AI Structured Summary
Not yet generated for this judgment
Judgment
Vibhu Bakhru, J
Indraprastha Gas Limited (hereinafter “IGLâ€) has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996
(hereinafter the “A&C Actâ€) impugning an arbitral award dated 10.12.2019 (hereinafter “the impugned awardâ€) delivered by the Arbitral
Tribunal constituted of Justice (Retd.) Dilip Raoshaeb Deshmukh, former Judge of the Chhattisgarh High Court, as the Sole Arbitrator.
Pawan Castings (hereinafter “the respondent') is a proprietorship concern of Mr. Deepak Dhuper. He is engaged in the business of
manufacturing of Aluminium Pressure Dye Castings under the said name. IGL is a company incorporated under the Companies Act, 1956 and is the
only supplier of natural gas in Delhi. IGL was the claimant before the Arbitral Tribunal. The impugned award was rendered in the context of disputes
that have arisen between the parties in relation to a Gas Sales Agreements (GSAs) dated 10.11.2009 and 1.11.2014.
Factual context
On 10.11.2009, the parties (IGL and the respondent, Pawan Castings) entered into a Gas Sales Agreement (GSA) under the category of Large
Industrial Customer for the supply of Piped Natural Gas (hereafter PNG). IGL agreed to supply 1,56,000 SCM of PNG annually and 500 SCM daily
under the aforesaid GSA.
Thereafter, on 01.11.2014, the respondent requested IGL to change his category to Small Industrial Customer and executed a fresh GSA (2014
GSA). In terms of the said 2014 GSA, the daily contract quantity of PNG was reduced to 250 SCM per day.
On 04.12.2014, officials of IGL, conducted an inspection at the premises of the respondent. IGL alleges that they found unauthorised tapping of
PNG and claims that the said officials took photographs and also a video recording of the unauthorised tapping. Thereafter, on 05.12.2014, IGL filed a
complaint and pursuant thereto an FIR bearing no. 1425 of 2014 under Sections 336/379 of the Indian Penal Code, 1860 was registered against the
respondent. The said FIR recorded that an unauthorised CS/MS pipeline had been laid with the covering of PVC pipe in the factory of the respondent.
The said pipeline was connected to the first floor of the factory premises and an unauthorised regulator was installed inside a shelf of a desk. Further,
the same pipeline was connected to a downstream pipeline bypassing the meter of IGL. Thus, the respondent had sourced PNG from an unauthorised
tapping point.
By a notice dated 11.12.2014, IGL terminated the 2014 GSA in terms of Article 25(ii) of the said GSA. It alleged that during the inspection
conducted on 04.12.2014, an unauthorised connection in IGLâ€s 32mm MDPE pipeline with continuous high pressure natural gas of 4 bar was found.
According to IGL, this amounted to theft of IGLâ€s gas.
On 20.12.2014, the respondent responded to the aforesaid letter and denied the allegation that he had tapped IGLâ€s gas pipeline. He stated that
PNG was consumed in terms of the GSA and he had not defaulted in making payment of bills. The respondent further requested IGL to resume the
supply of PNG with immediate effect as the production was suffering for want of gas supply. He further put IGL to notice that he would claim
compensation for any loss caused due to suspension of the supply of gas.
On 05.02.2015, IGL sent a notice informing the respondent that the total unauthorised overdrawal quantity of natural gas for the period of April,
2010 till November, 2014 was 347 SQM and raised a provisional demand of Rs. 1,52,51,669. The said amount was to be paid within three working
days with effect from 09.02.2016.
Thereafter, on 14.02.2015, in view of non-payment of the aforesaid amount, IGL invoked the Bank Guarantee of Rs. 6,04,050 issued by Canara
Bank. On 20.02.2015, the Canara Bank made the payment against the said Bank Guarantee.
In view of the disputes between the parties, by a letter dated 12.03.2015, IGL invoked the Arbitration Clauses (Article 15.3 of the GSA dated
10.11.2009 and Article 23(iii) of the GSA dated 01.11.2014) and nominated Mr. P.K. Pandey, Vice President (CNG O&M) of IGL as the Sole
Arbitrator.
On 15.04.2015, the respondent filed an application under Section 13 of the A&C Act challenging the appointment of the Sole Arbitrator. The
learned Arbitrator dismissed the aforesaid application on 11.08.2015.
On 11.05.2015, IGL filed a petition under Section 9 of the A&C Act (being O.M.P. (I) 217 of 2015), inter alia, praying for the appointment of a
Court Commissioner to visit the factory premises to collect the relevant information. This Court allowed the aforesaid prayer and by an order dated
15.05.2015, appointed Mr. S.K. Sharma, a former Registrar of this Court, as the Court Commissioner to visit the factory premises of the respondent
and collect the relevant information. The operative part of the said order indicating the scope of the work to be performed by the Commissioner is set
out below :
“9. In light of the above submissions, the Court considers it appropriate to issue the following directions:
(i) The Court appoints Mr. S.K. Shatma, a former Registrar of this Court, residing at WZ-321, Sri Nagar, Shakur Basti, Delhi-110034 (Mob.No.
9818103888) as Court Commissioner. The CC will inform the parties at least one day in advance of his proposed visit to the sites.
ii) The CC will inspect the factory premises of the four Respondents to ascertain the gas pipes running from the point where the meter of the
Petitioner was installed; take photographs of the pipeline and the equipments to which the pipelines may have been or are now connected
(iii) Prepare an inventory of all the equipments installed in the premises including the furnace and take photographs thereof. The details of the
equipments including dimensions, capacity etc. and any relevant documents in relation to such equipments will be furnished to the CC by the
concerned Respondent.
(iv) Each of the Respondents will make available to the CC documents pertaining to production of the final product, payment of excise duty, vouchers
reflecting sales of the final product and registers showing the stocks on hand. The above figures shall be produced for the billing period as may be
specified by the representatives of the Petitioner who will be present at the site. It is clarified that whatever records are unable to be produced by the
concerned Respondent, the CC will make note to that effect. The CC in his report shall make note of whatever is pointed out by the Respondents at
the site.
(v) The memo of the proceedings drawn up by the CC shall be got signed by the representatives of the Petitioner and the Respondents
(vi) One copy of the CC's report of his visit enclosing the proceedings, documents, photographs etc., shall be filed in the Court in these proceedings
within two weeks of the completion of the visits and another copy thereof shall be filed by the Petitioner before the learned Arbitrator. Copies of the
CC's report be made available to all the parties.
(vii) The fee of CC is fixed at Rs.2 lakhs which should be paid by the Petitioner to him in two instalments. 50% of fee be paid within one week from
today and the balance within a week of the submission of the report. This is apart from all incidental expenses towards travel, secretarial assistance,
photography, etc. which shall be paid by the Petitioner as per acutals.
(vii) The CC should complete the above exercise preferably on or before 10th June 2015.
On 30.05.2015, the Court Commissioner inspected the factory premises of the respondent. During the course of the inspection, he recorded the
contentions advanced by Mr. Deepak Dhuper (sole proprietor of the respondent). The respondent stated that one furnace and two dye casting
machines were shifted to Bawana in first week of May, 2015. He claimed that after disconnection of the gas supply from IGL, he was using
Diesel/Low Density Oil for melting aluminium in the existing furnace. Mr. Dhuper could not produce any documents regarding capacity of the
equipment or the excise records. He stated that the records were not available as the unit (Pawan Castings) was not registered with the Excise
Authorities because its sales were exempted. A list of documents required to be submitted by Mr. Deepak Dhuper was handed over to him and the
proceedings were adjourned to 03.06.2015.
On 03.06.2015, Mr. Deepak Dhuper handed over a note regarding the process of aluminium pressure die casting and the invoices of Kamal Gas
Service and Bharat Gas Service to the Court Commissioner along with his covering letter. The said covering letter recorded that “As the (LPG
Commercia) Gas was the fuel we were using just prior to PNG (IGL). At the time in December '14 the pipeline of this medium were installed in the
premises which may have been confused as that of PNG kindly noteâ€. The Court Commissioner also recorded the statement of the counsel for IGL
to the effect that no such pipeline as mentioned in the aforesaid letter existed at the time of installation of the PNG connection on 04.12.2014. Mr.
Deepak Dhuper had provided copies of the documents as per the list and the Court Commissioner also noted the same.
The aforesaid report by the Court Commissioner was filed before this Court on 29.06.2015.
On 05.09.2015, IGL filed its Statement of Claims and the respondent filed its Statement of Defence and Counter Claims on 04.11.2015. In view of
the rival stands, the Arbitral Tribunal revised the issues framed on 23.02.2016 and framed the following issues, on 08.04.2016:-
“1. Whether the invocation of the present Arbitration by the Claimant is valid as per the provisions of the Arbitration and Conciliation Act, 1996?
Whether the Claimant is entitled to claim any amount in respect to the Gas Supply Agreement dated 10.11.2009 in these proceedings in view of the
objection taken by the Respondent in the Preliminary Objection-III of its Statement of Defence?
Whether there was any unauthorized and illegal consumption of gas by the Respondent as on 04.12.2014 as contended by the Claimant?
Whether the Claimant is entitled to recover a sum of Rs.1,46,47 ,619 I - from the Respondent towards unauthorized and illegal consumption of gas
as claimed in the Statement of Claim?
Whether either of the Party is entitled to interest @ 18% on the amount claimed?
Whether the Claimant was justified in enchasing the Bank Guarantee of the Respondent worth Rs.6,04,050
Whether Respondent is entitled to recover the amount from the Claimant as claimed in his Counter Claim?â€
Thereafter, the learned Arbitrator resigned and on 19.12.2016, IGL appointed Justice (Retd.) Dilip Raosaheb Deshmuk, former judge of
Chhattisgarh High Court as the Sole Arbitrator to adjudicate the disputes.
On 20.12.2016, the respondent filed a petition under Section 11 of the A&C Act (ARB. P. 815/2016) seeking appointment of an Arbitrator to
adjudicate the disputes as the arbitrator appointed earlier, Mr. PK Pandey, had resigned. This Court by an order dated 22.12.2016 confirmed the
appointment of Justice (Retd.) Dilip Raosaheb Deshmukh, as the Sole Arbitrator to adjudicate the disputes and further directed that the arbitration be
conducted under the aegis of the Delhi International Arbitration Centre (DIAC).
On 10.12.2019, the Arbitral Tribunal made the impugned award rejecting IGLâ€s claims. It found that IGL had failed to prove tampering of the
pipeline or the unauthorised consumption of PNG, inside the respondentâ€s factory. The Arbitral Tribunal also held that the encashment of the Bank
Guarantee submitted by the respondent, was illegal. The Tribunal did not accept his prayer for refund of the amount received by IGL on invocation of
the Bank Guarantee because he had not paid any fee for the said claim. However, the Arbitral Tribunal held that IGL was liable to bear the entire
cost of the arbitration.
Aggrieved by the impugned award, IGL has filed the present petition.
Submissions
Mr. Saurav Agarwal, learned counsel appearing for IGL, submitted that the finding of the Arbitral Tribunal that IGL had failed to establish that
there was any tampering of IGLâ€s facilities in the premises of the respondent is patently erroneous. He submitted that the said finding is perverse
and based on assumptions, which are contrary to record. He drew the attention of this Court to the finding of the Arbitral Tribunal that “there is no
photograph or video on record to show that an illegal tapping point existed before the MRS†and contended that the said finding is patently erroneous
as the photographs placed on record clearly show an illegal tapping point. He referred to the photograph exhibited as CW-1/17 and submitted that the
said photograph clearly evidenced that IGLâ€s pipeline for supply of gas had been tapped before the Metering and Regulation Station (MRS).
Next, he submitted that the entire approach of the Arbitral Tribunal in rejecting the evidence led by IGL is perverse and indicated a pre-existent
disposition to reject the evidence. He further pointed out that the Arbitral Tribunal had rejected the electronic evidence on the ground that an affidavit
under Section 65B of the Indian Evidence Act, 1872 had not been filed. He stated that no such objection had been taken at the material time.
Reasons and conclusion
I have heard Mr. Agarwal, learned counsel appearing for IGL at some length.
IGLâ€s claim for a sum of Rs. 1,46,47,619/- is premised on the assumption that the respondent had consumed 3,17,822.09 SCM of PNG without
the said supply being recorded by the Metering and Regulation Station (MRS). The said consumption was calculated on the basis of the respondentâ€s
maximum monthly consumption during the period of supply. In August 2010, the respondent had consumed 16,686 SCM of PNG, which the maximum
consumption in any moth and IGL quantified its claim on the assumption that the respondent was consuming at least the said quantum of PNG every
month. According to IGL, the difference between the said consumption and that recorded by the MRS and invoiced by IGL, would be the bare
minimum consumption that had escaped being metered. And, the respondent was liable to pay for the same. The said claim was premised on the basis
that IGLâ€s facilities (supply pipelines) before MRS had been tapped by the respondent and bulk of the PNG for its consumption had been drawn
from the illegal tapping point. IGL claimed that only a small fraction of PNG supply was drawn from beyond the metering system and therefore, only
that part of the consumption was recorded and invoiced by IGL to the respondent.
As is apparent from the above, IGL was required to, essentially, prove that the respondent had in fact tapped IGLâ€s pipeline before the MRS and
had drawn the gas from the said pipeline for his consumption.
The respondent had contested the aforesaid claim on two fronts. First of all, it disputed that the inspection carried out at the factory premises had
resulted in discovery of any illegal or unauthorized tapping point. The respondent claimed that PNG supplied by IGL had not been consumed
unauthorizedly or without the same being recorded at the MRS. The respondent also contested IGLâ€s assumption that the reduction in the metered
PNG consumption was a result of the respondent tapping the said supply before the metering point. The respondent claimed that he was also using oil
for its production and relied upon the Court Commissionerâ€s report, which confirmed the existence of overhead oil tanks for storing oil for use as fuel
to carry on the manufacturing process. It was also submitted that in terms of the GSAs, the respondent had agreed to not depend on a single fuel. The
respondent had also produced certain bills showing purchases of oil.
The Arbitral Tribunal considered the rival contentions and had held that the onus of proving the following facts rested on IGL:
(i) that an inspection at the factory premises of the respondent was conducted by an authorized officer of IGL;
(ii) that the respondent had laid an unauthorized CS/MS pipeline with a covering of PVC pipe in its factory and had sourced PNG from the
unauthorized tapping point before the MRS; and
(iii) that an unauthorized regulator had been installed inside a shelf of the desk located at the first floor of the factory premises, to regulate the flow of
PNG.
The Arbitral Tribunal examined the evidence and concluded that IGL had failed to prove the above. The reasons for the same as articulated by the
Arbitral Tribunal in the impugned award are set out below:
“(iv) The inspection report dated 06.07.2015 by Mr. S.K. Sharma Local Commissioner appointed by the High Court and the photographs taken are
of no avail to the Claimant and prove nothing as none of the incriminating material alleged to have been found at the Respondentâ€s premises is seen
in the photographs. Such incriminating material was not even found by the police on 05.12.2014 as admitted by Mr. Dileep Kumar (CW-1).
(v) The Claimant has led the evidence of Mr. Dileep Kumar (CW- 1) and Mr. Narendra Nath Pandey (CW-2) officials of the Claimant to prove the
above allegations and has also filed the photographs and video stated to have been taken inside the factory of the Respondent. There were two
affidavits in evidence of the witness Mr. Dileep Kumar (CW-1). The first one was dated 13.04.2016 while the second was dated 24.05.2016. While
the first affidavit does not even whisper that Mr. Dileep Kumar (CW-1) an official of the Claimant had inspected the premises of the Respondent on
04.12.2014 the second affidavit is also totally silent about the name of any other official of the Claimant who was present in the factory premises of
the Respondent during such inspection. It was for the first time in the Rejoinder by the Claimant that it was stated that one Mr. Dilip and Mr. Pranav
Uppal officials of the Claimant had inspected the factory premises of the Respondent on 04.12.2014. Mr. Pranav Uppal was not examined by the
Claimant. Presence of Mr. Narendra Nath Pandey at the inspection is not mentioned therein. During cross-examination Mr. Narendra Nath Pandey
(CW-2) in answer to Q.No.30 stated that besides Mr. Dileep Kumar Mr. Shashank had carried the initial inspection on 04.12.2014 in the premises of
the Respondent. He further stated that Mr. Somil Garg, Mr. Rakesh Agarwal and Mr. Sushil Kumar also joined the inspection on being informed by
Mr. Dileep Kumar. Thus firstly, none of the witnesses corroborate the presence of Mr. Pranav Uppal during the inspection. The names of Mr.
Shashank, Mr. Somil Garg, Mr. Rakesh Agarwal and Mr. Sushil Kumar are also absent in the Rejoinder by the Claimant. None of these witnesses
have been examined by the Claimant. So far as Para 10 of the affidavit in evidence of Mr. Narendra Nath Pandey is concerned, it does not even
whisper about his presence at the factory premises of the Respondent during such inspection on 04.12.2014. Even during cross-examination he
admitted that he did not accompany Mr. Dileep Kumar to the Respondentâ€s factory premises but reached there only after Mr. Dileep Kumar called
him. At what stage of the inspection was he called is not known. His testimony being evasive to material questions does not in any manner prove
either his presence during inspection or any of the essential elements of alleged tampering by the Respondent.
(vi) Mr. Dileep Kumar (CW-1) has testified about some of the photographs C 1/8, 10, 12, 13 and 17 as proof of tampering done by the Respondent in
its premises to facilitate flow of PNG from the illegal tapping point done by the Respondent before the metering unit provided by the Claimant in the
factory premises. However, there is no photograph or video on record to show that an illegal tapping point existed before the MRS. There is no
photograph which shows the location or the existence of the MRS.
(vii) As regards the photographs and videos on record while the first affidavit of Mr. Dileep Kumar is silent, the second affidavit states as under in
Para 23:
“23. All the videos had been prepared and photographs using the mobile phone of different employees of IGL who were present at the
site at the time when the above stated incident was taking place. These videos and photos were then copied and stored on their computers by
the respective employees, which computer was working properly and was used regularly to store or process information for the purposes of
activities regularly carried on by the concerned employee and the photographs and the videos stored in the CD are reproduced from what
was stored in the said computers.â€
(viii) No such inference can be drawn from the above evidence that any photographs or videos were taken by Mr. Dileep Kumar (CW-1). In answer
to Q.No.80 he admits his inability to identify which of the photographs on record were taken by which of the officials. One CD on record was
displayed before the tribunal. The witness stated that he was seen taking videos in the CD. It naturally follows from it that the CD on record was not
made by Mr. Dileep Kumar but by some unidentified person. The evidence of Mr. Dileep Kumar is completely discredited by his admission in answer
to Q.No.81 that his statement regarding taking photographs and videos during inspection at the Respondentâ€s factory is incorrect while what was
stated in Para 23 of his additional affidavit (quoted above) is correct. This leads to the inescapable conclusion that the photographs and videos on
record cannot be read in evidence for three reasons, firstly because their author has not been examined, their source is not known and lastly because
of total non-compliance of Section 65-B of the Evidence Act. In Anvar P. V. vs. P.K. Basheer and Ors. (2014) 10 SCC 473 it was held that an
electronic record by way of photograph, CD etc. shall not be admitted in evidence unless the requirements under section 65-B of the Evidence Act
are satisfied. In the absence of a certificate in terms of Sec. 65-B of the Evidence Act by the author of such electronic record such secondary
evidence of photographs and CDs is wholly inadmissible.
(ix) What shocks the conscience is that Mr. Dileep Kumar (CW-1) admits that no panchnama or inspection report was prepared during or after the
inspection at the factory of the Respondent. He mentions the presence of some labourers of the Respondent during the inspection and asserts that if
called they may confirm the facts. However, no such labourer has been examined. He admits that on 04.12.2014 he had first inspected a factory
“Mangla Handles†adjacent to the Respondentâ€s factory but stated that he does not remember if he had prepared any inspection report there or
not. On being directed the witness was unable to produce such inspection report. The testimony of Mr. Dileep Kumar in cross-examination is so
evasive that it fails to inspire confidence. In answer to Q.No.18 he stated that he did not prepare any inspection report on 04.12.2014 but had informed
his boss Mr. Somil Garg, the then Chief Manager and requested him to come to the premises. Mr. Somil Garg has not been examined. He volunteered
that he had only given an oral information to his high officials and did not remember if any inspection report was made. According to him (Q.No.25)
Mr. Pawan Dhuper, brother of Mr. Deepak Dhuper was present during inspection. It was therefore incumbent that an inspection report or panchnama
was prepared at the factory premises of the respondent and got duly signed by Mr. Pawan Dhuper or any of the labourers present. His testimony is
replete with evasive replies.
(x) Mr. Dileep Kumar had lodged FIR on 05.12.2014 at PS Samaypur Badli regarding the incident. The said FIR shows that four number of
photographs during the cause of action, copy of disconnection notice dated 05.12.2014 and CD containing the video of excavation of unauthorized
tapping with softcopy of photographs were also handed over. None of the above material and primary evidence has been requisition before this
tribunal.
(xi) Mr. Dileep Kumar admits in answer to a tribunal question that he visited the police station in the night of 04.12.2014 at around 01.00 a.m. i.e. on
05.12.2014. In Rejoinder it is admitted by the Claimant that the possession of the Respondentâ€s factory was with the police from 05.12.2014 onwards
till 07.12.2014. Therefore, if the police officials had visited the factory premises on 05.12.2014 after the FIR being lodged and had taken possession
thereof, such police officials were material witnesses who ought to have been examined. What is equally shocking is that no incriminating article
evidencing any tampering by the Respondent with the sellerâ€s facilities was found in the factory premises when Mr. Dileep Kumar returned to the
factory with the police after lodging FIR. In answer to Q.No.31, the witness stated that “When we visited the premises with the police after
lodging the FIR in the next morning i.e. 05.12.2014 such regulator was not found at the premises as it was removed by the customer.†This in my
opinion is completely fallacious. One photograph CWl/17 shows a yellow pipeline with a “T†junction which according to the witness is the
unauthorized tapping point. However, in answer to Q.No.46 & 48 he admitted that no such unauthorized point was removed during or after the
inspection. If the officials of the Claimant were working at the factory premises of the Respondent late beyond midnight on 04.12.2014, had lodged a
prompt FIR on the morning of 05.12.2014 and the police had sealed the premises on the same day (Q.No.50) it is impossible that incriminating material
like “T†junction, tapping point, regulator etc. would not be found when the police reached the spot with Mr. Dileep Kumar. In answer to Q.No.62
the witness stated that he had not removed any such incriminating material from the Respondentâ€s premises before reporting to the police on
05.12.2014 and in answer to Q.No.64 he stated that the “T†junction and some pipeline as well as the regulator was also missing from the site at
the time of the visit by the Police. No panchnama or inspection report was prepared during inspection. An oral report only was made to the high
officials in Dec. 2014. No record was maintained regarding the inspection. No acknowledgement was obtained from the representative of the
Respondent or labourers alleged to be present during inspection. In reply to Q.No.69 the witness admits that no independent witness was either
present or called during his inspection. His first affidavit dated 13.04.2016 is wholly silent if Mr. Dileep Kumar conducted the inspection. Therefore, it
is difficult to fathom that the additional affidavit dated 24.05.2016 was prepared by Mr. Dileep Kumar from his memory or by simply seeing the
photographs or video. Even the map Ex.CW-1/7 is totally unsupported by any evidence. There is nothing in the photographs on record to rule out that
these were not taken during inspection of other factory premises as none of the photos show the name of Pawan Casting or the presence of Mr.
Deepak Dhuper who was absent during such inspection. Several premises were inspected and several photos and videos were taken by different
officials whose identity is not known. This completely demolishes the testimony of Mr. Dileep Kumar (CW-1).
(xii) An application dated 24.04.2018 was filed by the Respondent stating that the averments made by Mr. Dileep Kumar in the affidavit dated
23.05.2016 were beyond the pleadings and therefore paragraphs 6 to 19 of the said affidavit should not be read in evidence. Mr. Dileep Kumar was
specifically asked in cross examination why he did not mention the facts contained in his additional affidavit in his first affidavit to which he replied that
“Since I did not think that the above mentioned facts, photographs and videos could be material they did not form part of my first affidavit.†In
view of the most evasive manner in which the witness testified before this tribunal, the fact that no incriminating article evidencing tampering of gas
supply by the Respondent were found in the premises on the early morning of 05.12.2014 and for the reasons aforesaid no reliance can be placed on
what is stated in para 6 to 19 of the additional affidavit of Mr. Dileep Kumar as he has not only been completely discredited in cross-examination but
also his testimony has elements of admitted falsehood.â€
It is evident from the above that the finding of the Arbitral Tribunal that IGL had failed to prove that there was any unauthorized tapping from the
PNG pipeline before the MRS and, that PNG had been sourced from the said tapping point, is based on evaluation of evidence that was led before the
Arbitral Tribunal. The fact that IGL had not filed any affidavit in terms of Section 65B of the Indian Evidence Act, 1872 is not the only ground on
which the evidence (photographs and video) produced by IGLâ€s witness, CW-1, was rejected. It was also noticed that the person who had made the
video recording had not been examined. CW-1 could not have been the person who had recorded the video as apparently, he is visible in that video
recording. The Arbitral Tribunal thus, found that the source of the video recording and the photographs produced was not known because the person
who had made the video recording or captured the photograph had not been examined.
The contention that the finding of the Arbitral Tribunal that the photographs and the video on record do not show that there was any illegal tapping
point before the MRS must be read in its context. CW 1/17 is a photograph that shows a dug-out pit with an exposed pipeline below the surface. It
also shows that another pipe has been joined to that pipe. However, that photograph does not show any metering system. Mr. Agarwal submitted that
photograph CW-1/8 shows the metering system (MRS). That may be correct but it is apparent that there is no photograph that shows both the tapping
point and the MRS, which would clearly show that the tapping point was before the MRS. It was possible for the Arbitral Tribunal to examine both the
photographs (CW 1/17 and CW 1/8) and other photographs to evaluate whether the alleged tapping point shown in the photograph (CW 1/17) was
before the MRS. However, as a matter of fact, there is no photograph, which shows the illegal tapping point before the MRS since there is no single
photograph that shows both, the tapping point as well as the MRS. In order to make the photographs meaningful, IGL would have to establish the
location of the alleged tapping point and the MRS. The matter clearly is one of appreciation of evidence. It cannot be stated that the statement that
there is no such photograph, which shows tapping before the MRS, is incorrect.
It is also evident from the above that the entire controversy sought to be raised before this Court revolves on the question whether the Arbitral
Tribunal had correctly appreciated the evidence. Essentially, IGL seeks that this Court once again re-evaluate the evidence and examine the merits of
the dispute. Clearly, this is beyond the scope of examination under Section 34 of the A&C Act. Perhaps, on evaluation and reappreciation of evidence,
this Court may have not concurred with the decision of the Arbitral Tribunal. However, it is well settled and, has been reiterated by the Supreme
Court in several decisions that the examination under Section 34 of the A&C Act does not entail re-evaluation of the evidence as a first appellate
court and this Court cannot supplant its opinion in place of that of the Arbitral Tribunal. (See P.R. Shah, Share & Stock Brokers (P) Ltd. v. B.H.H.
Securities (P) Ltd: (2012) 1 SCC 594).
In Associated Builders v. Delhi Development Authority: (2015) 3 SCC 49, the Supreme court had observed that “Once it is found that the
arbitrators approach is not arbitrary or capricious, then he is the last word on factsâ€
In the present case, none of the grounds as set out in Section 34(2) or 34(2A) of the A&C Act are established and therefore, the impugned
awards cannot be set aside.
The petition is accordingly, dismissed. The pending application is also disposed of.
