High CourtsSingle Bench

GAIL (India) Limited vs Bansal Infratech Synergies Limited

Delhi High Court · Decided on 6 July 2021 · Citation: (2021) 07 DEL CK 0020

HON’BLE JUDGES
Vibhu Bakhru, J
ACTS & SECTIONS REFERRED
Arbitration And Conciliation Act, 1996 — Section 11(6)
RESULT
Dismissed
CASE NUMBER
Original Miscellaneous Petition (COMM.) No. 177 Of 2021, Miscellaneous Application No. 7093 Of 2021
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

194 paragraphs · 4,150 words

Vibhu Bakhru, J

1.

GAIL (India) Limited (hereinafter ‘GAIL’) has filed the present petition impugning an arbitral award dated 10.12.2020 (hereinafter ‘the

impugned award’) rendered by an Arbitral Tribunal constituted by Justice (Retd.) Badar Durrez Ahmed as the Sole Arbitrator. The said award

was rendered in respect of disputes that had arisen between the parties in connection with the contract for ‘Civil and Structural Works-II

(OFFSITES)’ at GAIL’s Petrochemical Complex-II at Pata, Uttar Pradesh (hereinafter ‘the Project’).

2.

GAIL had appointed Engineers India Limited (EIL) as the consultant for implementation of the Project. EIL invited bids for the Project on behalf of

GAIL and the respondent had submitted its bid pursuant to the said invitation. The respondent’s bid for a contract value of Rs. 67,09,29,050 /- was

accepted and the same was communicated to the respondent by a Fax of Acceptance (FAO) on 31.05.2011. Subsequently, on 14.06.2011, a detailed

letter of acceptance (DLOA) was issued to the respondent. The works were required to be completed within a period of seventeen months with

effect from the date of issuance of the FOA; that is, by 31.10.2012. The time for completing the works was extended and the respondent finally

completed the same on 30.06.2014. Thereafter, on 15.06.2015, the respondent submitted its Final Bill to EIL. The Final Bill was forwarded by EIL to

GAIL and payments against the same were made on the recommendations of EIL. The last payment was made to the respondent on 04.10.2017.

3.

Shortly after receiving the last payment, the respondent invoked the Arbitration Clause and issued a notice dated 12.10.2017. GAIL did not take any

steps for either resolving the disputes or constituting the Arbitral Tribunal pursuant to the aforesaid notice, as according to it, there were no disputes

between the parties. According to GAIL, the contract stood discharged by accord and satisfaction in view of the No Claim Certificate (hereinafter

‘the NCC’) issued by the respondent.

4.

Since GAIL did not act on the aforementioned notice for arbitration, the respondent filed a petition under Section 11(6) of the A&C Act seeking

appointment of an Arbitrator. This Court allowed the said petition and by an order dated 16.04.2018, appointed the Sole Arbitrator to adjudicate the

disputes between the parties.

5.

The respondent filed its Statement of Claims before the Arbitral Tribunal, inter alia, raising several claims. The same are briefly described below:

5.1 Claim No.1: a sum of Rs. 31,23,139/- plus interest at the rate of 16% per annum. An amount equivalent to 0.5% of the Running Account (RA)

bills submitted by the respondent had been deducted towards water charges. The respondent claimed the said amount on account of sums deducted by

GAIL as deduction on account of water charges. The respondent claimed that in fact at the material time, the water networks were either non-

existent or were not fully charged and therefore, the respondent could not draw any water from the same. And, since it was not supplied any water

for construction, the amounts deducted from its RA bills on account of water charges were liable to be refunded with interest.

5.2 Claim No.2: the respondent claimed reimbursement for structural steel and allied material, which according to the respondent had been treated as

scrap. The respondent claimed that it was entitled to 283.157 metric tons of structural steel that was brought at site or payment in lieu thereof.

According to the respondent, it had brought 4065.619 MTs of structural steel at site. GAIL/EIL accepted that 3,763.899 MTs of structural steel had

been utilized in the Project; 18.564 MTs of steel was not accounted for; and the balance 283.157 MTs of structure steel was treated as scrap. The

respondent claimed that 283.157 MTs of steel was not scrap as claimed by GAIL and it could not retain the same because it was not part of the

material that was paid for by GAIL.

5.3 Claim No.3: The respondent claimed a sum of Rs. 1,00,00,000/-(Rupees One crore) as compensation for extended sale at the site. The respondent

claimed that the delay of twenty months in completion of the Project was caused for reasons attributable to GAIL/EIL and the respondent was liable

to be compensated for the same. The respondent claimed that in terms of Clause 27 of the Special Conditions of Contract, the respondent was liable

to be compensated at the rate of Rs. 5 lacs per month.

5.4 Claim No.4: Interest on delayed payments. Engineer In-charge had sent the Final Bill amounting to Rs. 4,78,71,903/- (Rupees four crores, seventy-

eight lacs seventy-one thousand nine hundred and three) to GAIL on 09.09.2015 for payment. In terms of Clause 22.3 of the GCC, the payments

were required to be made within a period of sixty days from submission of bill on joint measurement, but GAIL did not make any payment against the

said Final Bill. The respondent also claimed interest on such delayed payment at the rate of 16% per annum and quantified the same at Rs.

45,43,366.96/-.

5.5 Claim No.5: The respondent sought reimbursement of legal cost.

6.

In addition to the aforesaid claims, the respondent also prayed that the Arbitral Tribunal declare that it had issued the NCC to GAIL under pressure,

duress and coercion.

7.

GAIL contested the claims raised by the respondent on merits. It also contended that the contract between the parties was fully discharged by

accord and satisfaction as the respondent had furnished the NCC. In addition, GAIL claimed that the respondent had submitted the Material

Reconciliation Statement (hereinafter ‘the MRS’) accepting that 283.157 MTs of structural steel was scrap and was deposited with GAIL.

According to GAIL, it was not open for the respondent to raise any claims in view of the NCC, as the contract stood fully discharged. Further, in view

of the MRS submitted by the respondent, it was not open for the respondent to make any claim in respect of 283.157 MTs of scrap steel, which it had

deposited with GAIL.

8.

The respondent disputed GAIL’s contention that the contract in question was discharged by accord and satisfaction. It claimed that the MRS

and the NCC were invalid and had been obtained by coercion and undue influence.

9.

The Arbitral Tribunal examined the evidence on record and concluded that the MRS and the NCC were invalid as they were obtained by exerting

undue influence and economic coercion. In addition, the Arbitral Tribunal also found in favour of the respondent that GAIL could not rely on the NCC

to constitute a waiver on the part of the respondent as it had not complied with the conditions as stated therein. The respondent had issued the NCC,

inter alia, stating that with the receipt of the aforesaid money (referring to a sum of Rs. 4,78,71,903/-) it would have no further claims against GAIL.

However, GAIL had not fulfilled the payment condition. GAIL had paid an aggregate sum of Rs. 4,38,98,238/- against the aforesaid amount and that

too in tranches. Rs. 1,00,00,000/- (Rupees one crore) had been paid after effecting the recoveries, which were later released to the respondent

subsequently. A sum of Rs. 2,99,07,376/- was released to the respondent on 28.07.2016. The retention amount of Rs. 39,90,862/- was released on two

tranches: Rs. 30,00,000/- was released on 22.04.2016 and the balance Rs. 9,90,862/-was released on 04.10.2017. The amount deducted on account of

water charges of Rs. 2,39,330/- was not released.

10.

The Arbitral Tribunal found that the amount released by GAIL fell short by Rs. 39,73,669/-. In terms of the NCC, the claims, dues, disputes and

differences between the parties would be fully and finally settled on receipt of the amount of Rs. 4,78,71,903/-. But as the said amount was not paid in

full, the Arbitral Tribunal held that even de hors the question of coercion and/or duress, the NCC could not constitute a waiver on the part of the

respondent.

11.

The Arbitral Tribunal examined the evidence relating to the respondent’s claim for refund of water charges to the extent of Rs. 31,23,139/-.

After evaluating the pleadings and the material available on record, the Arbitral Tribunal found that the respondent had constructed a bore and it had

drawn water for construction purposes. The Arbitral Tribunal also examined Clause 2.3 of the GCC and Clause 4.0 of the SCC. In terms of Clause

2.3 of the GCC, the respondent was required to make its own arrangements for water supply and GAIL was not obliged to provide the same.

However, the said Clause also provided that GAIL would endeavor to provide water at its own source. Clause 4.00 of SCC modified Clause 2.3 of

GCC to the limited extent and provided for supply of water by GAIL on payment of charges as stipulated therein. The Arbitral Tribunal interpreted

both the clauses (Clause 2.3 of the GCC and Clause 4.0 of SCC) and held that in terms of Clause 2.3 of the GCC, the respondent was required to

make arrangements for its water supply; however, in the event GAIL permitted the respondent to draw water from its network, the respondent would

be charged a lumpsum amount at the rate of ½ % (one half percent) of the contract value. The Arbitral Tribunal held that Clause 4.00 of the SCC

did not entitle GAIL to charge any amount for supply of water if it had not supplied it. The Arbitral Tribunal found that there was ample evidence to

support the respondent’s claim that it had not drawn water from the network of GAIL principally for two reasons. First, that the network had not

been charged. And second, that even after the network had been charged, GAIL had not specified the point from where water could be drawn.

12.

Insofar as the respondent’s claim for structural steel is concerned, the Arbitral Tribunal examined the clauses of the contract and found that in

terms of Clause 55 of the SCC, the surplus material comprising of sand, bricks, stones, aggregate and other products of dismantling temporary works,

would belong to the respondent. However, no other surplus material was permitted to be removed and the same would be deemed to be the property

of GAIL. But that did not entitle GAIL to claim the surplus steel, which was neither paid for nor formed a part of the Schedule of Rates (SoR).

13.

The Arbitral Tribunal also noted that in terms of Clause 59.45 of the SCC, full items of works were covered under SoR and no allowances

towards wastage/scrap etc. would be accounted for.

14.

It was also established from the record that the respondent had brought 4,065.619 MTs of structural steel on the site. GAIL had not paid for SoR

Item no. S004.03.03 (incorporating the structural steel) in excess of 3763.898 MTs. Thus, 301.720 MTs of structural steel was required to be

accounted for. Out of the said amount, 18.564 MTs of structural steel was unaccountable and the dispute essentially revolved around the remaining

283.157 MTs of structural steel. The Arbitral Tribunal found that since GAIL had not paid for the relevant SoR item in excess of 3763.898 MTs, it

could not retain any steel in excess of the said quantity. However, the Arbitral Tribunal also noted that in terms of Clause 59.45 of the SCC, no

allowances were permissible towards wastage and scrap. Thus, the respondent’s claim for 283.157 MTs was required to be reduced by quantity

of scrap, which would have been generated. The said quantity of scrap was determined on the normative basis at 1.5% of the SOR item of 3763.899

MTs. Therefore, a further amount of 56.459 MTs (1.5% of 3763.898 MTs) was required to be adjusted from the remaining quantity of 283.157 MTs

of steel. Reducing the aforesaid quantity, the Arbitral Tribunal held that the respondent was entitled for return of 226.698 MTs of structural steel,

which admittedly had been deposited with GAIL. GAIL’s contention that the said steel was scrap, was rejected by the Arbitral Tribunal after

evaluating the evidence led by both the parties. The Arbitral Tribunal further directed GAIL to return 226.698 MTs of structural steel or pay the value

thereof at the market price prevailing on the date of the award.

15.

Insofar as the respondent’s claim for compensation at the rate of 5,00,000/- per month for extended stay is concerned, the Arbitral Tribunal

rejected the same on two grounds. First, the Arbitral Tribunal held that the respondent had waived its right for claiming any compensation. By its letter

dated 09.09.2014, the respondent had applied for extension of time up to 30.06.2014 without any “financial implication on either sideâ€. The

Arbitral Tribunal found that there was no material to establish that the said request was made under coercion or under undue influence. GAIL had

acceded to the request for extension of time without the levy of PRS (Price Reduction Schedule) and therefore, it was not open for respondent to now

claim compensation on account of extended stay.

16.

Second, the Arbitral Tribunal held that compensation for extended stay would be payable in terms of the contract between the parties only if the

delay was attributable entirely to EIL/GAIL. The Arbitral Tribunal found that in the facts of the case, the delay in execution of the works was not

solely attributable to GAIL and therefore, the respondent was not entitled to the compensation as claimed.

17.

The Arbitral Tribunal found that payments to the respondent had been inordinately delayed. The payment under the Final Bill was required to be

made within a period of sixty days from its submission. EIL had forwarded the Final Bill to GAIL under the cover of its letter dated 09.09.2015 after

certifying the measurements but the payments were made in a piecemeal manner on various dates: Rs. 1,00,00,000/- was made on 18.02.2016; Rs.

30,00,000/- was made on 22.04.2016; Rs. 2,99,07,376/- was made on 28.07.2016 and Rs. 9,90,862/- was made on 04.10.2017. The Tribunal held that

GAIL was liable to pay interest at the rate of 10% per annum on the delayed payment. And, the said amount of interest was quantified at Rs.

27,35,749/-.

18.

In addition to the above, the Arbitral Tribunal also awarded costs in favour of the respondent, which was quantified at Rs. 18,43,878/-.

19.

As is apparent from the plain reading of the impugned award, it is based on pleadings and the evaluation of evidence. As noticed above, the

respondent’s claim for water charges is based on interpretation of Clause 2.3 of GCC and Clause 4.00 of SCC.

20.

Clause 2.3 of GCC and Clause 4.0 of the SCC are set out below:

“2.3 Water Supply: Contractor will have to make his own arrangements for supply of water to his labour camps and for works. All pumping

installations, pipe network and distribution system will have to be carried out by the Contractor at his own risk and cost.

Alternatively the Employer at his discretion may endeavour to provide water to the Contractor at the Employer’s source of supply provided the

Contractor makes his own arrangements for the water meter which shall be in custody of the Employer and other pipe networks from source of

supply and such distribution pipe network shall have prior approval of the Engineer-in-Charge so as not to interfere with the layout and progress of the

other construction works. In such case, the rate of water shall be deducted from the running account bills.

However, the Employer does not guarantee the supply of water and this does not relieve the Contractor of his responsibility in making his own

arrangement and for the timely completion of the various works as stipulated.â€​

“4.0 SUPPLY OF WATER, POWER & OTHER UTILITIES

The scope of supply of water, power and land for Contractor’s Office, Ware house, residential accommodation etc. shall be as described in Cl.

2.3 to 2.6 of GCC.

The clause no. Cl. 2.3 and 2.4 of GCC shall stand modified to the following extent only:

Water and power shall be supplied by EMPLOYER to the Contractor on chargeable basis. Lumsum amount @ ½ % of Contract value shall be

charged for water supply and Rs. 6.00 per KWH for power supply.â€​

21.

Clause 2.3 of the GCC clearly indicates that the respondent was required to make all arrangements for water for the Project. However, it also

expressly indicates that GAIL had agreed that it would endeavour to provide the same from its own network. Clause 4.0 of the SCC provides for the

charges to be paid by the respondent for supply of water by GAIL and to that extent it clarifies that the water supplied by GAIL would have to be

paid for at the rate of ½ % (one half percent) of the contract value. However, Clause 2.3 of the GCC does not absolve respondent from making the

necessary arrangements for supply of water in the event GAIL does not supply the same. This Court concurs with the Arbitral Tribunal’s

interpretation of Clause 2.3 of the GCC and Clause 4.0 of the SCC and therefore, no interference with the impugned award is warranted on this

ground.

22.

The Arbitral Tribunal had concluded that GAIL had, in fact, not supplied water to the respondent. During the initial period of the contract, the

water network was not charged and even thereafter, GAIL had failed to indicate the point from where respondent could draw any water.

23.

The Arbitral Tribunal reasoned that all that was required by GAIL to dispute the above was to provide some evidence to indicate that it had

communicated to the respondent the point from where water could be drawn from its network. However, GAIL had failed to do so.

24.

This Court finds no infirmity with the finding of the Arbitral Tribunal and its conclusion on facts warrants no interference by this Court.

25.

The Arbitral Tribunal’s conclusion that GAIL could not appropriate the structural steel that was brought at site and which did not form a part

of the Schedule of Rate (SOR) is based on the interpretation of the Clauses of the contract and this Court finds no infirmity with such interpretation as

well. Thus, the conclusion that GAIL was required to return the surplus structural steel or pay the market value thereof, cannot be faulted.

26.

In fairness, Mr. Luwang did not attempt to assail the Arbitral Tribunal’s award on merits of the aforesaid claim. He confined his arguments

principally to assail the conclusion of the Arbitral Tribunal that the MRS and NCC had been secured by coercion. He had contended that EIL could

not be faulted for demanding the NCC before processing the Final Bill as the same was a part of the contract between the parties. He had referred to

Clause 44.3 of the said contract in question, which reads as under:

“44.3 The final payment shall not become due until the CONTRACTOR delivers to the ENGINEER-IN-CHARGE a complete release or waiver

of all liens arising or which may arise out of his agreement or receipt in full or certification by the CONTRACTOR in a form approved by

ENGINEER-IN-CHARGE that all invoices for labour, materials, services have been paid in lien thereof and if required by the ENGINEER-IN-

CHARGE in any case an affidavit that so far as the CONTRACTOR has knowledge or information the releases and receipts include all the labour

and material for which a lien could be filled.â€​

27.

Mr. Luwang submitted that a bald allegation of coercion and undue influence would be insufficient to establish the same. He pointed out that the

Final Bill was submitted on 15.06.2015 and the respondent had invoked arbitration by a notice dated 12.10.2017. He submitted that in the present case,

the contention that the MRS and NCC had been obtained by undue influence and coercion was raised for the first time in the Statement of Claims,

which was filed almost two and a half years after the respondent had submitted its Final Bill and therefore, such a claim could not be accepted.

28.

There is no dispute that a bald assertion of coercion or duress without any material substantiating the same would be wholly insufficient to maintain

such a claim. The Arbitral Tribunal had referred to the decisions of the Supreme Court in Union of India v. Master Construction: (2011) 12 SCC 349;

National Insurance Co. Ltd. v. Boghara Polyfab Pvt. Ltd.: (2009) 1 SCC 267; and Oriental Insurance Co. Ltd. v. Dicitex Furnishing Ltd.: 2019 SCC

Online 1458 and had observed as under:

“26. From the said decisions it is clear that the issuance of a ‘No Claim Certificate’ does not, by itself, extinguish the rights and claims of the

party issuing such a certificate. If the party is able to establish duress or coercion, then the ‘No Claim Certificate’ issued by it would be void

and its claims would have to judged on merits. At the same time, a bald assertion of coercion or duress without any material to back such a plea would

not entitle the party who gave the ‘No Claim Certificate’ to renege from it.â€​

29.

After noting the law on the subject, the Arbitral Tribunal had proceeded to examine the evidence placed on record to ascertain whether the

respondent’s claim that the NCC and MRS had been obtained by coercion and duress was substantiated. The respondent had submitted its Final

Bill (RA Bill No. 26) to EIL on 15.06.2015. Fifteen days thereafter, EIL had issued a letter dated 30.06.2015 clearly stating that the Final Bill cannot

be processed without the documents mentioned therein. These included a ‘No Claim Certificate’ and a ‘Material Reconciliation

Statement’. Thus, admittedly, the petitioner was required to submit the same in order to be paid the admitted amount due under the Final Bill.

30.

The Arbitral Tribunal also found that there was substantial amount due to the respondent as EIL had also recommended payment of a sum of Rs.

4,78,71,903/-. However, EIL/GAIL had refused to process the payment until the respondent submitted the NCC. According to Mr. Luwang, Clause

44.3 of the GCC required the respondent to submit an NCC and MRS as demanded by EIL for the purposes of processing the Final Bill. Thus,

concededly, the substantial amount that was admittedly due to the respondent would have been held up on account of its claims for refund of water

charges and structural steel. As noticed by the Arbitral Tribunal, the respondent had already waived its right to compensation for extension in time for

completing the contract.

31.

The Arbitral Tribunal also noted that the language of the NCC was as dictated by EIL/GAIL. It was a one-sided letter and effectively deprived

the respondent from raising any claims. There is also material on record to establish that the respondent was facing a liquidity crunch. The respondent

had placed on record several letters seeking release of funds on that ground. It had also requested for release of funds in order to pay its vendors and

sub-contractors.

32.

The Arbitral Tribunal had evaluated the said material and accepted the respondent’s contention that it was economically coerced to issue the

NCC and MRS. In view of the substantial material placed on record, there is little doubt that the respondent was compelled to issue the NCC and

MRS.

33.

The contention that the allegation of coercion is a bald allegation without any substance, is unmerited. There is ample material on record to support

the respondent’s contention that it was compelled to issue the NCC and MRS. The Arbitral Tribunal had examined and evaluated the same and its

conclusion to accept the respondent’s claim cannot be stated to be perverse or patently illegal. This Court is not required to re-appreciate or re-

evaluate the evidence to examine the Arbitral Tribunal’s decision on merits as a first appellate court. As long as the said decision is a plausible

one, based on material on record, no interreference with the same is warranted. It is settled law that the Arbitral Tribunal is the final arbiter of facts

and the court would not supplant its opinion in place of the Arbitral Tribunal’s unless the same is found to fall foul of the public policy of India.

(See: Associate Builders v. Delhi Development Authority: (2015) 3 SCC 49).

34.

The contention that the allegation of coercion had been raised at a belated stage is also unmerited. The payments due to the respondent were

delayed. The respondent had made its claim shortly after GAIL had released the payments admittedly due to the respondent. Considering that it was

the respondent’s case that it was compelled to issue the NCC and MRS in order to secure the payments that were admittedly due to it; the

question of delay in making such allegation has to be considered not from the date when the Final Bill was submitted but when the admitted payments

were received.

35.

In view of the above, the present petition is unmerited and is, accordingly, dismissed. The pending application is also disposed of.