AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
115 paragraphs · 2,533 wordsVinod K. Sharma, J.—This application has been filed for seeking interim measure of prohibition, by granting an interim pro-order,
prohibiting respondent no. 2/Garnishee from releasing the amounts due and payable to the 1st respondent as on the date of this order under the
contract No. CNT/WSS/CWSAP-I/MWB/03/2001 Package III dated 31.10.202 in respect of supply and laying of raw water transmission main
and all other connected works from Vadakuthu to Ongur in the State of Tamil Nadu. The applicant and two others incorporated companies
formed a joint venture for the purpose of participating in the tender floated by the Chennai Metropolitan Water Supply and Sewerage Board. The
applicant was holding a minority share in the joint venture, but played an important role in bringing about the contract.
The entire project was to be completed within a period of 18 months. The joint venture was also awarded the contract relating to operation and
maintenance (O & M) for a period of five years, commencing from the taking over of the works by the Metro under the contract.
That for the purpose of convenient execution, the joint venture decided to divide the entire work of execution barring the supply part and
operation and maintenance into various sub packages of varying lengths and got it executed through other subcontractor.
It is submitted, that the applicant, besides being a partner in the joint venture, offered to take up the execution of a portion of the work and
accordingly, the join venture awarded to the sub package 8 of a length of 28.5 km in favour of the applicant. Under the sub-contract, it was the
obligation of the joint venture company to supply pipes required for the works to the subcontractors.
The case of the applicant is that though the contract was competed and taken over by Metro on 19.01.2005, the joint venture exhibited non
cooperative 5 attitude towards the applicant and did not issue completion certificate and also withheld huge amount payable to it for the work
executed.
That the dispute between the parties to be decided under Clause 3 of Special Conditions of Contract Part I of the contract. On application
made, an Arbitral Tribunal was constituted of three arbitrators. The applicant filed 34 claims, totalling Rs. 9,17,29,391/- (Rupees Nine Crores
Seventeen Lakhs Twenty Nine Thousand Three Hundred and Ninety One only), whereas the joint venture raised counter claim to the tune of Rs.
13,61,00,000/- (Rupees Thirteen Crores and Sixty One Lakhs only).
The case of applicant is that it was kept away in administering the affairs of the joint venture, even though it was one of the shareholders. The
applicant was also aware, that joint venture had substituted bank guarantee for the release of the balance retention money.
It is the case of the applicant, that joint venture submitted a final bill seeking additional payments and according to the applicant, the joint venture
would be receiving about Rs. 10 Crores from Metro, when the defect liability certificate is issued.
This application has been moved to restrain respondent no. 2 from releasing payment to the respondent no. 1, pending arbitration proceedings.
Learned counsel for the applicant vehemently contended, that as the applicant had undertaken sub-contract and filed claim for Rs.
9,17,29,391/- (Rupees Nine Crores Seventeen Lakhs Twenty Nine Thousand Three Hundred and Ninety One only). On the other hand, the claim
filed by respondent no. 1 is frivolous, therefore, the applicant is entitled to interim protection by restraining respondent no. 2 from releasing
payment due to respondent no. 1, pending arbitration proceedings.
The application is opposed by the respondents, by contending, that in the garb of garnishee order, the applicant is seeking injunction against
respondent no. 2 from releasing the amount. This is not permissible in law, in view of the law laid down by the Hon''ble Kerala High Court in the
case of Shoney Sanil Vs. M/s. Coastal Foundations (P) Ltd. and Others, , wherein the Hon''ble Kerala High Court has been pleased to lay down,
that interim injunction can be granted only against the party to arbitration agreement at the instance of other party to the agreement and not against
third party. The operative part of judgment reads as under:
For appreciating the scope of Section 9, the term ''party'' has to be understood, following the definition of the said term in Section 2(1)(h), which
states that unless the context otherwise requires ''party'' means a party to an arbitration agreement. By Section 2(1)(b), ''arbitration agreement''
means an agreement referred to in Section 7, whatever be its form as conceived in Sub-section (2) of Section 5 thereof, arbitration agreement,
going by Sub-section (1) of Section 7, means an agreement by the parties to submit to arbitration, all or certain disputes which have arisen or
which may arise between them in respect of a definite legal relationship, whether contractual or not. Section 9 occurs in Chapter II in Part 1 which
defines an arbitration agreement and provides the power of a judicial authority to refer the parties to arbitration, where there is an arbitration
agreement and provides further, for interim measures by Court. These are the three provisions contained in Chapter II of Part I. So much so, the
interim measures which are conceived by the Legislature while enacting Section 9 are those interim measures which relate to the arbitration
agreement between the parties and being interim, they are to confine to the matters relating to the arbitration agreement between the parties. This
intention is explicit from the opening words of Section 9, which provides for the party to apply for interim measure u/s 9. Therefore, only a party to
the arbitration agreement can apply to a court invoking Section 9, which consists of two parts. Section 9(i) deals with appointment of a guardian
for a minor or a person of unsound mind for the purpose of arbitrary proceedings. Section 9(ii) enumerates five types of interim measures of
protection in respect of the matters enumerated in Clauses (a) to (e) of Section 9(ii). Clause (a) deals with preservation, interim custody or sale of
any goods which are the subject-matter of the arbitration agreement. Clause (b) provides for securing the amount in dispute in the arbitration.
Clause (c) provides for detention, preservation or inspection of any property or thing which is the subject-matter of the dispute in arbitration, or as
to which any question may arise therein and authorising, for any of the aforesaid purposes any person, to enter upon any land or building in the
possession of any party or authorising any samples to be taken or any observation to be made, or experiment to be tried, which may be necessary
or expedient for the purpose of obtaining full information or evidence. A reading of the said provision would show that the orders u/s 9(ii)(c) can
be passed only in relation to the subject-matter of the dispute in arbitration which may be in the possession of any party since it is not the intention
of the Act or any arbitration proceedings as conceived by the law of arbitration, to interfere with or interpolate third party rights. The reason for
this is obvious, that, an arbitral tribunal rests its authority on the agreement between the parties to the arbitration agreement and it is not a Court, to
interfere with third party rights, as may the Courts authorised in that regard, by the law of the land. The issuance of interim injunction or
appointment of receiver provided for under Clause (d) and the residuary provision to issue such interim measure of protection as may appear to be
just and convenient in terms of Clause (e) of Section 9(i) and (ii) have to be read in the backdrop of the extent of jurisdiction which can be
exercised and, this is limited to the parties who are governed by the arbitral agreement and not in excess thereof. On a plain reading of Section 9 of
the Act and going by the scheme of the said Act, there is no room to hold that by an interim measure u/s 9, the rights of third party, holding
possession on the basis of a court sale could be interfered with, injuncted or subjected to proceedings u/s 9 of the Act. Section 9 of the Act
contemplates issuance of interim measures by the court only at the instance of a party to an arbitration agreement with regard to the subject-matter
of the arbitration agreement. This can be only as against the party to an arbitration agreement, or, at best, against any person claiming under him.
The writ petitioner is a third party auction purchaser in whose favour is a sale certificate, followed by delivery of possession. He cannot therefore
be subjected to proceedings u/s 9 of the Act, initiated on the basis of an alleged arbitral agreement between the respondents.
For the foregoing reasons, the impugned order, as against the writ petitioner, is without jurisdiction. I am of the considered view that the
proceedings before the court below, in so far as it is against the writ petitioner is a clear abuse of process of court.
Reliance was also placed on the judgment of the Hon''ble Calcutta High Court in Arch Hi-Rise (P) Ltd. Vs. Yatin Bhimani and Others,
On consideration, I find that this application is totally misconceived. The Hon''ble Supreme Court in the case of Adhunik Steels Ltd. Vs. Orissa
Manganese and Minerals Pvt. Ltd., has laid down as under:
It is true that Section 9 of the Act speaks of the court by way of an interim measure passing an order for protection, for the preservation,
interim custody or sale of any goods, which are the subject matter of the arbitration agreement and such interim measure of protection as may
appear to the court to be just and convenient. The grant of an interim prohibitory injunction or an interim mandatory injunction are governed by
well known rules and it is difficult to imagine that the legislature while enacting Section 9 of the Act intended to make a provision which was de
hors the accepted principles that governed the grant of an interim injunction. Same is the position regarding the appointment of a receiver since the
Section itself brings in, the concept of ''just and convenient'' while speaking of passing any interim measure of protection. The concluding words of
the Section, ""and the court shall have the same power for making orders as it has for the purpose and in relation to any proceedings before it"" also
suggest that the normal rules that govern the court in the grant of interim orders is not sought to be jettisoned by the provision. Moreover, when a
party is given a right to approach an ordinary court of the country without providing a special procedure or a special set of rules in that behalf, the
ordinary rules followed by that court would govern the exercise of power conferred by the Act. On that basis also, it is not possible to keep out
the concept of balance of convenience, prima facie case, irreparable injury and the concept of just and convenient while passing interim measures
u/s 9 of the Act.
The provisions with regard to the directions to the garnishee are governed by Order XXI Rule 46A, 46B and 46C, which read as under:
46A. Notice to garnishee
(1) The Court may in the case of a debt (other than a debt secured by a mortgage or a charge) which has been attached under rule 46, upon the
application of the attaching creditor, issue notice to the garnishee liable to pay such debt, calling upon him either to pay into Court the debt due
from him to the judgment-debtor or so much thereof as may be sufficient to satisfy the decree and costs of execution, or to appear and show cause
why he should not do so.
(2) An application under sub-rule (1) shall be made on affidavit verifying the facts alleged and stating that in the belief of the deponent, the
garnishee is indebted to the judgment-debtor.
(3) Where the garnishee pays in the Court the amount due from him to the judgment-debtor or so much thereof as is sufficient to satisfy the decree
and the costs of the execution, the Court may direct that the amount may be paid to the decree-holder towards satisfaction of the decree and costs
of the execution.
46B. Order against garnishee where the garnishee does not forthwith pay into Court the amount due from him to the judgment-debtor or so much
thereof as is sufficient to satisfy the decree and the costs of execution, and does not appear and show cause in answer to the notice, the Court may
order the garnishee to comply with the terms of such notice, and on such order, execution may issue as though such order were a decree against
him.
46C. Trial of disputed questions where the garnishee disputes liability, the Court may order that any issue or question necessary for the
determination of liability shall be tried as if it were an issue in a suit, and upon the determination of such issue shall make such order or orders as it
deems fit:
Provided that if the debt in respect of which the application under rule 46A is made is in respect of a sum of money beyond the pecuniary
jurisdiction of the Court, the Court shall send the execution case to the Court of the District Judge to which the said Court is subordinate, and
thereupon the Court of the District Judge or any other competent Court to which it may be transferred by the District Judge shall deal with it in the
same manner as if the case had been originally instituted in that Court.
The reading of the provisions shows, that the word used is ""judgment debtor"" and not a party to the litigation, the provisions for invoking the
relief against Garnishee therefore can only be after passing of decree and not during the pendency of the proceedings. The security pending
proceedings can be ordered under the provisions of Order 38 Rule 5 of CPC.
Therefore, in view of the judgment of the Hon''ble Supreme Court, it is only when the conditions stipulated under Order 38 Rule 5 are fulfilled,
that Court can pass order u/s 9 of the Arbitration and Conciliation Act to direct security or attach any property to secure the amount. No order
under directing garnishee to deposit quo amount therefore can be passed.
The application against garnishee would not be competent u/s 9, as the relief against third party is only with respect to the subject matter of
arbitration, when the third party is drawing title through parties to the arbitration.
The applicant therefore has also miserably failed to make out any case for grant of security, as it is yet to be determined as to whether payment
is due to the applicant or counter claim filed by respondents is to be accepted. The application therefore on the face of it, being totally
misconceived, is ordered to be dismissed, but with no order as to the costs.
