High CourtsSingle Bench

KSC Construction Co. vs Union Of India

Delhi High Court · Decided on 19 December 2017 · Citation: (2017) 12 DEL CK 0443

HON’BLE JUDGES
Navin Chawla, J
ACTS & SECTIONS REFERRED
Arbitration And Conciliation Act, 1996 — Section 11, 11(6), 11(6A), 12
RESULT
Allowed
CASE NUMBER
Arbitration Petition No. 751 Of 2017
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

84 paragraphs · 1,566 words

Navin Chawla, J

1.

This petition under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the Act) has been filed seeking appointment

of an Arbitrator for adjudicating the disputes that have arisen between the parties in relation to the work pertaining to Construction of Limited height

subway in lieu of U/M L-Xing no. C-95 at Km. 106/2-3 and C-98 at Km. 108/9-109/0 on DLl-BTl section under ADEN/JHl by cut and cover method

was awarded to the petitioner on 1st October, 2014 for Rs.2,86,93,655/-.

2.

The agreement between the parties has an arbitration agreement in form of clause 64 of the General Conditions of Contract, 2010, which is

reproduced hereinbelow:

“64(1)(i) Demand for Arbitration.-- In the event of any dispute or difference between the parties hereto as to the construction or

operation of this contract, or the respective rights and liabilities of the parties on any mater in question, dispute or difference on any

account or as to the withholding by the Railway of any certificate to which the contractor may claim to be entitled to, or if the Railway fails

to make a decision within 120 days, then and in any such case, but except in any of the 'excepted matters' referred to in clause-63 of these

conditions, the contractor, after 120 days but within 180 days of his presenting his final claim on disputed matters, shall demand in writing

that the dispute or difference be referred to arbitration.â€​

64(1)(ii)(a)â€" The demand for Arbitration shall specify the matters which are in question or subject of the dispute or differences as also

the amount of claim term wise. Only such dispute(s) or difference(s) in respect of which the demand has been made together with counter

claims or set off shall be referred to arbitration and other matters shall not be included in the reference.

64(1)(ii)(a)â€" the Arbitration proceedings shall be assumed to have commenced from the day, a written and valid demand for arbitration is

received by the Railway.

(b) The claimant shall submit his claim stating the facts supporting the claim along with all relevant documents and the relief or remedy

sought against each claim within a period of 30 days from the date of appointment of the Arbitral Tribunal.

(c) The Railway shall submit its defence statement and counter claim(s), if any, within a period of 60 days of receipt of copy of claim from

Tribunal thereafter unless otherwise extension has been granted by Tribunal.

64(1)(iii)â€"No new claim shall be added during proceedings by either party. However, a party may amend or supplement the original,

claim or defence thereof during the course of arbitration proceedings subject to acceptance by Tribunal having due regard to the delay in

making it.

64(1)(iv)- if the contractor(s) does/do not prefer his/ their specific and final claim in writing within a period of 90 days of receiving the

Intimation from the Railways that the final bill is ready for payment he/they will be deemed to have waived his/their claim(s) and the Railway

shall be discharged and released of all liabilities under the contract in respect to these claims.

64(2)â€" Obligation during pendency of arbitrationâ€" Work under the contract shall, unless otherwise directed by the Engineer, continue

during the arbitration proceedings, and no payment due to payable by the Railways shall be withheld on account of such proceedings,

provided, however, it shall be open for Arbitral Tribunal to consider and decide whether or not such work should continue during

arbitration proceedings.

64(3)(a)(i) â€" in case where, the total value of all claims in question added together does not exceed Rs.10,00,000/- (Rupees Ten Lacs

only), the Arbitral Tribunal consist of a sole arbitrator who shall be either the General Manager or a gazetted officer of Railway not below

the grade of JA grade nominated by the General Manger in that behalf. The sole arbitrator shall-be appointed within 60 days from the days

when a written and valid demand for arbitration is received by Railway.

64(3)(a)(ii) --- In cases not covered by Clause 64(a)(1), the Arbitral Tribunal shall consist of a panel of three. Gazetted Rly. Officers not

below JA grade, as the arbitrators'. For this purpose, the Railway will send a panel of more than 3 names of Gazette Rly. Officers of one or

more departments, of the Rly. To the contractor who will be asked to suggest to General Manager upto 2 names out of panel for

appointment as contractor's nominee. The General Manger shall appoint at east one out of them as the contract's nominee and will, also

simultaneously appoint the balance number of arbitrators either from the panel, or from outside the panel, duly Indicating the presiding

arbitrator from amongst the 3 arbitrators so appointed. While nominating the arbitrators it will be necessary to ensure that one of them is

from the Accounts department. An officer of Selection Grade of the Accounts department shall be considered of equal status to the officers

in SA grade of other departments of the Railways for the purpose of appointment of arbitrators.

3.

Counsel for the petitioner submits that though in the petition it has been mentioned that the claim of the petitioner would be Rs.1,05,82,063/-, in fact,

the petitioner would be confining his claim to an amount of Rs.99 lacs. He submits that in view thereof, Clause 64 (3)(A) (i) would be applicable and a

Sole Arbitrator would have to be appointed for adjudicating the dispute between the parties. Counsel for the respondent does not deny that there has

been an amendment in this clause and the figure of Rs.10 lacs has been substituted by Rs.1 crore.

4.

The petitioner invoked the arbitration agreement vide its notice dated 3rd August, 2017, however, having received no reply, the present petition was

filed.

5.

Counsel for the respondent submits that a reply has been filed, however, the same is not on record.

6.

I have perused the copy of reply which has been filed. Reply has been returned back to the counsel for the respondent who may check up with the

Registry and get the same placed on record after removing office objections, if any.

7.

The objection taken by the respondent is that the petitioner, while submitting his final bill had given a No Claim Certificate and it is on that basis that

the final bill had been paid to the petitioner. It is, therefore, submitted that there was a satisfaction of the agreement and there is no dispute that has to

be adjudicated before the arbitral tribunal under the agreement.

8.

Counsel for the petitioner disputes the above position.

9.

In any case, the fact whether there was a full and final satisfaction of the agreement by way of this No Claim Certificate, is a question to be

determined by the Arbitrator. This contention of the respondent is, therefore, not acceptable.

10.

It is further contended by the respondent that certain disputes raised by the petitioner would fall under the ‘excepted matters’ and certain

disputes are beyond the terms of the contract and, therefore, cannot be referred to arbitration.

11.

In my view, even these questions would have to be determined by the Arbitrator. In terms of Section 11 (6A) of the Act, this Court is to confine

with examination to the existence of an Arbitration Agreement. The respondent does not deny the existence of an Arbitration Agreement and

invocation thereof.

12.

In Duro Felguera, S.A. v. Gangavaram Port Limited (2017) 9 SCC 729 Supreme Cou,r twhile examining the scope of Section 11(6A), has held as

under:-

“47. what is the effect of the change introduced by the Arbitration and Conciliation (Amendment) Act, 2015 (hereinafter referred to as

“the 2015 Amendmentâ€) with particular reference to Section 11(6) and the newly added Section 11(6-A) of the Arbitration and

Conciliation Act, 1996 (hereinafter referred to as “the 1996 Actâ€​) is the crucial question arising for consideration in this case.

48.

Section 11(6-A) added by the 2015 Amendment, reads as follows:

11.

(6-A) The Supreme Court or, as the case may be, the High Court, while considering any application under sub-section (4) or sub-section

(5) or sub-section (6), shall, notwithstanding any judgment, decree or order of any court, confine to the examination of the existence of an

arbitration agreement.

(emphasis supplied)

From a reading of Section 11(6-A), the intention of the legislature is crystal clear i.e. the court should and need only look into one aspect-

the existence of an arbitration agreement. What are the factors for deciding as to whether there is any arbitration agreement is the next

question. The resolution to that is simple-it needs to be seen if the agreement contains a clause which provides for arbitration pertaining to

the disputes which have arisen between the parties to the agreementâ€​.

13.

In view of the above, I find no impediment in appointing a Sole Arbitrator for adjudicating the disputes that have arisen between the parties.

14.

I hereby appoint Mr. Amit Chadha, Advocate, D-25, IInd Floor, Vikaspuri, New Delhi-110008, Mobile-9911116613 and 9212729912 as the Sole

Arbitrator. He shall submit his disclosure in terms of Section 12 of the Act before proceeding with the reference. The arbitration shall be held under

the aegis of the Delhi International Arbitration Centre (DIAC). Arbitration procedure and the fee shall be governed by the DIAC Rules.

15.

The petition is allowed in the above terms, with no order as to costs.

Dasti.