High CourtsSingle Bench

GTM Builders & Promoters Pvtltd vs SNEH Developers Pvt Ltd

Delhi High Court · Decided on 20 September 2017 · Citation: (2017) 09 DEL CK 0274

HON’BLE JUDGES
Jayant Nath, J
ACTS & SECTIONS REFERRED
Code Of Civil Procedure, 1908 — Section 151, Order 6 Rule 17 · Arbitration And Conciliation Act, 1996 — Section 33, 34, 34(2)(b)
CASE NUMBER
Original Miscellaneous Petition (COMM) No. 10 Of 2016, Miscellaneous Application No. 6379 Of 2016
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

54 paragraphs · 1,111 words

Jayant Nath, J

I.A.4720/2017

1.

This application is filed under Order VI Rule 17 read with Section 151CPC on behalf of petitioner for amending the petition under Section 34 of the

Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘The Act’).

2.

The petitioner has filed the present petition under Section 34 of the Act challenging the impugned arbitral award dated 01.08.2015. After passing of

the award, the petitioner is said to have filed on 19.10.2015 objections under Section 34 of the Act before this court. In the meantime, the respondent

moved an application under Section 33 of the Act before the learned arbitrator seeking correction of certain typographical mistakes in the award. On

07.9.2016, the application of the respondent under Section 33 of the Act was allowed. The said order dated 07.09.2016 makes a correction in the

award. The award was for Rs. 4,37,88,000/-. This was noted to be a typographical error and was corrected as Rs.6,37,88,000/-. Now, the petitioner

has filed the present application seeking to add paras in the original petition placing on record the corrections made by the learned arbitrator while

disposing of the application under Section 33 of the Act on 07.09.2016 and also challenging the exercise of powers by the learned arbitrator under

Section 33 of the Act.

3.

I have heard the learned counsel for the parties.

4.

The learned counsel for the petitioner relies upon the judgment of the Supreme Court in State of Maharashtra v. Hindustan Construction Company

Ltd. (2010) 4 SCC 518 and Venture Global Engineering Satyam Computer Services Limited and another (2010) 8 SCC 660 to support his case that

amendment can be allowed by this court.

5.

The learned counsel for the respondent however submits that the court fees of main petition has not been filed within time and the same is barred

by limitation. This he states is the settled legal position. He submits that the original petition under Section 34 of the Act was filed by the petitioner on

19.10.2015 but the court fees has been paid some time in December, 2015. Hence, he submits that the original petition under Section 34 of the Act is

barred by the limitation and the question of allowing the present amendment would not arise. He however accepts that other than adding the

correction of the typographical mistake where the figure of Rs. 4,37,88,000/- was to read as Rs.6,37,88,000/-, no other amendment has been done by

the learned arbitrator.

6.

I may see the legal position regarding such amendments.

7.

In Venture Global Engineering Satyam Computer Services Limited and another (supra), the Supreme Court has held as follows:-

“13. In the course of argument before this Court, Mr Harish N. Salve, learned Senior Counsel appearing for the respondents did not make any

attempt to defend the order of the High Court on the question of limitation as the learned counsel was obviously conscious of the decision of this Court

in State of Maharashtra v. Hindustan Construction Co. Ltd. [(2010) 4 SCC 518 : (2010) 2 SCC (Civ) 207 : AIR 2010 SC 1299] This Court in

Hindustan Construction [(2010) 4 SCC 518 : (2010) 2 SCC (Civ) 207 : AIR 2010 SC 1299] made it clear that it cannot be the intention of the

legislature to shut out amendments, as a result of which incorporation of relevant materials in a pending setting-aside proceeding is prevented.

14.

In Hindustan Construction [(2010) 4 SCC 518 : (2010) 2 SCC (Civ) 207 : AIR 2010 SC 1299] this Court considered the provision in Section 34(2)

(b) of the A&C Act, 1996 and while considering the ambit of the expression “the Court finds that†in Section 34(2)(b), this Court opined that

where application under Section 34 has been made within the prescribed time, leave to amend grounds, in such an application, if the peculiar

circumstances of the case and the interest of justice so warrant, can be granted. In saying so, this Court in SCC para 31 : AIR para 25 of the Report,

relied on the decisions of this Court in L.J. Leach & Co. Ltd. v. Jardine Skinner & Co. [AIR 1957 SC 357] and Pirgonda Hongonda Patil v. Kalgonda

Shidgonda Patil [AIR 1957 SC 363] and held that where it is required in the interest of justice, the Court always has the power to grant leave to

amend and this power to grant an amendment is not affected under Section 34.

15.

We are of the opinion that in dealing with a prayer for amendment, courts normally prefer substance to form and techniques and the interest of

justice is one of the most relevant considerations. Therefore, if a party is entitled to amend its pleadings, having regard to the justice of the case, the

right of the party to amend cannot be defeated just because a wrong section or a wrong provision has been quoted in the amendment petition. The

approach of the High Court in this case, in rejecting the appellant's prayer for amendment, inter alia, on the ground that a wrong provision has been

quoted in the amendment petition, is obviously a very hypertechnical one. Mr Salve rightly did not even try to defend the impugned order on the

aforesaid technical ground adopted by the High Court.â€​

8.

At this stage, the learned counsel for the respondent submits that the original petition is barred by the limitation but he will make the said submission

at the time of admission/disposal of the main petition. The said submission on limitation is denied by the learned counsel for the petitioner.

9.

A perusal of the application for amendment filed by the petitioner would show that limited amendments are sought. In Para A, only the change of

the amount stated is sought. In para C, the exercise of power of the learned arbitrator under Section 33 of the Act is sought to be challenged. In these

circumstances, in my opinion, there are no substantial new issues or facts which are sought to be incorporated. The amendments sought are a

consequence of the application under Section 33 of the Act being allowed.

10.

Keeping in view the above decisions of the Supreme Court regarding amendment of petition under Section 34 of the Act, in my opinion,

amendments sought are necessary for the purpose of determining the real questions in controversy between the parties. The need to amend arises on

account of the events which have taken place subsequent to filing of the petition. Accordingly, the application is allowed.

11.

Amendment petition be filed within two weeks from today.

12.

List this matter for arguments on 11.01.2018.

13.

The said application is accordingly disposed of.