Supreme CourtDivision Bench

Maharashtra State Electricity Distribution Company Limited (Msedcl) & Ors vs R Z Malpani

Supreme Court Of India · Decided on 9 April 2026 · Citation: (2026) 04 SC CK 0469

HON’BLE JUDGES
J.K. Maheshwari, J · Atul S. Chandurkar, J
ACTS & SECTIONS REFERRED
Arbitration and Conciliation Act, 1996 — Section 7, 7(1), 7(4)(b), 7(5), 11, 11(6A), 11(7), 16, 21
RESULT
Allowed
CASE NUMBER
Civil Appeal No(S). 4307 Of 2026 (Arising Out Of Special Leave Petition (Civil) No. 36889 Of 2025)
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

142 paragraphs · 9,720 words

J.K. Maheshwari, J

1.

Leave granted.

2.

The instant appeal is directed against the judgment dated 01.10.2025  of  the  Bombay  High  Court  (hereinafter  referred  to  as“High Court”)in Arbitration Application (L) No. 1417 of 2025.

3.

By the impugned order, the High Court disposed of the application filed by the Respondent under Section 11 of the Arbitration  and  Conciliation  Act,  1996  (hereinafter  referred  to  as“1996  Act”)and appointed a sole arbitrator  to  adjudicate upon the disputes and differences between the parties.

FACTS

4.

The Appellant, Maharashtra State Electricity Distribution Company Limited (MSEDCL) is a State Government company, which is a fully-owned corporate entity owned by the Government of Maharashtra. It is an electricity distribution utility which distributes electricity throughout Maharashtra including a few suburbs of Mumbai. The Respondent is a partnership firm engaged in civil construction and other allied businesses.

5.

The Appellant floated a Tender dated 11.08.2021 bearing Code EEC/BND/TECH/42/21-22 for ‘Civil & Interior work –Providing / renovating 134 CFC Centres at various O&M Divisions of SEDCL throughout the State’. (hereinafter referred to as the “Tender”) Total estimated cost of the tender was₹17,41,37,020. The Tender document contained four different constituents, being (i) Instructions to Tenderers & Qualifying Criteria (ii) General Specifications (iii) Technical Specifications (iv) Special Conditions of Contract. (collectively referred to as“Tender documents”) The Tender documents also contained an agreement  pro-forma.  The  timeline  for  the  tender  process  as  per the Tender documents was as follows:

Particulars

Date / Time

Bid Start Date

15.07.2011, 13:00

Bid End Date

06.08.2021, 11:30

Techno-commercial Bid opening

18.08.2021, 15:00

Price Bid opening on

Will be declared later

Winner Selection Date

18.08.2021, 15:30

6.

The Respondent participated in the tender process and submitted a bank guarantee of ₹17,45,100 valid up to 06.03.2022. Respondent then submitted its bid/quotation against the said Tender with a validity of 120 days on 03.09.2021. Upon opening of the techno-commercial and price bids,  the  Appellant,  vide letter  bearing  No.  CEC/CCO/Tech/350 dated  16.11.2022  (hereinafter  referred  to  as“LOI”)accepted  the bid of the Respondent and entrusted the work under the said tender process to the Respondent for a value of₹17,76,19,699.

7.

On 29.11.2022, the Respondent furnished a further bank guarantee to  the tune of₹44,40,500 as security  deposit valid up to 27.05.2023. The Appellant wrote to the Respondent on 13.12.2022 requesting that bank guarantee be furnished on stamp  paper  of₹500  value  instead  of₹100  and  sent  a reminder in that respect on 31.12.2022. The Respondent submitted revised bank guarantee on stamp paper with value of ₹500 on 31.01.2023.

8.

On 02.02.2023, the Holding Company of the Appellant wrote to  the  Executive  Engineer  of  the  Appellant  seeking  correction  in the forwarding letter of the bank guarantees. Pursuant thereto, the  Respondent  sent  a corrected  forwarding  letter  with  the  bank guarantees on 06.02.2023.

9.

Thereafter, the Respondent sent various letters and representations to the Appellant seeking issuance of a Work Order in  terms of the  LOI, but no Work Order  was  issued by  the Appellant. On 08.08.2023, the Respondent submitted revised / renewed bank guarantees as security deposit.

10.

Despite repeated requests being made by the Respondent, the  Work  Order  was  not  issued  by  the  Appellant  and  ultimately, on 05.08.2024, the Respondent terminated the contract, citing Appellant’s failure to hand over the sites for the work to begin. Thereafter, on 30.08.2024, the Respondent issued a notice under Clause 23 of the Special Conditions of Contract in the Tender documents,  seeking reference of  the disputes  to  arbitration  and seeking compensation to the tune of₹4,89,85,500.

11.

On 27.09.2024, the Appellant formally cancelled the Tender and EMD, Security Deposit submitted by the Respondent was duly refunded on 24.10.2024. It is pertinent that the cancellation itself was not challenged by the Respondent availing public law remedies and instead, the Respondent chose to pursue its remedy by means of arbitration under the Tender documents.

12.

On 01.10.2024, the Respondent again invoked the arbitration agreement contained in Clause 23 of the Special Conditions of Contract in the Tender documents. On 04.11.2024, the  Appellant  replied  to  the  Respondent’s  arbitration  notice  and specifically  stated therein that Tender documents  along  with  LOI are not sufficient to form a valid contract or arbitration agreement. On 06.11.2024 and 03.12.2024, the Appellant informed the Respondent that since the EMD and Security Deposit has been refunded, no claims or dues are pending.

13.

At this stage, the Respondent filed an application under Section 11 of the 1996 Act before the High Court being Arbitration Application No. 1417 of 2025, seeking appointment of an arbitrator. Notice was issued by the High Court on 21.01.2025 and service was complete, but on 26.06.2025 and 17.07.2025, the Appellant did not appear before the High Court. The High Court vide the impugned ex-parte order on 01.10.2025 appointed one Mr. Drupad Patil, Advocate as the Sole Arbitrator to adjudicate the disputes between the parties.

FINDINGS OF THE HIGH COURT

14.

The High Court found that the offer made by the Respondent  in  response  to  the  Tender  was  accepted  by  the  LOI dated 16.11.2022 which resulted in a duly concluded contract. Existence of arbitration agreement can be discerned from correspondence  between  the  parties  and  the  scope  of  enquiry  in Section 11 proceedings is limited to  examining  the existence  of  a valid arbitration agreement. It was observed by the High Court that Appellant in their reply to the arbitration notice has not denied  the  existence  of  an  arbitration  agreement,  hence  directed appointment of an arbitrator.

ARGUMENTS ADVANCED

15.

Mr.  Vikas  Singh,  learned  senior  counsel  for  the  Appellants has vehemently argued that there exists no concluded contract between  the  parties,  much  less  an  arbitration  agreement  under the meaning of Section 7 of the 1996 Act, and as such, the High Court has erred in directing appointment of an arbitrator. He submitted the impugned order is patently erroneous in recording that the Appellant had not disputed the existence of an arbitration  agreement  in  their  reply  to  the  notice  under  Section 21 of the 1996 Act. Drawing our attention to the letter dated 04.11.2024  of  the  Appellant,  it  is  stated  that  a specific  plea  was taken about non-existence of arbitration agreement at the very first  instance  by  the  Appellant.  He  further  submitted  that  in  the absence  of  a concluded  contract  between  the  parties,  there  can be no question of existence of an arbitration agreement complying with Section 7 of the 1996 Act. In reference to the Tender documents with the LOI, it is submitted that looking to the material does not evince a concluded contract since the LOI itself is contingent in nature, it provides that a detailed Work Order and formal agreement was to follow and as such it is a precursor to  a  contract  and  not  the  contract  itself.  He  has  placed  reliance on the recent judgement of this Court in State of Himachal Pradesh and Anr. v. OASYS Cybernatics Pvt. Ltd. 2025 SCC OnLine SC 2536 and the judgement of South Eastern Coalfields Limited and Ors. v. S. Kumar’s Associates AKM (JV) (2021) 9 SCC 166 in support of this argument.

16.

The  Appellant  has  argued  that,  assuming  arguendo, even  if the  LOI  is  construed  to  be  a contract  creating  legal  relationship, mere  reference  in  the  LOI  to  the  terms  of  the  Tender  documents would  not  have  the  effect  of  importing  the  arbitration  clause  as contained therein. Further, learned senior counsel has drawn our attention  to  the  judgement  of  this  Court  in  NBCC  (India)  Ltd.  v. Zillion Infra projects Pvt. Ltd. (2024) 7 SCC 174 to submit that mere reference to another document containing an arbitration clause is not sufficient unless the arbitration clause is specifically incorporated in  the subsequent  document. He has submitted, therefore, that the instant appeal deserves to be allowed and the impugned order passed by the High Court warrants interference by this Court.

17.

Appearing  for  the  Respondents,  learned  counsel  Mr.  Abhijit A. Desai has argued with equal force that the instant appeal warrants dismissal since an order appointing an arbitrator is final and non-appealable as per Section 11(7) of the 1996 Act. He submits  that  this  Court  in  a  special  leave  petition  arising  out  of such appointment, must exercise caution while interfering against appointment of an arbitrator and the tribunal has the jurisdiction  to  decide  on  its  jurisdiction  under  Section  16  of  the 1996 Act in light of the principle of Kompetenz-Kompetenz. He has submitted that the instant case is a feeble attempt at delaying arbitration  proceedings  by  the  Appellant  who  has  chosen  not  to appear  before  the  High  Court  despite  adequate  service  of  notice. He has further argued that the existence of an arbitration agreement is clear from a conjoint reading of: (i) Clause 23 of the Special Conditions of the Tender documents; (ii) Respondent’s bid dated 03.09.2021; (iii) LOI dated 16.11.2022 accepting the Respondent’s bid. It is submitted that furnishing and repeated renewal of bank guarantees by the Appellant, exchange of correspondence regarding renewal of bank guarantees would further show that there was a concluded contract between the parties.

18.

Since an arbitration agreement can be formed by exchange of communication under Section 7(4)(b) of the 1996 Act, a formally executed commercial contract is not necessary and tender conditions containing an arbitration clause, once accepted and acted upon, form a valid arbitration agreement under Section 7 of the 1996 Act. Learned counsel has placed reliance on the judgement  of  this  Court  in  Office  for  Alternative  Architecture v. Ircon Infrastructure and Services Ltd. 2025 SCC OnLine SC 1098 to argue that the scope of scrutiny by the Court in an application under Section 11 of the  1996 Act is circumscribed by sub-section  (6A) thereto  and as such, unnecessary judicial interference in arbitration proceedings is not warranted. Since the question relates to formation of the contract, it must be left to the arbitrator to decide in an application under Section 16 of the 1996 Act as held by this Court in Maharshi Dayanand University v. Anand Coop. L/C Society Ltd. (2007) 5 SCC 295 Much emphasis has been laid on the judgement of this Court in UNISSI (India) (P) Ltd. v. Post Graduate Institute of Medical Education and Research (2009) 1 SCC 107 to argue that where the tender conditions contain an arbitration clause and the tender has been acted upon by the parties, it cannot be said that there existed no concluded contract and consequently, no arbitration agreement. Lastly, it has been submitted that cancellation of the tender itself does not extinguish the arbitration agreement between the parties and the said  cancellation  is  a subject  matter  of  arbitration.  As  such,  he has urged that the instant appeal warrants dismissal.

ANALYSIS

19.

After hearing learned counsel for the parties and having gone through the documents on record, the short question which falls  for  our  consideration  in  the  instant  appeal  is  whether,  on  a prima facie view, there exists an arbitration agreement between the parties and as such, whether the reference to arbitration under Section 11 by the High Court warrants interference by this Court?

20.

The law on appointment of an arbitrator under Section 11 of the  1996 Act has  undergone windfall change in  the recent  years, especially after the insertion of sub-section 6A therein w.e.f. 23.10.2015 which confines the Court’s jurisdiction to the examination of existence of an arbitration agreement. Initially, this Court in Vidya Drolia & Ors. v. Durga Trading Corporation, (2021) 2 SCC 1 had  developed  what  came  to  be  known  as  the  ‘ex- facie’ test, holding in clear terms that while scope of judicial review and interference by Courts at the Section 11 stage is extremely limited, the Courts may interfere where it is ‘manifestly and ex-facie certain that the arbitration agreement is non- existent, invalid or the disputes are non-arbitrable’. The ‘eye of the  needle’  test  was  propounded  by  the  judgement  of  this  Court in NTPC Ltd. v. SPML Infra Ltd. (2023) 9 SCC 385 to hold that limited scrutiny at the pre-arbitral stage by the referral court through the ‘eye of the needle’  must  be  done  in  order  to  protect  the  parties  from  being forced to arbitrate a matter which is demonstrably non-arbitrable. Subsequently,  however,  a co-ordinate  bench  of  this  Court  in  SBI General Insurance Co. Ltd. v. Krish Spg., (2024) 12 SCC 1 relying on the seven-judge bench decision in Interplay Between Arbitration Agreements under Arbitration Act, 1996 & Stamp Act, 1899, In re, (2024) 6 SCC 1 has held that the ‘ex-facie meritless’ and ‘eye of the needle’ tests cannot be said to be in conformity with the principles  of  modern  arbitration  and  they  would  not  apply  after the decision of the seven-judge bench, since even though they endeavour to minimise judicial interference, yet require the Courts  to  enter  into  a factual  examination  of contested facts  and evidence,  however  minimal.  Relevant  portion  of  the  judgement  in SBI General Insurance Co. Ltd. is quoted herein for reference:

“114. In view of the observations made by this Court in In Re  :  Interplay  (supra),  it  is  clear  that  the  scope  of  enquiry at the stage of appointment of arbitrator is limited to the scrutiny of prima facie existence of the arbitration agreement, and nothing else. For this reason, we find it difficult to hold that the observations made in Vidya Drolia (supra) and adopted in NTPC v. SPML (supra) that the jurisdiction of the referral court when dealing with the issue of “accord and satisfaction” under Section 11 extends to weeding out ex-facie non -arbitrable and frivolous disputes would continue to apply despite the subsequent decision in In Re : Interplay (supra).

….

118.

Tests like the “eye of the needle” and “ex-facie meritless”, although try to minimise the extent of judicial interference,  yet  they  require  the  referral court  to  examine contested facts and appreciate prima facie evidence (however limited the scope of enquiry may be) and thus are not  in  conformity  with  the  principles  of  modern  arbitration which place arbitral autonomy and judicial non- interference on the highest pedestal.”

21.

As  such,  the  pronouncement  of  this  Court  in  SBI  General Insurance Co. Ltd. (Supra) lays down a clear and comprehensive explanation about the scope of examination at the stage of Section 11 proceedings: it is limited to finding a prima facie existence of arbitration agreement and nothing beyond it. Questions  of  ‘accord  and  satisfaction’,  limitation,  dishonesty  and frivolity, arbitrability of the subject-matter are to be left to the adjudication by the arbitral tribunal under Section 16 of the 1996 Act which is a reflection of the doctrine of ‘Kompetenz- Kompetenz’ or ‘compétence de la compétence’. It is therefore incumbent  upon  us  to  only  examine  the  prima  facie  existence  of an arbitration agreement.

22.

At the outset, it would be apposite to extract the arbitration agreement purportedly contained in Clause 23 of the Special Conditions of Contract in the Tender documents. It reads as thus:

“23. Arbitration Clause:

a. The matters to be determine by the Chief Engineer:

All disputes and differences of any kind whatsoever arising out of or in connection with the contract, whether during the progress of the work or after its completion and whether before or after the determination of the contract shall be referred by the contractor to the C. E. and the C. E. shall [within 120 days) after receipt of the contractor's representation make and notify decisions of all matters referred to by the contractor in writing.

b. Demand for Arbitration:

i) In the event of any dispute or difference between the parties hereto as to the construction or operation of this contract, or the respective rights and liabilities of the parties on any matter in question, the dispute or difference on any account or as to the withholding by M.S.E.D.C.LTD. of  any  certificate  to  which  the  contractor  may  claim  to  be entitled to or if the C. E. fails  to make a decision (within 120 days), then and in any such case, the contractor (after 120 days) but within (180 days) of his presenting his final claim on disputed matters, shall demand in writing that the dispute or difference to be referred to arbitration.

ii)  The demand for arbitration shall specify the matters which are in question, or subject of the dispute or difference as also the amount of claim item wise. Only such dispute(s) or difference(s) in respect of which the demand has been made, together with counter claims or set off, shall be referred to arbitration and other matters shall not be included in the reference.

a) The arbitration proceedings shall be assumed to have commenced from the day, a written and valid demand for arbitration is received by the Company.

b) The claimant shall submit his claim stating the facts supporting the claims along with all relevant documents and the relief or remedy sought against each claim Within a period of 30 days from the date of appointment of the Arbitral Tribunal.

c) The  Company  shall  submit  its  defense  statement and counter claim(s), if any, within a period of 60 days of receipt of copy of claims from the Tribunal thereafter unless otherwise extension has been granted by the Tribunal.

iii) No new claim shall be added during the proceedings by either  party.  However,  a  party  may  amend  or  supplement the original claim or defense thereof during the course of arbitration proceedings subject to acceptance by Tribunal having due regard to the delay in making it.

iv) If  the contractor(s) does/do  not prefer his/their  specific and  final  claims  in  writing,  within  a  period  of  90  days  of receiving the intimation from the Company, that the final bill  is  ready  for  payment,  he/they  will  be  deemed  to  have waived his/their claim(s) and the Company shall be discharged and released of all liabilities under the contract in respect of these claims.

c. Obligation during pendency of Arbitration:

Work under the contract shall, unless otherwise directed by the Engineer, continue during the arbitration proceedings, and no payment due or payable by the Company shall be withheld on account of such proceedings, provided, however,  it  shall  be  open  for  Arbitral  Tribunal  to  consider and decide whether or not such work should be continued during arbitration proceedings.

In cases where the total value of all claims in question added together does not exceed Rs.1,00,00,000/- (Rs. One Crore) the Arbitrate Tribunal shall consist of a Sole Arbitrator  who  shall  be  either  the  C.E.  of  the  Company  or serving  or  retired  officer  of  the  Company/Government  not below the grade of C.E. or equivalent nominated by the Chairman of the Company in that behalf. The Sole Arbitrator shall be appointed within 60 days from the day when a written and valid demand for arbitration is received by the Company.

i) In cases the value of the claim exceeds Rs. 1,00,00,000/- (Rs. One Crore) as above, the Arbitral Tribunal shall consist of panel of 3 serving or retired officers of M.S.E.D.C.LTD. /Govt not below the grade of C.E./CA.O. as the Arbitrators. For this purpose, the Company will send a panel of more than 3 names of arbitrators of one or more department of the Company/Govt. to the contractor who will be asked to suggest to the Chairman at least 2 names for appointment as contractor's nominee. The Chairman shall appoint at least one of them as the contractor's nominee and will also appoint  the  balance  number  of  arbitrators  either  from  the panel or from outside the panel, duly indicating the presiding arbitrator from amongst the three [3) arbitrators so appointed. While nominating arbitrators, it will be necessary  to  ensure  that  one  of  them  is  or  has  worked  in Accounts department.

ii)  If one or more arbitrators appointed as above refuses to act as arbitrator, withdraws from his office as arbitrator or vacates his/their office/offices or is/are unable or unwilling to perform his functions as arbitrator for any reason whatsoever or dies or in the opinion of the Chairman fails to  act  without  undue  delay. The Chairman shall appoint new arbitrators to act in his/their place in the same manner in which the earlier arbitrator/s had been appointed. Such reconstituted Tribunal, may, as its discretion proceed with the reference from the stage at which it was left by the previous arbitrator(s).

iii) The Tribunal shall have powers to call for such evidence by  way  of  affidavits  or  otherwise  as  the  Arbitral  Tribunal shall  think  proper,  and  it  shall  be  the  duty  of  the  parties hereto to do or cause to be done all such things as may be necessary to enable the Arbitral Tribunal to make the award without any delay.

iv) While appointing arbitrator(s) as above, due care shall be taken that he/they is/are not the one/those who had an opportunity to deal with the matters to which the contract relates or who in the course of his/their duties as Company's servant(s) expressed views on all or any of the matters under dispute or differences. The proceedings or the Arbitral  Tribunal  or the award made by such  Tribunal will, however, not be invalid merely for the reason that one or more arbitrator had, in the course of his service, opportunity  to  deal  with  the  matters  to  which  the  contract relates  or  who  in  the  course  of  his/their  duties  expressed views on all or any of the matters under dispute.

v) Arbitral award shall state item wise, the sum and reasons upon which it is based.

vi) A party  may  apply  for  corrections  of  any  computational errors, any typographical or clerical errors or any other error of similar nature occurring in the award and interpretation  of  specific  point  of  award  to  tribunal  within 30 days of receipt of the award.

vii) A party  may  apply  to  Tribunal  within  30  days  of receipt of award to make an additional award as to claims presented in the arbitral proceedings, but omitted from the arbitral award.

viii) In case of the Tribunal, comprising of three members any ruling or award shall be made by a majority of Members of Tribunal. In the absence of such a majority, the views of the Presiding Arbitrator shall prevail.

ix) Where the arbitral award is for payment of money, no interest shall be payable on whole or any part of the money  for  any  period  till  the  date  on  which  the  award  is made.

x) The cost of the arbitration shall be borne equally by the respective parties.  The  cost  shall inter-alia  include  fees  of the arbitrators as per the rates fixed by the Company from time  to  time.  Provided  that  the  fees  payable  per  arbitrator for claims up to Rs. One Crore, shall not exceed Rs. 2000/- per  sitting  subject  to  a  maximum  of  Rs.  25,000/-  and  the fees  payable  per  arbitrator  for  claims  over  Rs.  One  Crore, shall not exceed Rs. 2000/- per sitting subject to a maximum of Rs. 50,000/-. Provided further that the arbitrators who are in service of Govt/M.S.E.D.C. LTD. shall draw fees at half of the rates mentioned above.

xi) Company shall maintain a list of arbitrators. The Chairman shall have full powers to delete or add the name of the arbitrators in the list or to make amendments to the said list as per his discretion.

xii) The arbitral proceedings should be completed and the award be  finalized  within  one  year  ff om the  date of appointment of arbitrators.

xiii) Subject  to  the  provisions  as  aforesaid,  Arbitration & Conciliation Act,1996 and the rules there under, and any statutory  notification  thereof  shall  apply  to  the  arbitration proceedings under this clause.”

23.

The ‘Instructions to Tenderers’ contained in the Tender documents at Clause 23 provides that the successful tenderer will  have  to  execute  an  agreement  with  the  Company  (Appellant) in the Company’s standard proforma. It reads as thus:

“23.0 The successful tenderer will also have to execute an agreement with the Company in Company’s standard proforma. The cost of stamp paper shall be borne by the contractor. (The  value of Stamp paper for agreement is Rs. 500/- up to ten lakh Plus RS. 100 for every one lakh or part there of above Rs Ten Lacks)”

24.

Clause 42 of the ‘Instructions to Tenderers’ contained in the Tender documents provides that in case the work is cancelled before starting the work for any reason after placement of work order, only E.M.D. / S.D. shall be refunded and no other claim in this respect shall be entertained. Clause 39 of the ‘Instructions to Tenderers’ in the Tender documents provides that the‘Instructions to Tenderers’ shall form part of the contract.

25.

The entire thrust of the argument of the Respondent is that the arbitration clause contained in Clause 23 of the Special Conditions of Contract in the Tender documents has been incorporated in the contract which has been concluded by the Appellant’s LOI dated 16.11.2022. The LOI  references the Tender documents and in the initial paragraphs, provides that the terms and conditions of the contract as per the reference documents shall  be  interpreted  by  reading  together  with  them  the  terms  of the  LOI  itself  and  in  case  of  conflict,  the  terms  of  the  LOI  shall prevail. The said portion of the LOI is quoted herein for reference:

“…

With reference to the above, on behalf of MSEDCL tender No. EEC/BND/TECH/T-42/2021-22 is invited for providing / renovating the CFC center at various O&M Division of MSEDCL  throughout the  State vide E-Tender Notice PR  No. 295/2021  dt.  14.7.2021.  In  this  regards  the  undersigned is pleased to inform you that your offer for the above work covered  under  the  scope  of  Schedule-B  of  the  said  tender has been accepted and work covered under the scope of the contract is entrusted to you subject to the following terms and conditions.

Notwithstanding  that  reference  are  given  above,  the  terms and conditions and specifications of contract shall be interpreted by reading together the terms and conditions, specifications and contents of this Letter of intent as below. In case of any deviations with the contents of this Letter of intent from corresponding conditions in the above said tender specifications or contents of the letter under reference  as  read  and  interpreted  up  to  date,  the  contents of this Letter of intent shall prevail.”

26.

In the concluding portion of the LOI, it is stated that the LOI has been issued to the Respondent to start with preliminaries and to start the work on the issuance of the detailed work order. The said portion of the LOI is quoted herein for reference:

“…

This letter of intent is issued to enable you to start with preliminaries to start the work as soon as the detailed work order is issued. ..."

27.

It  is  the  admitted  case  of  the  parties  that  pursuant  to  the LOI and in terms of Clause 23 of the ‘Instructions to Tenderers’ of the Tender documents, neither any work order was issued to the Respondent  nor  any  formal  agreement  was  entered  into  between the parties on the proforma of the Appellant. It is therefore required to be examined as to whether any agreement to arbitrate

has formed at this stage in order to meet the requirement of Section 7 of the 1996 Act. The said section is relevant for this purpose and is therefore quoted below for reference:

“7. Arbitration Agreement:

(1) In this Part, ‘arbitration agreement’ means an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.

(2) An arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement.

(3) An arbitration agreement shall be in writing.

(4)  An  arbitration  agreement  is  in  writing  if  it  is  contained in–

(a) a document signed by the parties;

(b) an exchange of letters, telex, telegrams or other means of telecommunications including communication through  electronic  means  which  provide  a record  of  the agreement; or

(c) an exchange of statement of claim and defence in which  the  existence  of  the  agreement  is  alleged  by  one party and not denied by the other.

(5) The reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract.”

28.

Section 7(1) of the 1996 Act posits that there must be a defined ‘legal relationship’ between the parties and the agreement to  arbitrate  may  be  contractual  or  not.  As  such,  conclusion  of  a contract might not be necessary for that purpose and what needs to  be seen is whether  the parties were  ad idem  in their  intention to refer a dispute to arbitration as evinced from their communication ‘Govind Rubber Ltd. v. Louis Dreyfus Commodities Asia (P) Ltd., (2015) 13 SCC 477’. A distinction, however, is drawn when the arbitration agreement is contained in some document which is sought to be incorporated within another. Section 7(5) is attracted  in  such  a situation  and  it refers to  the  incorporation  of an arbitration agreement contained in some document into a‘contract’ which has to be in writing. The use of the word‘contract’ when dealing with incorporation of an arbitration agreement from some other document is intentional and consequential. Since in the present appeal the Respondent’s case is  that  the  LOI  incorporates  the  arbitration  agreement  from  the terms of the Tender documents, both the contractual nature of the  LOI  as  well  as  the  validity  of  incorporation  becomes  relevant for our examination.

29.

In this context, at the very threshold it must be observed that the finding of the High Court that Appellant in its reply dated  04.11.2024  to  the  Respondent’s  arbitration  notice ‘did  not question the formation of arbitration agreement on any ground other than the fact that the project did not proceed further’ is prima facie  erroneous and stares at  the  face  of the  record, and is liable to be set aside. It has been contended in plain terms by the Appellant in its reply dated 04.11.2024 that there was no concluded  contract  between  the  parties  and  that  the  LOI  cannot bind either party to a contract, it is merely indicative of a party’s intention to enter into a contract. There is, therefore, no admission of any concluded contract, much less an arbitration agreement between the parties by the Appellant in its reply dated 04.11.2024. The Appellant has throughout maintained that there was  no  concluded  contract  between  the  parties  and  as  such,  no reference  to  arbitration  can  be  made  under  Clause  23  of  Special Conditions of Contract contained in the Tender documents merely because of a general reference to the Tender documents in the LOI.

30.

A co-ordinate bench of this Court in OASYS Cybernatics (Supra)  has  exhaustively  discussed  the  effect  of  a letter  of  intent pursuant  to  a tender,  its  legal  character  and  the  nature of  rights flowing there from. Relevant paragraphs of the said judgement are quoted herein for reference:

“11. The first issue that falls for our determination concerns the legal character of the LoI dated 02.09.2022 and the nature of rights, if any, accrued to the Respondent- company thereunder.

12.

This question goes to the root of the matter, and is not one of mere semantics, i.e. ascertaining whether the issuance of the LoI created a concluded contract capable of enforcement, or whether it remained a conditional and inchoate  expression  of  intent,  leaving  the  Government  free to reassess its position prior to formal acceptance. The answer defines the legal threshold for the Appellant-State's power to cancel and the Respondent-company's entitlement to protection.

13.

The jurisprudence on the subject is neither nascent nor unsettled. A catena of decisions starting from Rajasthan Cooperative Dairy Federation Ltd. v. Maha Laxmi Mingrate Marketing Service (P) Ltd., through Dresser Rand S.A. v. Bindal Agro Chem Ltd., to Level 9 Biz Pvt. Ltd. v. HP Housing & Urban Development Authority, this Court has consistently  held  that  an  LoI  is,  in  the  ordinary  course,  a precursor to a contract and not the contract itself.

14.

In Dresser Rand (supra), it was re-stated with clarity that “a letter of intent merely indicates a party's intention to enter into a contract with the other party  in  future.  A letter  of  intent  is  not  intended  to bind either party ultimately to enter into any contract.” The same principle animated Rajasthan Cooperative Dairy Federation (supra), where this Court observed that until the offer is accepted unconditionally and the preconditions are satisfied, “no binding legal relationship” comes  into  existence. The rationale  is  thus simple  but  fundamental:  the  law  of  contract  distinguishes between a promise to make a promise and a promise performed. The former is not legally binding until its contingencies are fulfilled.

15.

These authorities collectively articulate a coherent doctrine:  an  LoI  creates  no  vested  right  until  it  passes  the threshold of final and unconditional acceptance. It is but a“promise in embryo,” capable of maturing into a contract only upon the satisfaction of stipulated preconditions or upon the issue of an LoA. A bidder's expectation that such a contract  will  follow  may  be  commercially  genuine,  but  it is not a juridical entitlement. To hold otherwise would be to bind  the State  in contract before it has consciously  chosen to be bound—a proposition foreign to both contract law and public administration.

16.

Turning  then  to  the  LoI  before  us,  its  conditionality  is beyond doubt. As noticed heretofore in para 5.7, it required the Respondent-company to:

(i) undertake compatibility testing of its proposed ePoS devices at NICSI, Hyderabad;

(ii) provide a live demonstration of the devices with NIC's application before the Directorate at Shimla;

(iii) execute a formal agreement only after successful completion of the aforesaid steps; and

(iv) furnish a detailed MRP and landing cost of the devices and their major components.

17.

Each requirement was framed as a condition precedent; the LoI itself stated that a“final award letter”would issue only after the successful completion of these tasks. This language admits of no ambiguity. The tender architecture was sequential: testing, demonstration, acceptance, then execution. It was never contemplated that the LoI would operate as the contract itself.

18.

The  cumulative  effect  of  the  foregoing  analysis  is  that the LoI was no more than a provisional communication signifying the Appellant-State's intent to enter into a formal arrangement upon fulfilment of certain technical and procedural conditions. The acceptance of tender and the consequential formation of a binding contract were contingent upon satisfaction of these prerequisites. The Respondent-company's reliance upon the LoI as a source of vested contractual rights is, therefore, wholly misplaced.

19.

As a result, the First Issue is answered in the negative. We have no difficulty in holding that the LoI did not give rise to any binding or enforceable rights in favour of the Respondent-company.”

31.

It is settled law that a letter of intent does not, in and of itself, create a legal relationship or contractual obligations until there  is  a  clear,  unambiguous  final  acceptance  by  the  parties.  It is an expression of one party’s intent to enter into a contract with the other party in the forthcoming future. When the intent of the parties can be evinced from the letter of intent or the tender specifications and it is clear that the letter of intent is to be followed  by  a final  award or  a concluded agreement,  it  cannot  be said  that  the  letter  of  intent  itself  binds  the  parties  to  the  terms of the tender. Contractual obligations cannot be foisted upon a party without a clear indication of its intent to enter into a binding concluded contract. Therefore, what needs to be distinguished is whether the intent of the parties is to make a‘promise’ or a ‘promise to make a promise’. We are mindful of the fact  that  a tender  is  essentially  in  the  nature  of  an  ‘invitation  to offer’ and submission of a bid by the tenderer is an ‘offer’. By means  of  a letter  of  intent,  however,  it  must  be  examined  by  the Court whether the party extending the letter of intent is in consensus  ad  idem with  the  other  party  and  intends  to  create  a conclusive and binding agreement.

32.

Further, in South Eastern Coalfields Ltd. (Supra), this Court  held  that  the  question  as  to  whether  a contract  had  been concluded between the parties can be discerned by the notice inviting tender, the letter of intent and the conduct of parties. Relevant paragraph of the said judgement is quoted herein for reference:

“22. We would like to state the issue whether a concluded contract had been arrived at inter se the parties is in turn dependent  on  the  terms  and  conditions  of  the  NIT,  the  Lol and the conduct of the parties. The judicial views before us leave little doubt over the proposition that an Lol merely indicates a party's intention to enter into a contract with the  other  party  in  future.  No  binding  relationship  between the parties at this stage emerges and the totality of the circumstances  have  to  be  considered  in each  case.  It  is  no doubt possible to construe a letter of intent as a binding contract  if  such  an  intention  is  evident  from  its  terms.  But then the intention to do so must be clear and unambiguous as it takes a deviation from how normally a letter of intent has  to be  understood.  This  Court did  consider  in  Dresser Rand S.A. case that there are cases where a detailed contract is drawn up later on account of anxiety to start work on an urgent basis. In that case it was clearly stated that  the  contract  will  come  into  force  upon  receipt  of  letter by the supplier, and yet on a holistic analysis - it was held that the Lol could not be interpreted as a work order.”

33.

Applying  the  said  principles  of  law  to  the  facts  of  this  case, we are in agreement with the argument of the Appellant that the LOI in the facts of the instant case was a promise to make a promise and not a promise itself and no agreement had concluded  between  the  parties.  The  word  ‘contract’  as  defined  in Clause 1(c) of the Special Conditions contained in the Tender documents is ‘the document forming Notice Inviting Tenders, Tender Form, General Conditions of Contract, Technical Specifications, priced schedule of items, contract agreement and drawings  and  any  other  document  which  may  be  included  at  the time  of  signing  of  contract  agreement  along  with  acceptance  of  the contract thereof together’.This definition  incorporates the tender framework  under  Clause  23  of  the  ‘Instructions  to  Tenderers’  of the Tender documents, which posits that an agreement will be entered into by the Appellant with the successful bidder.

34.

The LOI provided that the work under the contract is entrusted to the Respondent subject to terms and conditions and as  per  clause  2 of  the  LOI,  the  time-limit  to  complete  the  entire work  was  six  months  from  the  date  of  handing  over  of  the  sites. Pertinently, the Appellant never handed over the sites to the Respondent.  Clause  3 provided  that  security  deposit  to  the  tune of 5% of order value, being ₹88,81,000 must be deposited by means of demand draft or F.D.R. or B.G. of any nationalized bank within 10 days from the date of receipt of LOI. Alternatively, 50% of the security deposit, amounting to ₹44,40,500 shall be deposited in the said form and the balance amount of₹44,40,500 may be deducted from the R.A. bill. Clause 7 of the LOI provides for the requirement to obtain insurance in specific form as mentioned therein. At the end of the LOI, it is mentioned that the LOI  has  been  issued  to  enable  the  Respondent  to  start  with  the preliminaries  so  that  work  may  be  initiated  as  soon  as  the  work order is issued. It contemplates a work order to be issued at a subsequent stage.

35.

Neither  the  specifications  of the Tender  documents,  nor  the LOI provides that the LOI itself would result in a concluded contract. Rather, the Tender documents in Clause 23 of the‘Instructions  to  Tenderers’  specifically  provides  for  an  agreement to be entered into between the Appellant and the successful tenderer and same is the import of Clause 1(c) defining the word‘contract’. The intent behind the LOI is explicitly clarified as merely to ensure that preliminaries are complied with so that the work may begin upon issuance of a work order. No such work order was issued pursuant to the LOI. On this count, it is stressed by the Respondent that it had submitted the requisite security deposit by means of bank guarantees and they were renewed from time to time. However, neither the LOI nor the Tender documents contemplate that upon submission of bank guarantees,  the  contract  would be said  to  be concluded, creating a binding legal relationship. Rather, they both contemplate the issuance  of  a work  order  and  the  signing  of  an  agreement;  mere completion of preliminaries cannot be said to be sufficient to form a binding  legal  relationship  unless  specified  in  the  terms  of  the tender specifications. From a reading of the LOI, the clauses relating  to  submission  of  security  deposit  and  insurance  clearly show the tender framework, where after acceptance of the bid, work was entrusted to the Respondent subject to terms and conditions  which  were  procedural  in  nature,  contemplating  that at a later stage, a final work order was to be issued and an agreement was to be entered into between the parties.

36.

In  the  above  conspectus  of  facts,  from  a  holistic  reading  of the Tender documents, the LOI and other subsequent communication  between  the  parties,  the  LOI  does  not  evince  the commercial intention of the Appellant to create a binding legal relationship, it informs the Respondent that the work was entrusted to them upon opening of bids and lays down preliminary conditions to be fulfilled in contemplation of a future work order and agreement in order to ensure that prior to the work  order  being  issued,  everything  is  set  in  place  and  the  work may begin at once upon such issuance. As such, it cannot be said that the LOI had the effect of creating a binding legal relationship between the parties.

37.

In  the  instant  case,  the  Appellant  argues  further  that  even assuming arguendo that the LOI itself can be considered a source of binding legal relationship between the parties, the LOI has made a general reference to the Tender documents and such a general  reference  cannot  have  the  effect  of  ‘incorporation’  of  the arbitration clause contained therein, in light of Section 7(5) of the 1996 Act. Section 7(5) provides that ‘The reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract.’.

38.

Reference in this respect has also been made to the judgement of this Court in NBCC (India) Ltd. (Supra). In the said judgement, this Court dealt with facts which are somewhat similar to the instant appeal; the arbitration clause was contained in the ‘Request for Proposal’ in the tender documents and the contract was awarded to the Respondent therein by means of issuance of a letter of intent which made the terms and conditions of the said tender documents applicable to the letter of intent  as  well.  This  Court  drew  a distinction  between  ‘reference’and  ‘incorporation’  of  an  arbitration  clause,  and  after  discussing the  decisions in  M.R.  Engineers  & Contractors  (P) Ltd.  v.  Som Datt Builders Ltd., (2009) 7 SCC 696 and Inox Wind Ltd. v. Thermocables Ltd., (2018) 2 SCC 519 found that the arbitration clause contained in some document may be incorporated in the contract between the parties  only  by  a specific  reference  to  the  arbitration  clause.  The intent  of  the  parties  to  incorporate  the  arbitration  clause  has  to be explicitly clear and a mere general ‘reference’ to the tender conditions would not suffice. Relevant paragraphs of the said judgement are quoted herein for reference:

“16. The issue is no more res integra. The provisions of sub-section (5) of Section 7 of the Arbitration Act have been considered by this Court in M.R. Engineers & Contractors [M.R. Engineers & Contractors (P) Ltd. v. Som Datt  Builders  Ltd.,  (2009)  7 SCC  696  : (2009)  3  SCC  (Civ) 271] . After considering the relevant passages from Russell on Arbitration and various English judgments, this Court held thus : (SCC p. 707, para 24)

“24. The scope and intent of Section 7(5) of the Act may therefore be summarised thus—

(i) An arbitration clause in another document, would get incorporated into a contract by reference, if the following conditions are fulfilled;

(1) the contract should contain a clear reference to the documents containing arbitration clause,

(2) the reference to the other document should clearly indicate an intention to incorporate the arbitration clause into the contract,

(3) the arbitration clause should be appropriate, that is capable of application in respect of disputes under the contract and should not be repugnant to any term of the contract.

(ii) When the parties enter into a contract, making a general reference to another contract, such general reference  would  not  have  the  effect  of  incorporating  the arbitration clause from the referred document into the contract between the parties. The arbitration clause from another contract can be incorporated into the contract (where such reference is made), only by a specific reference to arbitration clause.

(iii)  Where  a  contract  between  the  parties  provides  that the execution or performance of that contract shall be in terms of another contract (which contains the terms and conditions relating to performance and a provision for settlement of disputes by arbitration), then, the terms of the referred contract in regard to execution/performance alone will apply, and not the arbitration agreement in the referred contract, unless there is special reference to the arbitration clause also.

(iv) Where the contract provides that the standard form of terms and conditions of an independent trade or professional institution (as for example the standard terms and conditions of a trade association or architects association) will bind them or apply to the contract, such standard form of terms and conditions including any provision for arbitration in such standard terms and conditions, shall be deemed to be incorporated by reference. Sometimes the contract may also say that the parties  are  familiar  with  those  terms  and  conditions  or that the parties have read and understood the said terms and conditions.

(v) Where the contract between the parties stipulates that the conditions of contract of one of the parties to the contract shall form a part of their contract (as for example the general conditions of contract of the Government where the Government is a party), the arbitration clause forming part of such general conditions of contract will apply to the contract between the parties.”

17.

It could thus be seen that this Court has held that when the parties enter into a contract, making a general reference to another contract, such general reference would not have the effect of incorporating the arbitration clause from the referred document into the contract between the parties. It has been held that the arbitration clause from another contract can be incorporated into the contract (where such reference is made), only by a specific reference to arbitration clause. It has further been held that where a contract between the parties provides that the execution or performance of that contract shall be in terms of another contract  (which  contains  the  terms  and  conditions  relating to performance and  a provision  for  settlement  of  disputes by arbitration), then, the terms of the referred contract in regard to  execution/performance  alone will  apply,  and  not the arbitration agreement in the referred contract, unless there is special reference to the arbitration clause also.

18.

This Court further held that where the contract provides that the standard form of terms and conditions of an independent trade or professional institution will bind them or apply to the contract, such standard form of terms and conditions including any provision for arbitration in such standard terms and conditions, shall be deemed to be incorporated by reference. It has been held that sometimes  the  contract  may  also  say  that  the  parties  are familiar with those terms and conditions or that the parties have  read  and  understood  the  said  terms  and  conditions. It has also been held that where  the contract between the parties  stipulates  that  the  conditions  of  contract  of  one  of the parties to the contract shall form a part of their contract, the arbitration clause forming part of such general conditions of contract will apply to the contract between the parties.

19.

A perusal of sub-section (5) of Section 7 of the Arbitration Act itself would reveal that it provides for a conscious acceptance of the arbitration clause from another document, by the parties, as a part of their contract, before such arbitration clause could be read as a part of the contract between the parties.

20.

It is thus clear  that a reference  to the  document  in the contract should be such that shows the intention to incorporate the arbitration clause contained in the document into the contract.

21.

The law laid down in M.R. Engineers & Contractors [M.R. Engineers & Contractors (P) Ltd. v. Som Datt  Builders  Ltd.,  (2009)  7 SCC  696  : (2009)  3  SCC  (Civ) 271] has been followed by this Court in Duro Felguera, S.A. v. Gangavaram Port Ltd. [Duro Felguera, S.A. v. Gangavaram Port Ltd., (2017) 9 SCC 729 : (2017) 4 SCC (Civ) 764] and Elite Engg. & Construction (Hyd.) (P) Ltd. v. Techtrans Construction  India (P) Ltd. [Elite Engg.  & Construction (Hyd.) (P) Ltd. v. Techtrans Construction India (P) Ltd., (2018) 4 SCC 281 : (2018) 3 SCC (Civ) 60]

22.

No doubt that this Court in Inox Wind Ltd. v. Thermocables Ltd. [Inox Wind Ltd. v. Thermocables Ltd., (2018) 2 SCC 519 : (2018) 2 SCC (Civ) 195] has distinguished the law laid down in M.R. Engineers & Contractors [M.R. Engineers & Contractors (P) Ltd. v. Som Datt  Builders  Ltd.,  (2009)  7 SCC  696  : (2009)  3  SCC  (Civ) 271] . In the said case (i.e. Inox Wind [Inox Wind Ltd. v. Thermocables Ltd., (2018) 2 SCC 519 : (2018) 2 SCC  (Civ)  195]  ),  this  Court has  held  that  though general reference to an earlier contract is not sufficient for incorporation  of  an  arbitration  clause  in  the  later  contract, a general reference to a standard form would be enough for incorporation of the arbitration clause. Though this Court in Inox Wind [Inox Wind Ltd. v. Thermocables Ltd., (2018) 2 SCC 519 : (2018) 2 SCC (Civ) 195] agrees with the judgment in M.R. Engineers & Contractors [M.R. Engineers & Contractors (P) Ltd. v. Som Datt Builders Ltd., (2009) 7 SCC  696  : (2009)  3 SCC  (Civ)  271]  , it  holds  that  general reference to a standard form of contract of one party along with those of trade associations and professional bodies will be sufficient to incorporate the arbitration clause. In the said case (i.e. Inox Wind [Inox Wind Ltd. v. Thermocables Ltd., (2018) 2 SCC 519 : (2018) 2 SCC  (Civ)  195]  ),  this  Court  found  that  the  purchase  order was issued by the appellant therein in which it was categorically mentioned that the supply would be as per the terms mentioned therein and in the attached standard terms  and  conditions.  The  respondent  therein  by  his  letter had confirmed its acceptance. This Court found that the case before it was a case of a single contract and not two- contract case and, therefore, held that the arbitration clause as mentioned in the terms and conditions would be applicable.

23.

The present case is a “two-contract” case and not a“single-contract” case.

29.

As already discussed hereinabove, when there is a reference in the second contract to the terms and conditions of the  first  contract,  the  arbitration  clause  would  not  ipso facto be applicable to the second contract unless there is a specific mention/reference thereto.

30.

We are of the considered view that the present case is not  a case  of  “incorporation”  but  a case  of  “reference”.  As such, a general reference would not have the effect of incorporating the arbitration clause. In any case, Clause 7.0 of the LoI, which is also a part of the agreement, makes it amply clear that the redressal of the dispute between NBCC and the respondent has to be only through civil courts having jurisdiction of Delhi alone.”

39.

Although this Court in NBCC (India) Ltd. (Supra) was dealing with a factual situation which was quite similar to the instant case, the reasons why the Court interfered with the appointment of an arbitrator in the said case were twofold. Apart from  the  fact  that  a general  reference  in  the  letter  of  intent  to  an arbitration  clause  contained  in  the  tender  documents  was  found to  not  be  sufficient  for  its  incorporation,  the  second  reason  was that the letter of intent in that case had a separate dispute resolution clause which limited redressal of disputes to civil courts having  jurisdiction of Delhi alone. Even then, the law laid down  in respect  of incorporation  of  arbitration  clauses contained in tender  documents by  means of reference in the letter of intent is squarely applicable to the facts of the instant case. The LOI in the instant case makes a reference to the Tender documents contained in the following terms:

“Notwithstanding that reference are given above, the terms and conditions and specifications of contract shall be interpreted by reading together the terms and conditions, specifications and contents of this Letter of intent as below. In case of any deviations with the contents of this Letter of intent from corresponding conditions in the above said tender specifications or contents of the letter under reference  as  read  and  interpreted  up  to  date,  the  contents of this Letter of intent shall prevail.”

In  our view,  this  is a case  of ‘reference’ and  not  ‘incorporation’. There is no mention of any arbitration or dispute resolution clause in the LOI itself, neither does it purport specific incorporation thereof from the tender documents. As such, the arbitration  clause  contained  in  the  Tender  documents  could  not be said to have been incorporated in the LOI to evince the existence  of  an  arbitration  agreement  between  the  parties  on  its conjoint reading with the Tender documents.

40.

The  judgements  of  this  Court  in  NBCC  (India)  Ltd. (Supra) as  well  as  M.R.  Engineers  & Contractors  (P)  Ltd. (Supra)  were recently discussed and distinguished on facts by a co-ordinate bench of this Court in Glencore International AG v. Shree Ganesh Metals 2025 SCC OnLine SC 1815. In the facts of that case, there was no incorporation of the arbitration agreement, but rather the contract containing the arbitration agreement  was never signed by the parties, but it was acted upon and the communication between the parties evinced the creation of a binding legal relationship between them. In such context, the Court placed reliance on the judgement in Govind Rubber Ltd. (Supra) and held that  non-signing of the contract  containing the arbitration agreement cannot invalidate the arbitration agreement which is in  writing  and  the  parties  seem  to  be ad  idem in  respect  of  the agreement by communication about the contract. The judgement in Glencore International AG (Supra) is not applicable to the facts  of  this  case  since  it  distinguishes  the  judgement  in NBCC (India)  Ltd. (Supra)  where  the  factual  scenario  was  quite  similar to the facts of the instant appeal.

41.

Similar  is  the  case  of  the judgement  in UNISSI  (India)  (P) Ltd.(Supra) relied upon by the Appellant where the tender documents  contained  an  arbitration  clause  and  the  tender  offer of  the  Appellant  therein  was  accepted  and  the  Appellant  therein acted upon the said acceptance and made supply of oxymeters required under the tender even though no formal contract was signed  between  the  parties.  In  such  context,  the  Court  held  that the arbitration agreement contained in the tender was applicable and dispute between the parties ought to be referred to an arbitrator. In the facts of the present case, the terms of the tender itself have never been worked upon by the Respondent. The Work Order was never issued by the Appellant and the sites were never handed over by the Appellant. The Respondent has submitted bank guarantees pursuant to the LOI, which at best is a preliminary  requirement  as  a precursor  to  the  Work  Order  being issued. As discussed above, the LOI in the instant case was indicative of a preliminary document in course of the contract and was not intended to be an end-all-be-all contract between the parties, it did not create contractual obligations or legal relationship between them.

42.

It goes without saying that the scope of inquiry at the stage of Section 11 is extremely limited and only pertains to an examination about prima facie existence of an arbitration agreement. Judicial non-interference in the arbitration process is the sacrosanct principle which guides alternative dispute resolution  and  Courts  must  be  highly  circumspect  in  interfering at  the  referral  stage,  especially  since  there  is  no  appeal  available in  the  1996  Act  against  an  order  under  Section  11.  The  Arbitral Tribunal, in exercise of its jurisdiction under Section 16 must be left to decide on its jurisdiction. The Courts should follow the principle  of  ‘When  in  doubt,  do  refer’  and  lean  towards  referring matters to arbitration when the arbitration agreement is prima facie existent. However, it is only in the rarest of rare cases where even on a prima facie view, without going into disputed facts between the parties, there appears to be no existence of arbitration  agreement  between  the  parties,  the  Court  can  reject the  application  for  appointment  of  an  arbitrator  and  reference  of the parties to arbitration. The instant case appears to be a fit case where, as discussed, even  without  going into the disputed facts  and  merely  on  a  prima  facie  view  of  the  matter,  there  is  no existence  of  arbitration  agreement  and  therefore,  the  decision  of the High Court to appoint an arbitrator requires interference.

43.

As an upshot of the above discussion, the instant appeal deserves to be allowed and the order impugned passed by the High  Court stands set  aside.  The Respondent  is  given  the  liberty to pursue other alternative remedies in accordance with law, if any, available to it. All interim application(s) shall be treated to be disposed of.