AI Structured Summary
Not yet generated for this judgment
Judgment
Rajendra Menon, CJ
CM APPLs. 3864/2019 & 4525/2019
Both these applications have been filed in W.P.(C) No.1565/2015 Electrosteel Castings Limited & Anr. vs. Union of India & Anr. decided by a Co-
ordinate Bench of this Court on 09.03.2017.
Various writ petitions including W.P.(C) No.1565/2015 were filed challenging the provisions of Section 16 of the Coalmines (Special Provisions)
Second Ordinance, 2014 which was subsequently replaced by the Coalmines (Special Provisions) Act, 2015 and Rule 14 of the Coalmines (Special
Provisions) Rules, 2015. All the writ petitions were heard and decided by a common judgment, wherein the constitutional validity of the provisions was
upheld. It was held that Section 16 of the said Ordinance and Rule 14 of the Rules are to be interpreted and worked-out in the manner indicated in the
judgment; and that they cannot be held to be violative of Articles 14, 19(1)(g) and 300A of the Constitution. The manner of assessment of
compensation payable on various heads, i.e., for the land value and the mine infrastructure, etc. were to be determined in accordance to certain
observations made and directions contained in the judgment. Liberty was granted to each of the petitioners to raise disputes with regard to the
quantum of compensation if the same is not done in accordance to the indication made in the judgment, either before the Tribunal which has been
specifically created for this purpose under Section 27 of the impugned act or in accordance with law before the appropriate forum.
After the petition was disposed of, it seems that assessment of compensation was not done and therefore CM No.4201/2017 was filed by the
petitioners herein, namely, Electrosteel Castings Limited & Anr. and on 15.02.2017, whereupon the respondents were directed to reconsider the
valuation and assessment of land value and mine infrastructure in the Parbatpur Central Coal Mines within six weeks.
It was thereafter alleged that the six weeks period expired on 30.03.2017; and since no action was taken by the respondents in terms of the order
passed, therefore another application CM No.18977/2017 was filed by the petitioners complaining of non-compliance with the order passed on
15.02.2017. On this application, on 19.05.2017, respondents were granted eight weeks time to take a final view in the matter and the petitioners were
directed to re-furnish data within one week of 19.05.2017. The said eight weeks period also expired on 14.07.2017; and it was then alleged that the
respondents failed to comply with the order passed on 19.05.2017 despite repeated reminders by the petitioner. Accordingly, CM No.3840/2018 was
filed by the petitioners on 31.01.2018 on account of non-compliance. The matter was adjourned to 12.02.2018 at the request of the respondents. Since
no action was taken by the respondents, on 12.02.2018 it is said, and the order also indicates, that brief submissions were handed over by the
respondents seeking further three months time to comply with the previous orders of the Court. The respondents were therefore directed to consider
the information to be provided by the petitioner as per the new format, which is said to have been introduced by the respondents on 01.02.2018 at the
earliest and to expedite the decision making process. The matter was directed to be listed on 19.04.2018 when a status report was to be filed.
On 19.04.2018, the status report was filed by the respondents and a further period of three months was sought which was granted and the matter
was directed to be listed on 29.08.2018. Even though the three months period expired on 19.07.2018, it is said that the respondents failed to comply
with the orders passed.
On 29.08.2018, this Court directed for listing of the matter on 10.09.2018 and further directed the respondents to file an affidavit inter alia indicating
the procedure followed for assessment of compensation in terms of the order passed on 09.03.2017.
On 07.09.2018, CM No.36876/2018 was filed by the respondent stating that it was expected that the exercise as directed by this Court would take a
further period of three months to complete. This application was taken-up on 10.09.2018 and this Court directed that the decision be now taken within
three months from the date of the order, failing which this Court would consider taking coercive action against the respondents for violating the orders
passed by this Court from time-to-time. The period of three months expired on 10.12.2018. It is said that no compliance was made within the time
stipulated. Thereafter CM No.3864/2019 was filed by the respondents on 05.01.2019 seeking a further period of two months to comply with the
previous orders passed by this Court. This application was taken-up for consideration by the Court on 25.01.2019 but on that day as the Court could
not assemble, the case was adjourned to 19.02.2019. In the meanwhile, petitioners also filed CM No.4525/2019 seeking implementation of all the
orders including the order passed on 10.09.2018.
Both these applications i.e. CM No.3864/2019 for extension of time and CM No.4525/2019 were taken-up by the Court on 30.01.2019, on which
date this Court observed that the respondents have delayed the matter since 15.02.2017 and directed that the officer concerned responsible for taking
action in the matter should remain present in the Court on 19.02.2019. It was also observed that in case the order is complied with and a compliance
report is filed on or before 19.02.2019, the officer would be granted exemption from personal appearance.
On 18.02.2019, an affidavit was filed by the respondents in purported compliance of the order passed on 30.01.2019, just a day before the date of
hearing i.e. 19.02.2019 and along with the affidavit a decision dated 15.02.2019 rendered by the nominated authority was brought on record.
It was stated in the affidavit that the decision has been taken on 15.02.2019.
In relation to the determination of compensation for land and mine infrastructure payable to the petitioner, the prior allottee, and after providing the
revised valuation of compensation in para 8 of the order it was indicated that in case the prior allottee, namely the petitioner or the present allottee of
the coalmine namely M/s Steel Authority of India Limited, had any objection they were directed to appear and were given an opportunity of hearing on
25.02.2019 at 11:00 a.m., when they could present their objections for consideration. It was also indicated that it is open to them to raise any dispute
with regard to the quantum of compensation before the Tribunal. According to the petitioner, this was the tentative compensation assessment and the
final assessment was to be done only after the objections were considered at the hearing to be concluded on 25.02.2019.
On 19.02.2019, this Court took on record the affidavit filed on 18.02.2019; the matter was posted for 07.03.2019; and exemption from personal
appearance of the officer was also granted.
It is stated that in pursuance to the notice given while passing the order on 15.02.2019 the petitioners appeared before the authority concerned on
25.02.2019 and submitted their preliminary objections to the effect that the documents relied upon by the nominated authority while taking its decision
on 15.02.2019 were not provided to the petitioner; and petitioners claimed their right to receive all documents and further indicated that they would file
detailed objections once such documents are supplied to them. However, on 25.02.2019 the hearing was adjourned since Steel Authority of India
stated that they were not prepared and sought further time. Thereafter, on 27.02.2019, the hearing was again adjourned at the request of Steel
Authority of India. When petitioner again sought copies of documents from the nominated authority based on which the decision was taken on
15.02.2019, the proceedings of 27.02.2019 which are available on record indicate that the petitioner was informed that the same would be handed-over
on the next date of hearing i.e. 06.03.2019. However, on 05.03.2019, a day before the date of hearing, petitioner was informed via e-mail that no
hearing before the nominated authority would be held on 06.03.2019.
The matter was adjourned indefinitely and it was informed that the next date of hearing would be intimated. When the case was taken up by this
Court on 07.03.2019, this Court posted the matter for hearing on 26.03.2019 in order to enable the petitioners to file their response to the affidavit
dated 18.02.2019 filed by the respondents. The matter was posted for 26.03.2019. On 26.03.2019, petitioners filed reply to the affidavit dated
18.02.2019; raised objection to the decision dated 15.02.2019 and it was their contention that the decision is not in compliance with the order passed on
10.09.2018 or the original order passed in the writ petition. Respondents contended that it was only an interim decision and no final decision had been
taken.
However, on 26.03.2019 the Court could not assemble and the matter was adjourned to 16.04.2019. On a mention made on 27.03.2019, the matter
was directed to be listed on 08.04.2019; and on 08.04.2019, at the request of parties the matter was directed to be listed on 12.04.2019.
However, it is the case of the petitioner that on the same day, i.e., 08.04.2019 petitioner received an e-mail from the nominated authority informing
them that the next date of listing before the nominated authority is 10.04.2019, on which date the petitioner was directed to appear. Petitioner is said to
have made a request on the same day by pointing-out that this Court has listed the case for considering the objection to the decision dated 15.02.2019
on 12.04.2019 and therefore hearing before the nominated authority on 10.04.2019 be adjourned. It is said that in spite of this on 10.04.2019 the
nominated authority closed the matter on the ground that any adjournment would amount to contempt of court; and gave its final decision on
11.04.2019 by passing a detailed order a copy of which was submitted before this Court.
When the matter was taken up on 12.04.2019 the petitioners pointed-out all the facts and sought time to bring on record their objections with
regard to the manner in which the decision was taken. This was permitted and on 30.04.2019 the petitioners filed objections and documents to show
infirmities in both the decisions, namely, the first decision taken on 15.02.2019, the final decision taken on 11.04.2019; attempting to demonstrate how
proper consideration has not been made; the documents requested by the petitioners were not provided and how in a hasty manner the entire decision
was taken only to show to this Court that a decision has been taken. In reply to these submissions, the respondents have also filed their affidavit; and
by referring to the detailed orders passed they have indicated that now, as both the tentative and the final decisions have been taken, all objections and
submissions made by the petitioners have been considered, they have been dealt-with in the order in seriatim; and now the only remedy available to
the petitioner is to challenge the action before the appropriate specified Tribunal under the statute and the matter be now disposed of.
We have heard the matter at length on various dates and have considered the submissions made with regard to the decisions taken by the
nominated authority as indicated hereinabove, namely, the first decision on 15.02.2019 and the final determination on 11.04.2019.
The contention of the petitioners represented by Shri Akhil Sibal, learned Senior Advocate, Shri Pushpinder Kaurav, learned Senior Advocate with
Shri Gaurav Juneja, learned counsel are that considerations have not been made in accordance to the mandate of the directions and the observations
made in the original order passed in the writ petition and the observations made by this Court on 10.09.2018. The assessment of land value based on
circle rates and documents like sale deed have not been done in a proper manner. The value of mine infrastructure has not been calculated properly;
and even though claims have been made under various heads, compensation has not been assessed properly. Detailed submissions were made to
demonstrate before us, as to how and in what manner, an arbitrary assessment of compensation has been done.
Per contra, Ms. Maninder Acharya, learned Addl. Solicitor General assisted by Shri Kirtiman Singh, learned Standing Counsel refuted the
contentions, took us through the order passed on 15.02.2019 in detail, the written objections brought on record by the petitioner, their considerations
made in the order passed on 15.02.2019, the final decision taken on 11.04.2019; and tried to indicate that all the objections were considered when the
decision was taken on 15.02.2019. It was submitted that there being no material or evidence to take a different view subsequently, the same view that
was originally taken on 15.02.2019 has been affirmed; and once the nominated authority in accordance with the statute has taken a decision, the
petitioner should challenge the same before the statutory appellate forum, namely, a Tribunal created for the same; and that this Court should not
make any further indulgence in the matter.
It is the case of the petitioners that from the narration of facts as detailed by them hereinabove, right from 09.03.2017 after the original petition
was decided and thereafter from 15.02.2017 when CM No.4201/2017 was disposed of granting six weeks time to the respondents to take a decision,
the respondents have been delaying the matter for more than two years; and it was only when this Court started taking coercive action by directing for
appearance of the officer concerned on 30.01.2019 that, in a hurried manner within 15 days, initially on 15.02.2019 and thereafter on 11.04.2019
without granting proper opportunity or time and without supplying all the documents as claimed for including the land evaluation report, CMPDI report,
etc. a decision has been taken. In these circumstances the prayer made before us is that both the decisions taken on 15.02.2019 and 11.04.2019 be
set-aside and the matter be remanded back to the nominated authority, with a direction to supply all the documents, give a proper opportunity of
hearing and thereafter take a decision.
Ms. Maninder Acharya, learned Addl. Solicitor General submitted that full opportunity has been granted, detailed orders have already been passed
and now when a statutory remedy of appeal before a nominated Tribunal is available, exercise of extraordinary jurisdiction by this Court is not called
for.
We have considered the rival contentions and have gone through the records. We find that originally, when the writ petition was decided and
thereafter on 15.02.2017 and on various dates including on 10.09.2018, this Court had directed that a decision be taken by the nominated authority by
issuing certain observations and directions. For more than two years and two months nothing was done; and it was only after this Court took a serious
view of the matter and initiated coercive steps on 30.01.2019 that the first decision was taken within 15 days on 15.02.2019; and in this decision the
petitioners and Steel Authority of India were granted an opportunity to appear for hearing and file their objections on 25.02.2019. On 25.02.2019, and
even before that, the petitioners submitted their preliminary objections, reserved their right to file detailed objections and sought for various documents
and material; however because of requests made by Steel Authority of India the matter was adjourned to 27.02.2019. On 27.02.2019, again at the
instance of Steel Authority of India the matter was adjourned. No hearing took place on 06.03.2019; and proceedings were adjourned; and when the
matter was fixed by this Court on 12.04.2019, it seems on 10.04.2019 a hearing was fixed; request of the petitioner for adjournment was rejected; and
immediately on the next date i.e. on 11.04.2019 a final decision was taken.
Even though as canvassed by Ms. Maninder Acharya, learned Addl. Solicitor General the petitioner’s have a right to assail all these actions
before the nominated statutory Tribunal by way of an appeal but the fact remains that in this case a decision has been taken in a hurried manner and
the procedure followed, as detailed by us hereinabove, does indicate that a reasonable and fair opportunity to the petitioner to put-up their objections
and relevant material have not been afforded. That being so, we are of the considered view that once the respondents were themselves responsible
for the delay of more than two years in taking a decision, a reasonable prayer made by the petitioners for providing them certain documents and
granting them time to file detailed objections should have been acceded to; and the decision taken in such a hurried manner is not proper. We need not
go into the details, or the reasoning and the justification given by the respondents for assessment of the compensation at this stage and approve or
reject it. We are satisfied that the decision was taken in a hurried manner; and the haste in which the proceedings were held did result in prejudice to
the petitioners. That being the position, we are of the considered view that interests of justice would be met if the orders passed by the respondents
are set aside and the matter is remanded back to the nominated authority, to proceed in accordance with law and take a decision afresh.
Accordingly, we hold and direct that the first decision taken on 15.02.2019 and the second decision (final determination done) on 11.04.2019,
having been taken without granting due opportunity to the petitioners, are set-aside.
The petitioners shall appear before the nominated authority on 17.06.2019, file their objections as they may be advised; they may also file
applications seeking documents or any other information as permissible in law; and the nominated authority, after considering their objections and the
request for supply of documents or information, after hearing all concerned including Steel Authority of India or any other authority, and after granting
such personal hearing as may be required in the facts and circumstances, take a final decision in the matter on or before 31st August, 2019.
Needless to emphasize that we have not expressed any opinion on the merits with regard to assessment of compensation or its quantification. We
have simply remanded the matter back for fresh determination as we are of the considered view that proper opportunity of hearing, as is required, was
not afforded to the petitioners.
