AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
9 paragraphs · 420 wordsManoj Kumar Gupta, CJ
The present writ petition has been filed assailing the order dated 24.04.2026, passed by Tender Evaluation Committee, Uttarakhand Rural Roads Development Agency (respondent no. 2 herein), whereby it was recommended that since only single bidder was found responsive in part 1 of the bidding process i.e. Technical Evaluation Round, the same was not acceptable and, accordingly, a recommendation was made for re-tendering.
The petitioner and respondent no. 3 submitted their bids in pursuance of E-procurement notice dated 28.01.2026 issued under the Pradhan anti Gram Sarak Yojna. The Tender Evaluation Committee, as noted above, observed that in the technical round only a single bid remained after evaluation, as the bid of respondent no.3 was found to be non-responsive, and therefore, decided to go for re-tendering.
The case of the petitioner is that the bid of respondent no.3 was rejected on the ground of non- responsiveness in terms of para 5 of NIT12(P-IV) 2025- 26, dated 28.01.2026 read with Section 1, Clause 6.2 and Section 2, Clause 12.2(d) of the Standard Bidding Documents, which required submission of the Original Documents by the bidders. The contention of learned counsel for the petitioner is that the National Rural Roads Development Agency, vide a circular letter dated 25.01.2026, clarified that the scanned copies of the documents/affidavits would suffice and that originals were not required to be uploaded with the bid.
It is urged that in such circumstances, the bid of respondent no.3 was wrongly held to be non- responsive and if the said bid is treated to be responsive, there would have been two bids and thus, no impediment in proceeding to the second stage of the bidding process i.e. opening of the financial bids.
Undoubtedly, after the rejection of the bid of respondent no.3, the petitioner remained the sole bidder. It is also not in disputes that where only a single bid is found responsive, then as per the prescribed guidelines, re-tendering has to be done. Respondent no.3, whose bid has been rejected in the technical round, has not come forward to challenge the rejection of his bid. The respondents have taken decision for re- tendering as per the prescribed norms. The petitioner will also have opportunity to participate in the fresh tender process.
Consequently, we are of the considered opinion that no ground is made out for interference with the decision taken by the respondents.
The petition lacks merit and is accordingly dismissed.
Pending application, if any, also stands disposed of.
