High CourtsSingle Bench

Francis Parkash Mathur And Anr vs Suridhi Infracon Private Limited

Delhi High Court · Decided on 28 November 2018 · Citation: (2018) 11 DEL CK 0253

HON’BLE JUDGES
Navin Chawla, J
ACTS & SECTIONS REFERRED
Arbitration and Conciliation Act, 1996 — Section 17, 34
RESULT
Dismissed
CASE NUMBER
Original Miscellaneous Petition 379 Of 2012
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

93 paragraphs · 1,971 words
1.

This petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) has been filed by the

petitioners challenging the Arbitral Award dated 16.01.2012 passed by the Sole Arbitrator adjudicating the disputes that have arisen between the

parties in relation to the Collaboration Agreement dated 02.09.2004 executed between the parties.

2.

The petitioners, as owners of property bearing no. F8/2 Vasant Vihar, New Delhi, had entered into the Collaboration Agreement with the

respondent, who was the builder, for the purpose of re-development of their property. As certain disputes arose between the parties in relation to the

said Collaboration Agreement, the same were referred to the Sole Arbitrator resulting in the Impugned Award.

3.

The learned counsel for the petitioners submits that the Arbitrator has erred in rejecting the claim of the petitioners for Damages for delay in

handing over of the possession of the property upon its re-development by the respondent to the petitioners. He submits that in terms of the

Collaboration Agreement, the construction of the property was to be completed within twelve months of handing over of the possession of the same

by the petitioners to the respondent. Such possession was handed over by the petitioners to the respondent on 14.09.2004, however, admittedly, the

possession of the property was given by the respondent to the petitioners upon its re-development only on 14.12.2005, that is, beyond the period

prescribed in the Collaboration Agreement. He submits that in terms of the Collaboration Agreement, incase of such delay in handing over of the

possession, the respondent was to pay penalty of Rs. 5,000/- per day to the petitioners for the period of such delay. He submits that the Arbitrator has,

therefore, erred in not granting the claim of the petitioners for such damages on account of delay.

4.

I have considered the submissions made by the learned counsel for the petitioners. At the outset I would quote clauses of the Collaboration

Agreement relied upon by the learned counsel for the petitioners:-

“That the Builder undertake to complete the proposed building within a period of 12 months from the date of handing over of vacant possession

from the Owners to the Builder, subject to FORCE MAJEURE and further if delay is occasioned for any reason of any act or legislation or restriction,

prohibition or restrained imposed by any Statutory Body and or Governmental Authority, no liability shall attach to the Builder.

xxx

That in case the Builder fails to complete the construction of the proposed building within the above stipulated period, then the Builder shall be liable to

pay a penalty to the tune of Rs. 5,000/- (Rupees five thousand only) per day to the Owners.â€​ (Emphasis supplied)

5.

The Arbitrator, in the Impugned Award has found that the construction of the property was completed and the completion certificate was obtained

by the respondent on 04.08.2005, that is, within the period of twelve months from the date of handing over of the possession by the petitioners to the

respondent. The Arbitrator further found that the above mentioned Clauses of the Collaboration Agreement applied only to the construction of the

building and therefore, would not be applicable where, though the construction has been completed on time, the possession was not delivered by the

respondent to the petitioners due to certain other disputes.

6.

I am in agreement with the finding of the learned Arbitrator and therefore, do not find any force in the contention raised by the learned counsel for

the petitioners. The above referred Clauses clearly apply only to the completion of construction of the re-developed building. Admittedly, such

construction had been completed within the prescribed period of twelve months from the handing over of the possession by the petitioners to the

respondent and therefore, the above referred Clauses of the Collaboration Agreement would have no application. If the handing over of the possession

of the re-developed building after its construction was delayed by the respondent, the same had to be separately proved by the respondent. Any

consequential damages caused to the petitioners thereby had also to be separately proved by the petitioners by leading evidence in that regard. The

petitioners did not lead any evidence on their claim for damages and merely relied upon the above Clauses of the Collaboration Agreement. Therefore,

the Arbitrator has rightly rejected the said claim of the petitioners.

7.

The learned counsel for the petitioners further submitted that the Collaboration Agreement provided for only one lift for the second floor of the

property, which fell in the share of the petitioners. However, the respondent constructed the second lift for the first floor, which fell in the share of the

respondent. The petitioner had therefore, claimed cost of the additional area occupied by this second lift, however, the Arbitrator has wrongly rejected

the same by relying upon the legal notice dated 22.08.2005 addressed on behalf of the petitioners to the respondent.

8.

I have considered the submissions made by the learned counsel for the petitioners, however, again find no merit in the same. The Arbitrator in his

Impugned Award has found that the second lift was installed by the respondent without the consent of the petitioners, however, the petitioners later

consented to the same and demanded certain works to be carried out by the respondent in the property. As there was no complaint about the said

works having not been carried out by the respondent, the petitioners cannot now turn around and make a grievance regarding this lift.

9.

I am in agreement with the view taken by the learned Arbitrator. The petitioner no.1 vide his letter dated 27.07.2005 had protested against the

proposed construction of the lift for the first floor and called upon the respondent to cease and desist from installing the same. However, from the

subsequent letter dated 10.08.2005 and the legal notice dated 22.08.2005 it becomes apparent that the petitioners requested the respondent toÂ

carry out certain specified works in the property as a condition for allowing the respondent to install the said lift. As noted by the

Arbitrator and not denied even before me, there is no grievance made by the petitioners that such additional work was not carried out by the

respondent. The petitioners having taken advantage of such additional works from the respondent, cannot now be allowed to sustain a claim against

the construction of the said lift.

10.

The final challenge of the petitioners to the Impugned Award is to the refusal of the Arbitrator to grant damages for the sub-standard construction

of the basement by the respondent. The learned counsel for the petitioners submits that the Arbitrator has found in his Award that the work done with

respect to the basement by the respondent was totally defective, however, has still not granted damages in favour of the petitioners.

11.

I have considered the submission made by the learned counsel for the petitioners, however, find no merit in the same. The Arbitrator while

rejecting the claim of damages has observed as under:-

“The controversy however is as to what damages should be awarded to the claimants. Pertaining to the bills submitted there has been no evidence

laid. No attempt was made to amend the claim and seek damages specifically. The substantive law in terms of the Arbitration and Conciliation Act

cannot be ignored. Damages necessarily had to be proved. The claimant got the work done himself without the permission of this tribunal and,

therefore, made the claim infructuous. Thus little can be awarded.â€​

12.

Though the learned counsel for the petitioners contends that alongwith the application under Section 17 of the Act the petitioners have filed

evidence in form of the bills regarding the expenses incurred by them for repairing and rectifying the defects in the basement and the same need not

be further proved as the respondent filed no reply to the said application, the fact remains that the petitioners, apart from filing the said bills, did not

lead any evidence in proof of those bills or the work done by the petitioners in repairing/rectifying defects in the basement.

13.

Even otherwise, a perusal of the contents of the application filed by the petitioners under Section 17 of the Act before the Arbitrator would suggest

that the petitioners had only filed the estimate of the expenses that may have to be incurred on rectifying the defects in the basement. The actual work

carried out by the petitioners and the expenses incurred on the same has not been filed by the petitioners before the Arbitrator. The relevant pleadings

of the petitioners in their application under Section 17 of the Act are reproduced hereinbelow:

“9. Similarly, the seepage / leakage problem in basement of property got severe, and needed urgent attention, as it caused hindrance in the use of

entire property and there was severe danger to strength of the building. In fact the said fact was brought to the notice of Respondent on 13.08.2010

during cross-examination. However, as no effort was made by Respondent to carry out the urgent necessary repair, Claimants themselves engaged

the service of specialized personnel to remedy the defect. The Claimants/Applicants hired the services of expert (M/s Mercury Waterproofing) to test

the defects and discrepancies, who after verification, reported inter-alia, that the entire basement is in dilapidatedÂ

condition and whole basement will have to be reopened, i.e. to reach RCC walls and PCC levels so that a fresh fool proof treatment could be

provided. The estimated cost quoted by M/s Mercury Waterproofing to carry our entire task is Rs.44,52,500/- (Rupees Forty Four Lakhs Fifty Two

Thousand Five Hundred only). The copies of report, dated 09.07.2010 and letter dated 06.10.2010 of M/s Mercury Waterproofing,

informing the Claimant No.1 certain  shocking facts about the poor construction and condition of the basement, alongwith photographs are annexed

herewith and marked as ANNEXURF A/2 (COLLY).

xxxx

14.

In view of the circumstances mentioned above, the Claimants/Applicants submit that it is just, fair, equitable, in the interest of justice besides being

absolutely necessary for the protection of the rights and interests of the Claimants/Applicants that the Respondent may be directed by an order of this

Hon'ble Tribunal to secure the property by either properly repairing and permanently fixing the leakage of water as per the satisfaction of the

Claimants/Applicants at the earliest or in turn reimburse/ compensate (as approved by the experts) the Claimants/Applicants suitably so that the

necessary work could be carried out by the Claimants/Applicants themselves.

xxx

a) direct the Respondent to repair and permanently fix the leakage/seepage of water as per the advise of expert at the earliest; or alternatively

b. direct the Respondent to reimburse and properly compensate the Claimants/Applicants suitably by depositing the amount as per the estimate given

by the expert required for the necessary work, as the same has to be carried out by the Claimants themselves.â€​

14.

A reading of the above would show that the petitioners, by the time of filing of the said application, had not rectified the defects in the basement.

Once the rectification work had been done by the petitioners, if at all, it was for the petitioners to have produced the evidence for the amount spent by

them on the said work. Even otherwise, the report had to be proved by leading evidence. Mere filing of this estimate alongwith an application under

Section 17 of the Act, cannot lead to the inference of the same having been proved. Therefore, no fault can be found with the Award passed by the

Sole Arbitrator. In any case, this being the matter of appreciation of evidence, this Court cannot sit as a Court of Appeal to re-appreciate the same.

15.

In view of the above, I find no merit in the present petition. The same is accordingly dismissed, with no order as to cost.