High CourtsSingle Bench

M/S BSCPL Infrastructure Ltd vs Union Of India & Anr.

Delhi High Court · Decided on 23 July 2021 · Citation: (2021) 07 DEL CK 0151

HON’BLE JUDGES
Suresh Kumar Kait, J
ACTS & SECTIONS REFERRED
Arbitration And Conciliation Act, 1996 — Section 11(6), 12
RESULT
Disposed Of
CASE NUMBER
Arbitration Petition No. 611 Of 2021
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

46 paragraphs · 836 words

Suresh Kumar Kait, J

1.

Petitioner- M/s BSCPL Infrastructure Ltd. has preferred the present petition under Section 11 sub-section (6) of Arbitration and Conciliation Act,

1996 seeking appointment of an Arbitrator to settle the disputes with respondents, as mentioned in Para-7 of the present petition. A direction is also

sought to respondents to produce original Agreement dated 31.03.2017.

2.

The crux of the case in hand, according to petitioner, is that on 15.02.2017, respondent No.1- Chief Engineer (AF) WAC invited applications from

the Contractors for issue of tender for the work relating to “Resurfacing of Runway and Aircraft Operating Areas at AF Station Chandigarhâ€​ and

vide letter dated 15.02.2017, authorized the petitioner to tender for the above work and thereafter, petitioner submitted the tender. Respondent No.1,

Accepting Officer, for and on behalf of President of India, vide letter No.83022/CHD/283/E8 dated 31.03.2013 issued by their Chief Engineer,

communicated the petitioner that its tender had been accepted for a contract sum of Rs.433,92,71,325.30. The period fixed for completion of the work

was 28 months commencing from 05.04.2017 and ending with 04.08.2019.

3.

In the meanwhile, the parties entered into amendment No.2, dated 29.03.2019 2019 to the aforesaid Agreement dated 31.03.2017 for referring the

matters in dispute in the first place to the Dispute Resolution Board (DRB) by incorporating a Condition 50 “DISPUTE RESOLUTION BOARD

(DRB)'†as part of Special Conditions. The Contract in Condition 70 of the General Conditions of Contract contained in I.A.F .W.-2249 provides for

settlement of disputes by arbitration.

4.

According to petitioner, upon receipt of the letter of acceptance dated 31.03.2017, petitioner mobilized its organization and deployed at site the

necessary manpower, materials, machinery and other facilities and commenced the works so as to complete before the due date according to the

contractual conditions. However, it was completed on 27.05.2020. But since respondent No.1 failed and neglected in releasing various amounts due

for payment, petitioner referred such matters in dispute to Dispute Resolution Board for decision thereon.

5.

The Dispute Resolution Board after hearing the parties rendered its decision on 05.02.2021. Being dissatisfied therewith, petitioner issued a notice

under Clause 6(b) on page 29 of the Agreement read with Condition

70 of the General Conditions of Contract contained in I.A.F.W.-2249 and thereby referred the disputes for arbitration and requested the appointing

authority, i.e. respondent No.2 for reference of the resultant disputes to arbitration and for appointment of a sole Arbitrator. Upon failure of

respondent No.2 to appoint Arbitrator in terms of agreement within 30 days of petitioner’s Notice dated 15.02.2021. Thus, petitioner has

approached this Court seeking appointment of an Arbitrator to resolve the present dispute falling under Commercial Courts Act, 2015.

6.

Mr. Ripudaman Bhardwaj, learned Central Government Standing Counsel, has opposed the claim of petitioner while submitting that in terms of

agreement between the parties, the Arbitrator has to be appointed by respondent No.2 and therefore, this petition be not allowed.

7.

Both sides have been heard and record of this case has been perused.

8.

Petitioner has invoked arbitration vide notice dated 15.02.2021. According to petitioner, the claim raised in the present petition is of approximately

Rs.39,34,40,117.73 besides 18% per annum interest and cost of arbitration. The arbitration agreement between the parties and invocation of arbitration

are not disputed by the respondents. However, contention of respondents that the Arbitrator has to be appointed by respondent No.2 is rejected, as no

party can be permitted to unilaterally appoint an Arbitrator, as the same would defeat the purpose of unbiased adjudication of dispute between the

parties.

9.

The Hon’ble Supreme Court in Perkins Eastman Architects DPC & Anr. vs. HSCC (India) Ltd. 2019 SCC Online SC 1517 has categorically

stated that “in cases where one party has a right to appoint a sole arbitrator, its choice will always have an element of exclusivity in determining or

charting the course for dispute resolution. Naturally, the person who has an interest in the outcome or decision of the dispute must not have the power

to appoint a sole arbitrator.â€​

10.

The afore-noted dictum of Hon’ble Supreme Court in Perkins Eastman (Supra), has been followed by Coordinate Benches of this Court in

Proddatur Cable Tv Digi Services Vs. Siti Cable Network Limited 2020 SCC OnLine Del 350 and VSK Technologies Private Limited and Others Vs.

Delhi Jal Board 2021 SCC OnLine Del 3525 in unequivocal terms.

11.

Concurring with the decisions as noted above, the present petition is allowed.

12.

Accordingly, Justice KG Balakrishnan, former Chief Justice of India (Mobile: 9717266700) is appointed the Sole Arbitrator to adjudicate the

dispute between the parties. The arbitration shall be conducted under the Delhi International Arbitration Centre (DIAC).

13.

The fee of the Arbitrator shall be in accordance with the Schedule of Fees prescribed under the Delhi International Arbitration Centre (DIAC)

(Administrative Cost and Arbitrators Fees) Rules, 2018.

14.

The learned Arbitrator shall ensure compliance of Section 12 of Arbitration and Conciliation Act, 1996 before commencing the arbitration.

15.

With aforesaid directions, the present petition is accordingly disposed of.