AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
53 paragraphs · 1,072 wordsVivek Puri, J
The matter has been taken up through video conferencing in the light of the Covid-19 pandemic situation and as per instructions.
The petitioner has assailed the order dated 8.6.2020 (Annexure P-9) passed by the respondent cancelling the extension of tender awarded in his
favour on 3.6.2020.
Learned counsel for the petitioner submits that the petitioner was allotted the tender for house keeping and other sourcing services for
MCH/CHC/PHC for Dadri District invited by respondent No.3 on 15.6.2019. The petitioner was successful bidder, who was awarded work and an
agreement was entered into between the parties. As per the terms of the agreement dated 6.7.2019 (Annexure P-3), the agreement was extendable
by another year subject to the performance of satisfactory work. The period of work was to expire in July 2020 and the process for extension was
initiated by respondent No.3. The concerned authorities under whom the petitioner had provided about 170 skilled and unskilled persons reported the
performance of the petitioner's agency as satisfactory. Accordingly, the contract was extended for further one year vide letter dated 3.6.2020
(Annexure P-8). However, the extension for one year has been arbitrarily and unilaterally cancelled in terms of letter dated 8.6.2020 (Annexure P-9).
No reason was assigned while unceremoniously terminating the contract ending on 5.7.2020. Even no opportunity of hearing was afforded to the
petitioner.
Per contra, learned State counsel submits that in terms of Clause 2.4 of the Detailed Notice Inviting Tender (DNIT) the contract was subject to
approval by the Competent Authority. Since the approval was declined by the Competent Authority, the contract was automatically cancelled. In view
of the change in the policy of the Government for deployment of Home Guards instead of Security Guards. The change was incorporated. Considering
the fact that the Home Guards Security Personnel were better trained in mob control, riot management, vehicular management, human traffic
management etc. as compared to the outsourced staff. The Home Guard recruits are better trained to deal untoward incidents, mishappenings in
emergent situations. The financial implications are also on lesser side on account of employment of Home Guards was also considered by the
Government. Furthermore, the petitioner was expected to start work from 1.7.2020 and the extension was cancelled in terms of letter dated 8.6.2020
in view of the non-approval by the Competent Authority. Even the Clause 9 of DNIT empowers the respondent to cancel the bid at any stage.
Heard.
There is no controversy between the parties to the effect that at the first instance the petitioner was awarded the work for providing manpower by
way of outsourcing for CHC, PHC, MCH from 6.7.2019 to 5.7.2020. As per the terms and conditions of DNIT, the contract was liable to be extended
by one year subject to review and satisfactory performance of services/activities. Accordingly, respondent No.3 had issued the letter dated 3.6.2020
extending the contract from 1.7.2020 to 30.6.2021 for a further period of one year. Subsequently, on account of non-approval by the Director, Health
Services, the extension was cancelled in terms of the notice dated 8.6.2020 (Annexure P-9). The extension of tender of outsourcing services was
cancelled in response to the letter from respondent No.2 i.e. Director, Health Services, Haryana dated 4.6.2020. Clause 2.4 of DNIT reads as follows:
“The work contract shall be awarded initially for a period of one year, subject to review and the satisfactory performance of Services/Activities
and compliance of all terms and conditions of the service Agreement, which is further, subject to the approval of Competent Authority. The Contract
shall stand automatically cancelled if the Competent Authority declines to grant such approval it will be responsibility of contractor to apply for
extension beyond one year at least 3 months before the expiry of contract.â€
The poser for consideration is as to whether any vested right had accrued in favour of the petitioner on account of issuance of the letter dated
3.6.2020 (Annexure P-8) vide which the tender was extended for a period of one year by respondent No.3. A perusal of Clause 2.4 makes it amply
clear that the contract was subject to approval by the Competent Authority and since the Competent Authority declined to grant such approval, the
contract automatically stood cancelled. The case of the respondent is to the effect that on account of change in policy for recruitment of Home
Guards instead of Security Guards, the approval was declined by the Competent Authority i.e. Respondent No.2 and consequently the extension
granted to the petitioner was cancelled in terms of the letter dated 8.6.2020 (Annexure P-9).
The petitioner has sought to putforth a case to the effect that the action of the respondents is biased and malafide. The contract has been cancelled as
the earlier Civil Surgeon was transferred and new incumbent had cancelled the contract. The contention of the learned counsel for the petitioner is
liable to be rejected in the wake of the fact that no reason has been assigned which might have actuated respondent No.3 to act with malice or bias.
Furthermore, the action for cancellation of extension of contract has not been initiated at the instance of respondent No.3 but on account of non-grant
of approval by the Competent Authority i.e. respondent No.2.
The petitioner has also sought to putforth a case to the effect that no approval is required for extension of work. We find no merit in the contention of
the learned counsel for the petitioner since Clause 2.4 of DNIT is not to be read in isolation or separation for awarding the contract at the first
instance and extension for one year. In the event, the approval is declined by the Competent Authority, the contract automatically stands cancelled. In
these set of circumstances, it cannot be said that any vested right has been created in favour of the petitioner on account of issuance of letter dated
3.6.2020 (Annexure P-8) vide which the tender was extended for a period of one year by respondent No.3 as the extension was subject to the
approval by the Competent Authority. The Competent
Authority has declined the approval and moreover, the cancellation has been done even prior to the commencement of the work. As such, we feel that
no illegality or irregularity is made out in the action of the respondents in cancellation of the extension granted to the petitioner which may warrant any
interference by this Court.
For the aforesaid reasons, the petition being devoid of merit is dismissed.