present",,,,,

petition and has been disposed by a separate order rendered today.,,,,,

Claim No.,Claim in brief,"Amount referred

by the C.E.","Amount as per

S.O.C.",Amount awarded,"Re mar

ks

1.,"Payment of

F/bill","53,90,498","1,40,94,470","42,87,422",

2.,"Release of

withheld

amounts and

amount of

illegal

recoveries","1,28,71,710","1,27,96,042","1,12,37,900",

3.,"On a/c of

D.VAT

(W.C.T.)

and labor cess","3,69,490","3,69,490","2,77,117",

4.,"On a/c of

escalatio ns in

the extended

period of

contract","5,10,02,733","3,04,86,958","91,38,560",

5.,"Damages due

to keeping

staff, estt; and

machiner y in

the extended

period","3,32,43,766","3,32,43,766","48,45,700",

6.,"Loss of profit

due to

reduction in

scope of work","67,02,683","67,02,683",NIL,

7.,"Revalida tion

charges of

B.G.s due to

prolonga tion of

contract.","7,97,850","7,97,850",NIL,

8.,"Interest on

delayed

payment s of

RA & F/bills,

withheld

amounts as

well as above

amounts","Amount not

specified","Intt. On withheld

amounts

Rs.1,61,94,

821 + intt. On

other claims @

15%","(i) Intt. On delayed

payment of RA

bills=2,27,42 4

(ii) Intt. @ 8.5%

p.a. on amounts

awarded under

claim nos.1,2&3 as

per details",

9.,"Cost of

arbitration",,"5,00,000+A

.T.‟s fee","2,00,000+2,

77,500

(under section 38(2)

of the A&C Act-

1996)",

,Total,"11,03,78,73

0 + Intt.","11,51,86,08

0 + intt.","Rs.3,04,91,6

23 + intt. On

amounts awarded

under claim

nos.1,2,&3

as per details",

1.,"Loss of name,

reputation of

DSIIDC

and loss

of work

of the DSIIDC","20,00,00,000/-","20,00,00,000/-",NIL,

2.,"Cost of

arbitration","5,00,000/- +

fee and

expenses","5,00,000/- +

fee",NIL,

,Total,"20,05,00,000/-","20,05,00,000/-",NIL,

Reasons and Conclusion,,,,,

32.

The first and foremost question to be examined is whether the impugned award, inasmuch as the Arbitral Tribunal has allowed Claim No.2 of",,,,,

HRB, is without jurisdiction. DSIIDC had withheld/deducted certain sums aggregating Rs. 1,27,96,042/- from the amounts payable to HRB. This",,,,,

included a sum of Rs. 15,54,400/- on account of the amount allegedly paid to PWD for certain works and Rs. 1,04,60,700/- as compensation for delay",,,,,

in completion of the works. The Arbitral Tribunal found that a sum of Rs. 15,54,400/- was withheld to rectify certain defects. According to DSIIDC, it",,,,,

had paid the said amount to PWD for rectifying the defects. The Arbitral Tribunal found that, in fact, DSIIDC had incurred a liability of only 50% of",,,,,

the amount withheld for rectification of the said defects. Accordingly, the Arbitral Tribunal directed that the balance 50% of the said amount, that is, a",,,,,

sum of Rs. 7,77,200/- be paid to HRB as the same was in excess of the liability to cure the defects.",,,,,

33.

Ms Wani has not contested the Arbitral Tribunalâ€s decision to award the amount of Rs. 7,77,200/- in favour of HRB. She confined her challenge",,,,,

to the award of an amount of Rs. 1,04,60,700/-, which was levied as compensation under Clause 2 of the Agreement on account of delay in",,,,,

completion of the works. According to DSIIDC, there was a delay of 478 days in completion of the works out of which HRB was responsible for a",,,,,

delay of 59 days. The Project Director had, accordingly, assessed the compensation at the rate of 1.5% per month of the tendered amount for a period",,,,,

of 59 days. The principal question to be addressed is whether Arbitral Tribunalâ€s decision to award refund of the said amount in favour of HRB is,,,,,

beyond its jurisdiction.,,,,,

34.

The relevant extract of Clause 2 of the Agreement reads as under:,,,,,

“If the contractor fails to maintain the required progress in terms of clause 5 or to complete the work and clear the site on or before the contract,,,,,

extended date of completion, he shall; without prejudice to any right or remedy available under the law to the Government on account of such breach,",,,,,

pay as agreed compensation the amount calculated at the rates stipulated below as the authority specified in schedule 'F' (whose decision in writing,,,,,

shall be final and binding) may decide on the amount of tendered value of the work for every completed day/month (as applicable) that the progress,,,,,

remains below that specified in Clause 5 or that the work remains incomplete.,,,,,

This will also apply to items or group of items for which a separate period of completion has been specified:-,,,,,

(i) Compensation @1.5% per month of delay for delay of work to be computed on per day basis Provided always that the total amount of,,,,,

compensation for delay to be paid under this Condition shall not exceed 10% of the Tendered Value of work or of the Tendered Value of the item or,,,,,

group of items of work for which a separate period of completion is originally given.â€​“,,,,,

35.

It is not disputed that the authority as specified under Schedule “F†of the Agreement is empowered to calculate the compensation payable if,,,,,

the contractor fails to complete the work and clear the site as agreed. The decision of the specified authority in regard to the computation of,,,,,

compensation is final and binding on the parties. Such decision is excluded from the scope of the Arbitration Clause. However, in the present case, the",,,,,

principal dispute between the parties is whether HRB is responsible for the delay in maintaining the required progress and completion of the works,,,,,

within the stipulated period. According to HRB, DSIIDC is responsible for the delay in execution of the works, which included delay in providing the",,,,,

sites and providing necessary drawings. HRB had relied extensively on the hindrance register as well as produced other material to establish that there,,,,,

was no delay on its part in completion of the works in question.,,,,,

36.

HRB had also pointed out that in respect of one of the schools, the assessed hindrance extended to 510 days. DSIIDC has contested HRBâ€s",,,,,

claim by contending that the delay has to be calculated on an overall basis and not with respect to individual items or schools. DSIIDC conceded that,,,,,

the delay of 419 days was not attributable to HRB but claimed that HRB was accountable for the balance 59 days delay. The Arbitral Tribunal,,,,,

accepted DSIIDCâ€s contention that the delay had to be viewed on an overall basis as milestones were also fixed in relation to financial terms and no,,,,,

specified period had been stipulated for separate schools or separate items. However, the Arbitral Tribunal found that there was no justification for",,,,,

levy of compensation as the hindrances in respect of certain schools were removed barely a fortnight before the date of actual completion. The,,,,,

Arbitral Tribunal noted that the last of hindrances in four schools were removed on 04.01.2012, 10.01.2012, 10.01.2012 and 16.01.2012 respectively.",,,,,

The hinderances in question were on account of delay in handing of the sites; yet the work was completed on 18.01.2012. In view of the above, the",,,,,

Arbitral Tribunal found that the levy of compensation was unjustified. In addition to the above, the Arbitral Tribunal also noted that the compensation",,,,,

levied was not assessed with reference to any alleged damage. The actual damage or loss allegedly suffered was also not proved.,,,,,

37.

It is apparent from the impugned award that the Arbitral Tribunal did not engage in any exercise of assessing the quantum of compensation,,,,,

payable in terms of Clause 2 of the Agreement. The Arbitral Tribunal restricted itself to examining whether there was any delay on the basis of which,,,,,

any compensation could be paid.,,,,,

38.

In J.G. Engineers Pvt. Ltd. vs. Union of India (UOI) & Anr.: (supra), the Supreme Court had examined the questions whether an arbitrator was",,,,,

precluded from adjudicating the issue, whether there was any delay on the part of the contractor or the department in view of clauses (2) and (3) of",,,,,

the agreement that was before the Supreme Court in those proceedings. The said clauses are somewhat similar to the relevant clauses in the,,,,,

Agreement. The Court had analyzed the import of those clauses and concluded that, the decision of the specified authority on the question whether the",,,,,

contractor is responsible for the delay is not final and binding. However, the decision of the specified authority on the consequential issues of",,,,,

quantification of compensation is final. The relevant extract of the said decision is set out below:,,,,,

“17. Clauses (2) and (3) of the contract relied upon by the respondents no doubt make certain decisions by the Superintending Engineer,,,,,

and Engineer-in-charge final/final and binding/final and conclusive, in regard to certain matters. But the question is whether Clauses (2)",,,,,

and (3) of the agreement stipulate that the decision of any authority is final in regard to the responsibility for the delay in execution and,,,,,

consequential breach and therefore exclude those issues from being the subject-matter of arbitration. We will refer to and analyse each of,,,,,

the “excepted mattersâ€​ in Clauses (2) and (3) of the agreement to find their true scope and ambit:,,,,,

(i) Clause (2) provides that if the work remains uncommenced or unfinished after proper dates, the contractor shall pay as compensation",,,,,

for every day's delay an amount equal to 1% or such small amount as the Superintending Engineer (whose decision in writing shall be final),,,,,

may decide on the estimated cost of the whole work as shown in the tender. What is made final is only the decision of the Superintending,,,,,

Engineer in regard to the percentage of compensation payable by the contractor for every day's delay, that is, whether it should be 1% or",,,,,

lesser. His decision is not made final in regard to the question as to why the work was not commenced on the due date or remained,,,,,

unfinished by the due date of completion and who was responsible for such delay.,,,,,

(ii) Clause (2) also provides that if the contractor fails to ensure progress as per the time schedule submitted by the contractor, he shall be",,,,,

liable to pay as compensation an amount equal to 1% or such smaller amount as the Superintending Engineer (whose decision in writing,,,,,

shall be final) may decide on the estimated cost of the whole work for every day the due quantity of the work remains incomplete, subject to",,,,,

a ceiling of ten per cent. This provision makes the decision of the Superintending Engineer final only in regard to the percentage of,,,,,

compensation (that is, the quantum) to be levied and not on the question as to whether the contractor had failed to complete the work or the",,,,,

portion of the work within the agreed time schedule, whether the contractor was prevented by any reasons beyond its control or by the acts",,,,,

or omissions of the respondents, and who is responsible for the delay.",,,,,

(iii) The first part of Clause (3) provides that if the contractor delays or suspends the execution of the work so that either in the judgment of,,,,,

the Engineer-in-charge (which shall be final and binding), he will be unable to secure the completion of the work by the date of completion",,,,,

or he has already failed to complete the work by that date, certain consequences as stated therein, will follow. What is made final by this",,,,,

provision is the decision of the Engineer-in-charge as to whether the contractor will be able to secure the completion of the work by the due,,,,,

date of completion, which could lead to the termination of the contract or other consequences. The question whether such failure to",,,,,

complete the work was due to reasons for which the contractor was responsible or the Department was responsible, or the question whether",,,,,

the contractor was justified in suspending the execution of the work, are not matters in regard to which the decision of the Engineer-in-",,,,,

charge is made final.,,,,,

(iv) The second part of Clause (3) of the agreement provides that where the contractor had made himself liable for action as stated in the,,,,,

first part of that clause, the Engineer-in-charge shall have powers to determine or rescind the contract and the notice in writing to the",,,,,

contractor under the hand of the Engineer-in-charge shall be conclusive evidence of such termination or rescission. This does not make the,,,,,

decision of the Engineer-in-charge as to the validity of determination or rescission, valid or final. In fact it does not make any decision of",,,,,

the Engineer-in-charge final at all. It only provides that if a notice of termination or rescission is issued by the Engineer-in-charge under,,,,,

his signature, it shall be conclusive evidence of the fact that the contract has been rescinded or determined.",,,,,

(v) After determination or rescission of the contract, if the Engineer-in-charge entrusts the unexecuted part of the work to another",,,,,

contractor, for completion, and any expense is incurred in excess of the sum which would have been paid to the original contractor if the",,,,,

whole work had been executed by him, the decision in writing of the Engineer-in-charge in regard to such excess shall be final and",,,,,

conclusive, shall be borne and paid by the original contractor. What is made final is the actual calculation of the difference or the excess,",,,,,

that is, if the value of the unexecuted work as per the contract with the original contractor was Rs. 1 lakh and the cost of getting it executed",,,,,

by an alternative contractor was Rs. 1,50,000 what is made final is the certificate in writing issued by the Engineer-in-charge that Rs.",,,,,

50,000 is the excess cost. The question whether the determination or rescission of the contractor by the Engineer-in-charge is valid and",,,,,

legal and whether it was due to any breach on the part of the contractor, or whether the contractor could be made liable to pay such",,,,,

excess, are not issues on which the decision of Engineer-in-charge is made final.",,,,,

18.

Thus what is made final an conclusive by Clauses (2) and (3) of the agreement, is not the decision of any authority on the issue whether the",,,,,

contractor was responsible for the delay or the Department was responsible for the delay or on the question whether termination/rescission is valid or,,,,,

illegal. What is made final, is the decisions on consequential issues relating to quantification, if there is no dispute as to who committed breach. That is,",,,,,

if the contractor admits that he is in breach, or if the arbitrator finds that the contractor is in breach by being responsible for the delay, the decision of",,,,,

the Superintending Engineer will be final in regard to two issues. The first is the percentage (whether it should be 1% or less) of the value of the work,,,,,

that is to be levied as liquidated damages per day. The second is the determination of the actual excess cost in getting the work completed through an,,,,,

alternative agency. The decision as to who is responsible for the delay in execution and who committed breach is not made subject to any decision of,,,,,

the respondents or its officers, nor excepted from arbitration under any provision of the contract.",,,,,

19.

In fact the question whether the other party committed breach cannot be decided by the party alleging breach. A contract cannot provide that one,,,,,

party will be the arbiter to decide whether he committed breach or the other party committed breach. That question can only be decided by only an,,,,,

adjudicatory forum, that is, a court or an Arbitral Tribunal.â€​",,,,,

39.

Further, the Supreme Court had also referred to its earlier decision in State of Karnataka v. Shree Rameshwara Rice Mills, Thirthahalli: (1987) 2",,,,,

SCC 160, wherein the Court had observed as under:",,,,,

“7. … Even assuming for argumentâ€s sake that the terms of Clause 12 afford scope for being construed as empowering the officer of,,,,,

the State to decide upon the question of breach as well as assess the quantum of damages, we do not think that adjudication by the officer",,,,,

regarding the breach of the contract can be sustained under law because a party to the agreement cannot be an arbiter in his own cause.,,,,,

Interests of justice and equity require that where a party to a contract disputes the committing of any breach of conditions the adjudication,,,,,

should be by an independent person or body and not by the other party to the contract. The position will, however, be different where there",,,,,

is no dispute or there is consensus between the contracting parties regarding the breach of conditions. In such a case the officer of the,,,,,

State, even though a party to the contract will be well within his rights in assessing the damages occasioned by the breach in view of the",,,,,

specific terms of Clause 12.,,,,,

8.

We are, therefore, in agreement with the view of the Full Bench that the powers of the State under an agreement entered into by it with a",,,,,

private person providing for assessment of damages for breach of conditions and recovery of the damages will stand confined only to those,,,,,

cases where the breach of conditions is admitted or it is not disputed.â€​,,,,,

40.

The decision of the Supreme Court in M/s. Mitra Guha Builders (India) Company v. Oil and Natural Gas Corporation Limited: (supra) was,,,,,

rendered in the context of a clause, which empowered the Superintending Engineer to decide on the contract value for the whole week where the",,,,,

work remained un-commenced and unfinished. It also provided milestones of the work to be followed and provided the proportion of the work to be,,,,,

completed in case the time allowed for completing the work exceeded one month. In the context of the said clause in that question, the Supreme Court",,,,,

found that it provided a complete mechanism for determination of liability as well as its quantum and therefore, held that the same was beyond the",,,,,

scope of the arbitration clause in that case.,,,,,

41.

As noticed above, Clause 2 of the Agreement in this case is somewhat similar to the clause as considered by the Supreme Court in J.G. Engineers",,,,,

Pvt. Ltd. v. Union of India (UOI) & Anr. (supra).,,,,,

42.

Having stated the above, it is also important to note that before the Arbitral Tribunal, DSIIDC did not raise any question regarding the jurisdiction",,,,,

of the Arbitral Tribunal to entertain Claim No.2. The said claim was specifically referred to the Arbitral Tribunal without any reservation by the CE,",,,,,

DSIIDC. This Court has also examined the Statement of Defence filed by DSIIDC and there is no averment to the effect that the determination of,,,,,

liability under Clause 2 of the Agreement is an excepted matter. On the contrary, DSIIDC had joined the controversy as to whether the compensation",,,,,

as recovered was leviable. Even before this Court, DSIIDC has not made any averment in the present petition to challenge the decision of the Arbitral",,,,,

Tribunal allowing HRBâ€​s Claim No.2 as being without jurisdiction or on the ground that the said claim was not arbitrable. There is no averment to the,,,,,

effect that the said dispute (claim) adjudicated by the Arbitral Tribunal falls is an “excepted†matter. The contention advanced by Ms Wani is,,,,,

clearly an afterthought and, not supported by pleadings. In this view as well, it would not be apposite to permit DSIIDC to question the jurisdiction of",,,,,

the Arbitral Tribunal at this stage.,,,,,

43.

Considering the above, this Court is unable to accept that the Arbitral Tribunalâ€s decision to award a sum of Rs. 1,04,60,700/-recovered by",,,,,

DSIIDC on account of delay in execution of the works, warrants any interference in these proceedings.",,,,,

44.

The next question to be examined is whether the Arbitral Tribunalâ€s decision to allow HRBâ€s claim for labour cess at the rate of 1% and,,,,,

DVAT at the rate of 3% of the amount of work done, is patently illegal.",,,,,

45.

Ms Wani contended that the said amounts were included in the rates quoted and the Arbitral Tribunal has committed an error in awarding the,,,,,

same over and above the said rates. She submitted that awarding the said amount has effectively subverted the tendering process as there may have,,,,,

been bidders, who would have included labour cess and DVAT in the price bid by them for executing the works in question. The said contention is",,,,,

misconceived. HRBâ€s claim was restricted to recovery of labour cess and DVAT on deviated items. Obviously, these were items, which were not",,,,,

part of the bid as submitted by HRB. HRB had submitted its analysis of rates for payment of deviated items. DSIIDC made payments for these,,,,,

deviated items on the basis of the analysis of rates as approved. However, it also recovered labour cess at the rate of 1% and DVAT at the rate of",,,,,

3% from such payments. HRB raised a claim regarding the said levies as it claimed that the same did not form a part of the rates approved for the,,,,,

deviated items.,,,,,

46.

The Arbitral Tribunal had examined the material on record and had found that labour cess and DVAT were required to be included in the analysis,,,,,

of rates. The Arbitral Tribunal drew support from the fact that the CPWD Manual also requires such levies to be included in the rates. The Arbitral,,,,,

Tribunal accepted that the same did not form a part of the approved rates and therefore, allowed HRBâ€s claim in this regard. Clearly, the said",,,,,

decision warrants no interference in these proceedings. The decision of the Arbitral Tribunal is well reasoned. It is based on material placed on record,,,,,

and the same cannot be faulted. In any view of the matter, the said decision cannot be considered as either patently illegal or violative of the",,,,,

fundamental policy of Indian law.,,,,,

47.

The contention that the escalation awarded in favour of HRB (HRBâ€s Claim No.4) is patently illegal, is also unpersuasive. It was contended by",,,,,

Ms Wani that the escalation award is contrary to Clause 10CC of the Agreement. However, it is seen that it was DSIIDCâ€​s case before the Arbitral",,,,,

Tribunal that Clause 10CC is not applicable to the contract in question since the works were to be completed within 12 months. The Arbitral Tribunal,,,,,

had also noted DSIIDCâ€​s contention to the effect that Clause 10CC does not form a part of the Agreement.,,,,,

48.

Before the Arbitral Tribunal, it was contended on behalf of DSIIDC that Clauses 10C and 10CA of the Agreement were applicable and the",,,,,

escalation was to be paid under the said clauses but HRB has not raised bills under the said clauses. The Arbitral Tribunal found that HRB had raised,,,,,

one bill under Clause 10CA for a sum of Rs. 16,03,271/-, but that too was not paid. It had sent letters regarding escalation. However, DSIIDC did not",,,,,

call upon HRB to raise claims under the said clauses.,,,,,

49.

The Arbitral Tribunal further reasoned that the time allowed for the completion of the works was twelve months but there was an inordinate delay,,,,,

of 478 days. The Arbitral Tribunal observed that in the competitive bidding system, no contractor could cushion his quoted rates to cater to such",,,,,

extended period. The Arbitral Tribunal also held that since major part of the delays resulting in prolongation were attributable to DSIIDC, HRB was",,,,,

entitled to escalation.,,,,,

50.

This Court finds no fault in the aforesaid reasoning. The contention that the Arbitral Tribunal has erred in applying cost indices by CPWD instead,,,,,

of cost indices for commodities issued by the Economic Bureau, is also unsubstantial. Clause 10CA of the Agreement, contemplates that increase and",,,,,

decrease in prices would be determined on the basis of the All India Wholesale Price Indices of Materials as published by the Economic Advisor to,,,,,

the Government of India, Ministry of Commerce and Industry. However, it is pointed out that escalation calculated on the basis of such indices would",,,,,

be higher than that allowed by the Arbitral Tribunal. The Arbitral Tribunal had considered the indices adopted by DG, CPWD to be more appropriate",,,,,

and accordingly, moderated the amount claimed by HRB. Considering that time for completion of the works had far acceded the initial period as",,,,,

contemplated under the Agreement, the Arbitral Tribunalâ€s decision to award escalation on the basis of indices published by DG, CPWD cannot be",,,,,

held to be perverse or unreasonable. This Court is unable to accept that the same is patently illegal and warrants interference in these proceedings.,,,,,

51.

The contention that the Arbitral Tribunal had committed a patent error in awarding Rs. 48,45,700/- as overheads on account of prolongation of",,,,,

works, is unmerited. The Arbitral Tribunal had awarded the said amount to compensate HRB for its overheads expenses by using the widely accepted",,,,,

Hudson Formula. The Arbitral Tribunal found that HRB was required to be compensated for the prolongation of works on account of overheads,,,,,

incurred by it during the extended period. Although HRB had claimed a sum of Rs. 3,32,43,766/- on account of prolongation of works, the Arbitral",,,,,

Tribunal had moderated it significantly by applying the Hudson Formula. The view taken by the Arbitral Tribunal is a plausible view. This Court finds,,,,,

no patent illegality in the said award and thus, finds no reason to interfere with the same.",,,,,

52.

Ms Wani had also contended that the award of interest and costs is exorbitant. The said contention is bereft of any merit. There is no prohibition,,,,,

for grant of interest and the interest rate of 8.5% per annum cannot be stated to be exorbitant or patently illegal.,,,,,

53.

Ms Wani had also sought to assail the Arbitral Tribunalâ€s decision to reject DSIIDCâ€s counter claim of Rs. 20 crores on account of loss of,,,,,

name, reputation and loss of work. However, this Court finds no infirmity with the decision of the Arbitral Tribunal to do so. The Arbitral Tribunal had",,,,,

noted that DSIIDC had not raised any such claim at the material time nor had it asserted that it had incurred any loss. The Arbitral Tribunal,",,,,,

accordingly, observed that the counter claim was raised as a counterblast to the arbitration invoked by HRB. There was no evidence of DSIIDC",,,,,

suffering any direct loss and the calculation submitted by it was hypothetical.,,,,,

54.

This Court finds that there is no material to establish that DSIIDC had suffered any loss attributable to HRB.,,,,,

55.

In view of the above, the petition is dismissed. All pending applications are also disposed of.",,,,,