The appellant herein is engaged in providing taxable service on work contract of civil work like concrete and other miscellaneous works being
awarded by M/s. Gannon Dunkerley and Co. Ltd. On the basis of data available with the Department, it was observed that the appellant has received
an amount of Rs 51,14,456/-towards the provisions of said services from their service receiver but have not paid the Service Tax on such taxable
receipts amounting to Rs 6,322,147/- during the period of 2013-14. Accordingly vide Show Cause Notice No. 4611 dated 12.10.2018 aforesaid amount
of Service Tax was proposed to be recovered from the appellant along with the interest and proportionate penalties. The said proposal was rejected by
the Original Adjudication Authority vide the order No. 97/2019-20 dated 11.3.2020 holding that the law does not discriminate between the contractor
and sub contractor in so far as the Service Tax liability is concerned. The appeal against this order as filed by the Department has been allowed vide
Order-in-Appeal No. 76/20-21 dated 18.2.2021 holding that the receiver has provided the ‘work contract service’ to M/s. Gannon Dunkerley
and Co. Ltd. However the service provider, the present appellant was held liable for benefit of Notification No. 30/2012 dated 20.6.2012. Being
aggrieved of the said order, the appeal is filed before this Tribunal raising the sole ground of impugned Show Cause Notice to be barred by time.
I have heard Shri Naresh Pratap Chand, learned Counsel appearing for the appellant and Shri Mahesh Bhardwaj, learned Authorised
Representative appearing for the Department.
Learned Counsel for the appellant has mentioned that during the financial year 2013-14 the services of ‘work contract’ were provided to
M/s. Gannon Dunkerley and Co. Ltd. Hyderabad on sub contract basis against the consideration of Rs. 51,14,456/-. It is mentioned that on said
consideration the main contractor had discharged the due Service Tax liability. Letter of the company dated 13.2.2019 has been impressed upon and
as far as the impugned Show Cause Notice is concerned, it is mentioned that Show Cause Notice dated 10.2.2018 covers the period from 1.04.2013 to
31.03.2014. The Show Cause Notice could have been issued for the said period during one and a half year only i.e. up to 25.10.2015 but the impugned
Show Cause Notice has been issued in the 2018 invoking the extended period of 5 years. It is submitted that the extended period cannot be invoked in
the present case because there is no wilful intention of the appellant for avoiding payment of Service Tax. There was confusion in the industry about
the liability of sub contractor during the period in dispute. Said contravention / confusion has been settled by the decision of Larger Bench of this
Tribunal in the case of CCE vs. Melange Developer Pvt. Ltd. reported as [2020 33 GSTL 116 (Tri-LB)] making sub contractor individually liable for
the payment. In the present case that there is non payment by the appellant as sub contractor but the impugned Service Tax liability stand already
discharged and the amount received already stand deposited with the Government by the main contractor. It is therefore submitted that the demand is
alleged to have been wrongly invoked by extending period of limitation. Order under challenge is accordingly prayed to be set aside. The appeal is
prayed to be allowed.
Per contra learned Departmental Representative has laid emphasis upon the Order in Appeal itself which has been passed based on settled law
about the liability of the contractor being separate from liability of the sub contractor to discharge the Service Tax. It is submitted that the
Commissioner (Appeals) has been reasonable while extending the benefit of Notification dated 20.6.2012 to the appellant. There is no infirmity in the
order with respect to invoking the extended period of limitation. Learned Departmental Representative has not expressed any submission. However,
appeal is prayed to be dismissed.
After hearing both the sides it is held as follows:
There is no dispute about the fact that the amount of Service Tax for the amount of consideration received by the appellant stand already paid with the
Government exchequer, however by the main contractor M/s. Gannon Dunkerley and Co. Ltd. There is also no denial to the fact that during the
period there were several pronouncements made not only by this Tribunal but even by the departmental adjudicating authority holding that the sub-
contractor is not liable to pay the Service Tax when the main contractor has paid the said Service Tax. Till the order in which the impugned Show
Cause Notices has been issued similar was the scenario. Few of such decisions are in the case of
1 M/s. Abed Ali Malda, VS Asstt Commissioner,CGST, Malda Division, WB [OIA No. 325/SLG-ST/2018-19 dated 5.3.2019];
DNS Contractor vs. CCE Delhi 2015 (51) GSTL 636];
Murari Lal Singhal vs CCE & ST, Jaipur [2019 (25) GSTL 45 (Tri-Del)];
Thadi Satya Ramalinga Reddy vs. CCE Visakapatnam II [2017 (4) GSTL 421]
I also observe that it was the decision of Larger Bench of this Tribunal in the case of CCE vs. Melange Developer Pvt. Ltd. reported as [2020 33
GSTL 116 (Tri-LB)] that the aforesaid decisions have been altered to the fact that the sub contractor being an individual service provider that to the
main contractor but is liable to discharge the Service Tax liability to the extent of amount of service being provided by him to the main contractor. All
the above decisions and the prevalent contradiction stand cleared by final judgement of Larger Bench. In view of this, and the facts of the case are
sufficient to hold that there was no clarity about the individual liability of the sub contractor towards the payment of service tax. Even the Department
was not clear on the interpretation of the circulars issued, judgements made and practice followed on sub contractors liability. As such in the case
where the main contractor had discharged the Service Tax on entire value of service. These findings are sufficient for me to hold that there cannot be
any intentional conduct of the appellant to not to pay the service tax during 2013-14. Alleging fraud mis-statement or suppression of facts upon the
appellant in view of above prevalent situation is opined to be definite error on part of the Adjudicating Authority below. The onus was otherwise on the
Department to prove that short payment of service tax has been made with intent to evade such payment. Apparently and admittedly in the present
case the service tax stands already paid with respect to the amount involved in the present appeal, i.e. the amount of consideration received by the
appellant/ sub contractor for providing ‘works contract services’ to main Contractor M/s. Gannon Dunkerley & Co. Ltd. The question of any
positive evidence proving evasion does not at all arise. Hence there arises the occasion for invoking the extended period of limitation. I draw my
support from the decision in the case of Savira Industries vs. CCE, Chennai reported as [2016 (331) ELT 504 (Tri-Chennai)] wherein it was held that
where the assessee was under the bonafide belief of his no liability towards service tax or there are divergent views of the Courts on the issue,
extended period of limitation can not be invoked. The entire demand in such a case gets hit by limitation. In view of the entire above discussion, the
impugned show cause notice is held to be barred by limitation, any question of sustenance of any demand raised by said show cause notice do not
survive. Order under challenge is accordingly, set aside. Appeal stands allowed.