High CourtsDivision Bench(2015) 05 DEL CK 0179

Mass Estate (P) Ltd. vs Lt. Governor of Delhi and Others

Delhi High Court · Decided on 18 May 2015

HON’BLE JUDGES
Badar Durrez Ahmed, J · Sanjeev Sachdeva, J
RESULT
Allowed
CASE NUMBER
Writ Petition (C) 2456/2014, CM Nos. 5117 and 20434 of 2014

AI Structured Summary

Not yet generated for this judgment

Judgment

8 paragraphs · 459 words

Badar Durrez Ahmed, J.—By way of this writ petition the petitioner is seeking the benefit of section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as ''the 2013 Act'') which came into effect on 01.01.2014. The petitioner, consequently, seeks a declaration that the acquisition proceeding initiated under the Land Acquisition Act, 1894 (hereinafter referred to as ''the 1894 Act'') and in respect of which Award No. 29/2002-03 dated 01.11.2002 was made, inter alia, in respect of the petitioner''s land comprised in Khasra Nos. 15/26(0-03), 26/4/1 (0-8), 26/4/2 (1-17), 15/26 (0-3), 15/24/2 (1-0) measuring 3 Bighas 11 Biswas in Village Shahbad Daulatpur shall be deemed to have lapsed.

2.

In the petition, it has been claimed that the physical possession of the subject land has not been taken by the land acquiring agency nor has any compensation been paid to the petitioner. This fact is not specifically refuted by the Land Acquisition Collector in the counter affidavit filed by him. The counter affidavit filed on behalf of DDA also indicates that the possession of the land could not be taken because the area was built up. Insofar as the compensation is concerned, there is also no specific denial of the allegations on the part of the petitioner that the compensation has not been paid in respect of the said land. Consequently, it will have to be considered as a case where possession of the subject land has not been taken and compensation has also not been paid in respect thereof. The award was made more than five years prior to the commencement of the 2013 Act. All the ingredients of section 24(2) of the 2013 Act as interpreted by the Supreme Court and this Court in the following decisions stand satisfied:-

(i) Pune Municipal Corporation and Another Vs. Harakchand Misirimal Solanki and Others, AIR 2014 SC 982 : (2014) AIRSCW 787 : (2014) 3 JT 283 : (2014) 1 RCR(Civil) 880 : (2014) 1 SCALE 618 : (2014) 3 SCC 183 ;

(ii) Union of India (UOI) and Others Vs. Shiv Raj and Others, AIR 2014 SC 2242 : (2014) AIRSCW 3388 : (2014) 6 SCC 564 ;

(iii) Sree Balaji Nagar Residential Association v. State of Tamil Nadu and Ors: Civil Appeal No. 8700/2013 decided on 10.09.2014;

(iv) Surinder Singh vs. Union of India and Ors.: W.P.(C) 2294/2014 decided 12.09.2014 by this Court.

3.

As a result the petitioner is entitled to a declaration that the said acquisition proceedings initiated under the 1894 Act in respect of the subject lands are deemed to have lapsed. It is so declared.

4.

The writ petition is allowed to the aforesaid extent. There shall be no order as to costs.