AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
325 paragraphs · 6,592 wordsNavin Chawla, J
This petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) has been filed by the
petitioner M/s Lifelong Meditech (P) Ltd. challenging the Arbitral Award dated 16.09.2016 passed by the Sole Arbitrator in case reference
No.DAC/935/04/15.
The dispute between the parties has arisen out of a Comprehensive Standard Fire & Special Perils Policy No.041100/11/12/11/00000021 for a sum
of Rs. 40,61,03,196/- taken by the petitioner from the respondent. The policy was valid from 01.04.2012 to 31.03.2013. Another policy covering stocks
i.e. Floater Policy No. 041100/11/12/13/00000018 valid from 01.04.2012 to 31.03.2013 for a total sum of Rs.13 crores was also taken by the petitioner
from the respondent.
A fire took place in the factory premises of the petitioner on 27.05.2012. On intimation of the same to the respondent, the respondent appointed M/s
Sandeep Bharti Insurance Surveyors and Mr.P.R. Ramanathan as Surveyors.
A claim of Rs.41,78,43,286/- was lodged by the petitioner with the surveyors. The surveyors submitted an interim survey report dated 03.11.2012
based on which the respondent released an “on account payment†of Rs.10 crores in favour of the petitioner on 15.11.2012. The surveyors
submitted their final report on 17.08.2013. The respondent thereafter released further payment of Rs.20,41,60,835/- on 16.12.2013 and
Rs.1,88,78,410/- on 09.05.2014.
The petitioner was dissatisfied with the above payment and therefore vide its letter dated 20.05.2014 called upon the respondent to pay a further
sum of Rs.9,38,84,995/- along with interest. As the payment was not made by the respondent and the dispute persisted, this Court on a petition filed by
the petitioner under Section 11(6) of the Act appointed a Sole Arbitrator who has passed the impugned Award dismissing the claim filed by the
petitioner.
It is an admitted case that the claimant/ petitioner herein had signed three discharge vouchers dated 15.11.2012, 16.12.2013 and 09.05.2014 while
accepting the payment made by the respondent. The respondent had therefore contended that in view of the discharge vouchers, the claim of the
petitioner could not be entertained. It is important to note here that these alleged discharge vouchers were not produced before Sole Arbitrator by
either party. Learned Arbitrator, however held that even if the discharge vouchers are not produced, it would not, in any manner, effect the defence of
the respondent that the claimant/petitioner is bound by the terms of the discharge vouchers under the Principle of Accord and Satisfaction. After
relying on various judgments and commentaries, the Sole Arbitrator held that as the discharge vouchers were executed at different points of time
between 15.11.2012 to 09.05.2014 and during this period no protest was made by the claimant and further as no evidence had been led by the claimant
to prove any undue influence or coercion practiced by the respondent for execution of these vouchers and as the protest letter was filed only 11 days
after the third discharge voucher was signed, the claimant had failed to prove that the discharge vouchers were obtained through exercise of undue
influence or coercion by the respondent. The Sole Arbitrator also refused to rely upon Circular dated 24.09.2015 issued by Insurance Regulatory and
Development Authority of India (hereinafter referred as IRDAI) on the ground that said circular can only apply prospectively. The finding of the
Arbitrator on the effect of the discharge vouchers has been summarized by him in paragraph 37 of the Award, which is reproduced herein below:
“37. In view of the above, I have no hesitation to hold as under:
a. The discharge vouchers cannot be said to have been obtained fraud, coercion, duress or undue influence. The Claimant has failed to
establish any fraud, coercion, duress or undue influence in the facts of the instant case.
b. The claimant has also failed to establish the allegation of duress due to financial difficulty
c. The Circular dated 24.09.2015 issued by Insurance Regulatory and Development Authority of India (IRDAI) is not applicable to the facts
of the present case.
d. Thus, in the facts of the instant case there was a full and final settlement resulting in accord and satisfaction and hence there does not
exist any arbitrable dispute between the parties.â€
Learned counsel for the petitioner/claimant submits that as the discharge vouchers had not been filed by the respondent before the Sole Arbitrator,
no reliance could have been placed on the same. He further contends that with every release of payment it was a pre-condition imposed by the
respondent that a discharge voucher in form of full and final payment has to be executed by the claimant. It is for this reason that even in the present
case as many as three discharge vouchers were executed, though, admittedly the payment was also released in three trenches. He further referred to
the answer of question No.6 put to Sh. Vijay Sharma, witness of the respondent, during his cross-examination wherein he admits that if the claimant
would not have signed the discharge vouchers, the respondent would not have released any amount to it. Answer to question No.6 and 8 put to the
witness are reproduced herein below:
“Q.6: If the claimant would not have signed the discharge voucher, would the respondent release any amount to the claimant?
A. No.
Q.8: If the claimant would have protested during the time of release of interim payment, would the respondent pay the same or pay any
future amounts?
A. I have already replied that discharge and acknowledgement is required for making any payment. If the claimant would have protested,
there was no question of getting an acknowledgement and therefore, the Respondent would not have made payment.â€
As far as the Circular dated 24.09.2015 of IRDAI is concerned, learned counsel for the petitioner submits that the circular was, in fact, an
admission of the fact that Insurance Companies are misusing such discharge vouchers to claim full and final settlement against the aggrieved policy
holders and that execution of such vouchers does not foreclose the right of the policy holder to seek higher compensation before any judicial fora or
any other fora established by law. He submits that this circular was therefore relevant for adjudicating the dispute in hand.
On the other hand, learned counsel for the respondent submits that the Arbitrator having appreciated the evidence led before him, this Court in
exercise of its power under Section 34 of the Act would not sit in Appeal over such findings. He further submits that non-production of discharge
vouchers before Sole Arbitrator would have no effect as the execution of the same had been admitted by the claimant/petitioner.
I am unable to agree with submission made by the learned counsel for the respondent. Though, it is correct that in exercise of its limited jurisdiction
under Section 34 of the Act, this Court would not sit in Appeal over the findings of the Sole Arbitrator, however, at the same time if an Arbitral
Tribunal takes into account some irrelevant evidence for decision which it arrives at or ignores vital evidence in arriving at its decision, the Award can
certainly be interfered with. In the present case, the following glaring facts were ignored by the Sole Arbitrator:
a. The discharge vouchers were not produced before the Sole Arbitrator. Therefore, the terms of the same were also not before the Sole Arbitrator.
The Sole Arbitrator proceeded by an assumption that the discharge vouchers would contain full and final settlement. Though, it is true that the
petitioner/claimant had admitted the execution of said discharge vouchers, in my opinion, in the absence of the production of the documents itself,
terms of such documents could not have been assumed.
b. The Arbitrator failed to appreciate that admittedly there were three discharge vouchers in this case. Which amongst these would actually be a full
and final settlement of the claim? Admittedly, even after execution of the first and second discharge vouchers on 15.11.2012 and 16.12.2013, the
respondent yet made a further payment of Rs.1,88,78,410/-which is a substantial amount on 09.05.2014. If the first and second discharge vouchers
were not full and final settlement of the claim, then how was the third discharge voucher a full and final settlement? This was not explained by the
respondent and certainly has not been discussed by the Sole Arbitrator.
c. As the payment was admittedly made after the first and second discharge vouchers, they could not have been treated as full and final settlement of
the claim. Therefore, the only document which could be relied upon by the respondent as a full and final settlement was the third discharge voucher
executed on 09.05.2014. Admittedly, within 11 days thereof the petitioner has lodged his protest. Therefore, the finding of the Sole Arbitrator that no
protest was lodged for a period of 1½ years, taking the first discharge voucher executed on 15.11.2012 to be of relevance, is totally unfounded and
arbitrary.
d. Answers to question Nos.6 and 8 of the witness of the respondent itself clearly shows that no payment would have been released to the petitioner
without execution of the discharge vouchers. It is to be seen that the petitioner has already suffered a loss due to fire which stands admitted by the
respondent inasmuch as the claim was finally sanctioned. The claim was not for a small amount but a very large amount. The fire had taken place in
the factory premises of the petitioner/claimant. Therefore, the facts on record clearly show that the petitioner/claimant had no option but to execute
such discharge vouchers without which no payment would have been released in its favour and it would have been forced to initiate lengthy legal
proceedings for recovery of the amount.
e. The Sole Arbitrator has completely missed the purport of Circular dated 24.09.2015 issued by IRDAI. The question was not whether the said
circular would apply retrospectively or not but one of the recognition of general trade practice whether discharge vouchers are being wrongly used by
the Insurance Companies to claim full and final discharge against the policy holders. Where the regulatory body itself recognises such mal-practice,
Sole Arbitrator could not have ignored the same.
The Arbitrator, while relying upon the judgment of Supreme Court in Union of India v. Master Construction Company, (2011) 12 SCC 349, failed
to appreciate that in that case Supreme Court had analysed the terms of the certificate issued by the contractor at the time of receiving the payment
on account of the final bill and found that No Claim Certificate was given voluntarily and the contract stood discharge voluntarily.
In the case of New India Assurance Company Limited v. Genus Power Infrastructure Limited, (2015) 2 SCC 424, the Supreme Court again
analysed terms of the letter of subrogation, which was on a stamp paper, accepting the amount in full and final settlement of the claim under the
policy. The Court found that there was no protest or demur raised around the time or soon after the letter was signed.
The above two cases were, therefore, clearly distinguishable inasmuch as the terms of the discharge vouchers had not been filed before the
Arbitrator. As there were three discharge vouchers executed over a period of 1 ½ years and the witness of the respondent had clearly admitted that
no payment would have been released without the petitioner having executed such discharge vouchers, in my opinion, the present case was clearly
covered under illustration (iv) given in paragraph 52 by the Supreme Court in National Insurance Company Limited v. Boghara Polyfab Private
Limited, (2009) 1 SCC 267. The same is reproduced herein below:
“52xxxxxx
(iv) An insured makes a claim for loss suffered. The claim is neither admitted nor rejected. But the insured is informed during discussions
that unless the claimant gives a full and final voucher for a specified amount (far lesser than the amount claimed by the insured), the entire
claim will be rejected. Being in financial difficulties, the claimant agrees to the demand and issues an undated discharge voucher in full and
final settlement. Only a few days thereafter, the admitted amount mentioned in the voucher is paid. The accord and satisfaction in such a
case is not voluntary but under duress, compulsion and coercion. The coercion is subtle, but very much real. The `accord' is not by free
consent. The arbitration agreement can thus be invoked to refer the disputes to arbitration.â€
In view of the above, the finding of the Sole Arbitrator regarding the discharge vouchers having fully and finally settled the claim of the petitioner/
claimant cannot be sustained.
My above finding, however, is not sufficient to set aside the Award passed by the Sole Arbitrator inasmuch as the Sole Arbitrator, inspite of his
above finding on the discharge vouchers, has proceeded to examine the claim of the petitioner/claimant on its own merit. As the Sole Arbitrator has
dismissed the claim made by the petitioner on merit, the same has been challenged before me on all heads of claim. I shall now be examining each
heads of claims separately.
CLAIM TOWARDS COST OF NEEDLE ASSEMBLY MACHINE OF Rs.66,22,393
This claim of the petitioner has been rejected by the arbitrator relying upon the findings of the Surveyors who had come to the conclusion that the
claim has to be disallowed for the entire Needle Assembly Machine based on the exclusion from liability contained in Clause 7 of the policy condition.
Clause 7 of the policy reads as under:
Loss, destruction or damage to any electrical machine, apparatus, fixture or fitting arising from or occasioned by over-running,
excessive pressure, short circuiting, arcing, self-heating or leakage of electricity from whatever caused (lightning included) provided that
this exclusion shall apply only to the particular electrical machine, apparatus, fixture or fitting so affected and not to other machines,
apparatus, fixtures or fittings which may be destroyed or damaged by fire so set up.
Learned counsel for the petitioner submits that the arbitrator has failed to appreciate that in an insurance contract where there is any ambiguity or
terms which are capable of two possible interpretation, one being beneficiary to the insured should be accepted. He further submits that arbitrator has
committed an error by merely relying upon the recommendation of the surveyors in support of rejection of its claim.
I have considered the submission made by the learned counsel for the petitioner, however, I am unable to accept the same. Clause 7 of the policy
clearly mentions where loss or destruction to any electric machine or apparatus is caused by over running, excessive pressure etc., the policy would
not cover such a loss. It is correct that the proviso to Clause 7 limits the exclusion only to that particular machine or apparatus and does not extend to
the exclusion of other machines which may be destroyed or damaged by fire, in the present case, the Needle Assembly Machine was found to be one
unit by the Surveyor. The Arbitrator records that no cogent reason has been given by the petitioner for challenging the said finding of the Surveyor.
Even before me no such reason could be given. A machine may contain various parts. The purpose of Clause 7 is not to confine the exclusion to a
part of the machine but to the whole machine itself. There is no ambiguity in Clause 7 which would require any interpretation or application of principle
of interpretation as was sought to be contended by the learned counsel for the petitioner.
In view of the above, the challenge to the Arbitral Award, as far as the claim with respect to the Needle Assembly Machine is concerned, is
rejected.
CLAIM IN RESPECT OF DEDUCTION BY THE HEAD OFFICE OF THE RESPONDENT AGAINST RECOMMENDATION OF
SURVEYOR OF RS.1,51,05,165/-.
This claim was surmised on the fact that from the amount recommended by the Surveyor, the respondent had proposed a deduction of
Rs.1,51,05,165/-, which was accepted by the Surveyor in its final report without any notice or opportunity on hearing given to the claimant/petitioner.
The petitioner placed reliance on Regulation 9(3) of the Insurance Regulatory and Development Authority (Protection of Policyholders’ interest)
Regulations, 2002 (IRDA Regulation). The same is quoted herein below:
“9. Claim procedure in respect of a general insurance policy
(1) xxxxxxxxxxxxxx
(2) xxxxxxxxxxxxxx
(3) If an insurer, on the receipt of a survey report, finds that it is incomplete in any respect, he shall require the surveyor under intimation to
the insured, to furnish an additional report on certain specific issues as may be required by the insurer. Such a request may be made by the
insurer within 15 days of the receipt of the original survey report:
Provided that the facility of calling for an additional report by the insurer shall not be resorted to more than once in the case of a claim.â€
It is contended that though the above Regulation was cited before the Arbitrator, he has not considered the same. It is further contended that in
answers to question Nos.12 and 13, Mr.Sandeep Bharti, Surveyor, who was brought as a witness by the respondent, clearly admitted that the mode of
calculation by the respondent “was also acceptableâ€. It is therefore, contended that the Surveyor did not say that its earlier calculation was
incorrect. In view of above answer, it is submitted that the deduction made by the respondent was arbitrary.
Learned counsel for the respondent, on the other hand, submits that though it may be correct that intimation to the petitioner was necessary when
the respondent had proposed a deduction to be made from the initial report of the Surveyor, same was inconsequential. He submits that before the
Arbitrator complete calculation with respect to the claim amount was submitted and as recorded by the arbitrator in the impugned award, no infirmity
could be pointed out by the petitioner in the same.
Arbitrator has rejected this claim observing as under:
“47. I have considered the submissions made by the parties in this regard. It is an admitted position that the Respondent has reduced an
amount of Rs.1,51,05,165/-from the amount assessed by the Surveyors. Although, the Surveyor report is very relevant and material but yet
the Respondent insurer could always have different view with regard to assessment made by the Surveyors provided the aforesaid dissent is
based on valid, strong and sound reasons. In this regard, Mr. Vijay Sharma, RWl who is the Regional Manager of the Respondent company
has elaborately stated in his evidence the reasons which led to reworking of the amount at the Head Office and thereby arriving at a
different amount of Rs. 1,51,05,165/-. I have no reason to doubt the said reasoning. I rather find that the reworking is based on sound
principle, which is also accepted to be so by Mr. Sandeep Bharti,RW2.(Surveyor). The witness has also stated in his evidence that while
process and finalizing amount payable to the Claimant at the Head Office of the Respondent, the amount of assessment was reworked
adopting a different method which is also a normal practice, and the amount of assessment was reworked out to be Rs.32,39,58,291/-. The
said witness was also cross examined and he had deposed that Head Office of the Respondent consulted the Surveyor on the working but 6f
the claim and that the mode of calculation adopted by the Head Office of the Respondent was also acceptable. Neither during the cross
examination of the said witness nor during the time of final arguments, it could be shown by the Claimant that the reasoning and mode of
calculation adopted by the Head Office of the Respondent as wrong and erroneous. The Claimant was unable to prove that the reasoning
given by the Respondent while differing with the recommendations of the surveyor is wrong. Therefore, the aforesaid claim of the Claimant
also is rejected.â€
Having considered the above finding of the Arbitrator, I find no infirmity with the same. In the present case, even if it is assumed that there was
violation of Principle of Natural Justice and/or violation of Regulation 9(3) of the IRDA Regulation, the same would not ipso facto result in allowing
the claim of the petitioner. The Arbitrator, taking into account the evidence led before him has found that the petitioner could not prove that the mode
of calculation adopted by the respondent was wrong or erroneous. On the other hand, Arbitrator has found the work to be based on sound principle. In
fact, no submission was made before me to show how the calculation adopted by the respondent was incorrect or unreasonable. In view of the above,
challenge to the Award as far as denial of this claim, cannot be accepted.
CLAIM TOWARDS EXCISE DUTY REVERSAL CHARGES OF Rs.12,20,931/-
The Arbitrator has rejected the above claim observing as under:
“50. I have considered the submissions made by the parties. The Surveyor RW2 on oath has stated that the said claim is an afterthought
as the same was neither claimed in the claim bill nor did the Claimant submit the break up details with documentary support. The claim made
by the Claimant at page 83 of the documents filed by the Claimant as well as Exhibit RW2/3 clearly show that there is no such Claim as
Excise duty reversal charges. The said Surveyor in his cross examination has clearly deposed that excise duty reversal was not claimed by
the Claimant in the claim bill. He had also stated that such excise duty reversal if any was required to be certified by the Excise authorities.
This fact is not disputed. Admittedly in the instant case no such certificate was either produced or filed by the Claimant to the Surveyor or
before me during the proceedings. The official certificate is not available on record, which according to the Surveyor is mandatory for
granting such claim and hence, I am of the view that the said amount cannot be allowed in favour of the Claimant.â€
Learned counsel for the petitioner contends that the finding of the Arbitration is perverse as he has not only ignored the documents filed before
him but has also not considered the relevant provision of Excise Manual which provides that such duty reversal can be claimed by the petitioner by
merely making an entry in the CENVAT Credit Account maintained by him and does not require any certificate from the Excise Department. He
further submits that the Arbitrator has failed to take note of email dated 22.07.2013 addressed by the petitioner to the Surveyor raising a claim towards
reversal of Excise Duty on an asset. He submits that the finding of the Arbitrator that such claim was not raised before the Surveyor is, therefore,
contrary to the documents produced before the Arbitrator and in ignorance of the same.
On the other hand, learned counsel for the respondent submits that the email dated 22.07.2013 had been filed by the petitioner only after
conclusion of the evidence led by the respondent. There was no reference of this email in either Statement of Claim or the evidence led by the
claimant. In any case, the said claim has been rejected on the ground that the same was an afterthought.
I have considered the submissions made by the counsel for the parties. Admittedly, the email dated 22.07.2013 was filed by the petitioner only
after the conclusion of cross-examination of the witness produced by the respondent. It is also important to note that the said email was not filed as an
additional document before the Arbitrator but was simply filed as a part of the application seeking production of the records from the respondent. The
said document was, therefore, not produced in evidence before the Arbitrator and in my opinion, therefore, cannot be relied upon. Equally, the finding
of the Arbitrator that claim for Excise Duty reversal could not be granted in the absence of a certificate from the Excise Authorities, cannot be stated
to be perverse or in violation of the statutory provision. It may be true that the assessee may make an entry of such reversal in his book of accounts,
however, once the claim in this regard is made to a third party like Insurance Company who insist on proof of the same and production of the
necessary certificate from the Excise Department, denial of the claim on non-production cannot be said to be arbitrary or perverse. In fact, in the
petition filed before me, there is no ground for challenging the Arbitral Award on the plea of non-consideration of this email dated 22.07.2013.
In view of the above, I find no merits in the challenge to the Arbitral Award as far as the rejection of this claim is concerned.
Claim Towards Slow Moving Dead Stock @ 1.5% Of The Stock Value Of Rs.12,45,957/-
Learned counsel for the petitioner has submitted that the respondent had arbitrary deducted 1.5% of the stock value towards slow moving/dead
stock. This was challenged before the Arbitrator, however, the Arbitrator has also rejected the said claim without appreciating the evidenced led
before him. It is submitted that the books of account produced by the petitioner before the Surveyor showed no entry towards dead stock or slow
moving stock, therefore, such deduction could not have been made.
The finding of the Arbitrator on this claim is in paragraph 57 of the Award which is quoted herein below:
“57. I find that the Surveyor in the report has stated that a reasonable amount of 1.5% of the stock value is considered for deduction for
slow moving/dead stock. This is the categorical finding recorded by the Surveyor who was the expert in the field. I also agree with the
argument of the Counsel for the Respondent that the Surveyor is also aware of the nature and practice of the industry and therefore
capable of taking reasonable and conscious decision regarding the extent of deduction to be made on account of slow moving/dead stock.
The Counsel for the Claimant has not been able to show the relevant books of accounts have been produced by the Claimant to substantiate
this claim. In the absence of proof of the claim, the claim is found to be not tenable.’’
As far as this claim is concerned, question number 19 to 22 put to Mr.Sandeep Bharti Surveyor are relevant and are reproduced herein below:
“Q.19 What do you mean by dead stock?
A. It is that stock which is not sold in normal course of business and gets accumulated in due course of time in the industry.
Q.20 Is there any provision in the books of the claimant for the dead stock/slow moving stock?
A. Since majority of their records got burnt, they were not able to produce their complete set of books of accounts and stocks.
Q.21 What was the basis for taking 1½ % of the dead stock in your survey report?
A. It is as per industry norms, keeping in view the manufacturing product of the claimant.
Q.22 I put it to you that you have taken the percentage of 1½ % on the basis of assumption and the same is not based on any rationality.
What do you have to say?
A. I deny the suggestion.â€
The Arbitrator has appreciated the evidence led before him, specially the evidence of the Surveyor and has placed reliance on the same. It,
therefore, cannot be said that the finding of the Arbitrator is based on no evidence or on surmises. In the case of Associate Builders v. Delhi
Development Authority, (2015) 3 SCC 49 Supreme Court explained the limit of challenge to an Arbitral Award on the ground of it being in conflict
with ""Public Policy of India"" in the following words:-
“33. It must clearly be understood that when a court is applying the “public policy†test to an arbitration award, it does not act as a
court of appeal and consequently errors of fact cannot be corrected. A possible view by the arbitrator on facts has necessarily to pass
muster as the arbitrator is the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award.
Thus an award based on little evidence or on evidence which does not measure up in quality to a trained legal mind would not be held to be
invalid on this score. Once it is found that the arbitrators approach is not arbitrary or capricious, then he is the last word on facts. In P.R.
Shah, Shares & Stock Brokers (P) Ltd. v. B.H.H. Securities (P) Ltd.[(2012) 1 SCC 594 : (2012) 1 SCC (Civ) 342] , this Court held: (SCC pp.
601-02, para 21)
“21. A court does not sit in appeal over the award of an Arbitral Tribunal by reassessing or reappreciating the evidence. An award can
be challenged only under the grounds mentioned in Section 34(2) of the Act. The Arbitral Tribunal has examined the facts and held that
both the second respondent and the appellant are liable. The case as put forward by the first respondent has been accepted. Even the
minority view was that the second respondent was liable as claimed by the first respondent, but the appellant was not liable only on the
ground that the arbitrators appointed by the Stock Exchange under Bye-law 248, in a claim against a non-member, had no jurisdiction to
decide a claim against another member. The finding of the majority is that the appellant did the transaction in the name of the second
respondent and is therefore, liable along with the second respondent. Therefore, in the absence of any ground under Section 34(2) of the
Act, it is not possible to re-examine the facts to find out whether a different decision can be arrived at.â€
It is with this very important caveat that the two fundamental principles which form part of the fundamental policy of Indian law (that the
arbitrator must have a judicial approach and that he must not act perversely) are to be understood.â€
Once the Arbitrator has appreciated the evidence led before him, this Court cannot sit in an appeal over it and re-examine the facts to find out
whether a different decision can be arrived at. In view of the above, the challenge to the Arbitral Award, so far as rejection of the claim of the
petitioner towards deduction for slow moving/dead stock, cannot be sustained.
CLAIM TOWARDS DEDUCTION ON ACCOUNT OF TECHNOLOGICAL ADVANCEMENT OF Rs.1,66,00,000/-
Learned counsel for the petitioner has submitted that the respondent had made arbitrary deduction on account of technological advancement
against the value of the machine and the challenge against the said deduction has been arbitrarily rejected by the Arbitrator merely relying upon the
report of the Surveyor. Placing reliance on the judgment of Supreme Court In New India Assurance Company Limited v. Pradeep Kumar, (2009)
INSC 713, United India Insurance Co. Ltd. v. M/s Pushpalaya Printers (2004) 3 SCC 694 and M/s Suraj Mal Ram Niwas Oil Mills. V. United India
Insurance Co. Ltd., (2010) 10 SCC 567, it is contended that the Surveyor's report is not the last and final word; it is not that sacrosanct that it cannot
be departed from; it is not conclusive.
There is no doubt on the above proposition of law, however, I find that in the present case the Arbitrator has taken into account that the machine,
that was destroyed in fire, was no longer available in the market due to which the petitioner claims to have purchased a machine of higher capacity.
Arbitrator, therefore, found that the proportionate deduction made by the Surveyor because of the purchase of high capacity machine was justifiable
and cannot be said to be erroneous or fallible or not based on reason. It is therefore, not the case where the Arbitrator has simply relied upon the
report of the Surveyor. It is a case where the Arbitrator finds the report of the Surveyor to be correct and as following a reasonable approach. In my
opinion, therefore, the above referred judgments would be of no assistance to the objection raised by the petitioner. The same is, therefore, rejected.
CLAIM TOWARDS WRONGLY CHARGED DEPRECIATION ON NON REINSTATED PLANT AND MACHINERY OF
RS.83,24,032/-
Learned counsel for the petitioner submits that by taking a fewer numbers of years as life of the plant and machinery, higher value of depreciation
was arrived at by the Surveyor. This was contrary to the Schedule II-Useful Lives to compute depreciation under the Companies Act, 2013. It is
submitted that in support, this provision having been drawn to the attention of the Arbitrator and a calculation sheet being given showing the
overcharging of depreciation amount, the arbitrator has rejected the said claim, in an arbitrary manner.
On the other hand, learned counsel for the respondent submits that barring producing the extract of the above referred provision of the Companies
Act and a chart based on such provision, there was neither any pleading nor any evidence led by the petitioner to show the life of the machine, in form
of any brochures or material from the manufacturers or otherwise and therefore, the finding of the Surveyor, in this regard, has been rightly relied
upon by the Arbitrator.
Finding of the Arbitrator with regard to the above claim is in paragraph 63 of the Arbitral Award, which is quoted herein below:
“63. I have heard the parties in this regard. It has been contended by the Claimant that the deduction on account of depreciation of non-
reinstated machines should have been taken as recommended by the Companies Act or following the depreciation or the basis of life span of
the machines as per the certificate given by its manufacturer. However, no reason or calculation as to how the depreciation charged in
respect of the Machines in question was on higher side is submitted nor the calculation in terms of the provisions of Company Law has been
placed on record by the Claimant. The Surveyor RW2 has deposed that the depreciation was taken on the basis of operational life of the
Machinery and equipment based upon its usage and maintenance and also relied on internal page 17 to 26 of the Joint Final Survey
Report. I have not found any reason for forming a contrary view. Therefore, in the absence of any basis or calculation to show that the
deduction made on account of depreciation of non-reinstated plant and machinery was on the higher side, this claim stands rejected as
being not tenable.â€
A reading of the above would show that the Arbitrator has come to the conclusion that surveyor report, so far as it relates to operational life of the
machinery and equipments based upon it usages and maintenance, could not be shown to be unreasonable. It may be correct that the computation in
terms of the provision of Companies Act has been placed before the Arbitrator, however, merely on that ground the finding of the Arbitrator cannot
be upset by this Court in exercise of its power under Section 34 of the Act specially when, apart from making a reliance on the above mentioned
provision, no other document or material has been shown as to the nature of the machine, and/or the amount of the depreciation claimed in the books
of account etc. As stated above, the Arbitrator has relied on the deposition of Surveyor with regard to the above claim and I find no reason to
interfere with such findings.
CLAIM OF INTEREST IN DELAY IN SETTLEMENT/PAYMENT
The petitioner has relied upon Regulation 9(6) of the IRDA Regulation. The same is quoted herein below:-
“9.Claim procedure in respect of a general insurance policy-
xxxx
xxxx
xxxx
xxxx
xxxx
Upon acceptance of an offer of settlement as stated in sub-regulation (5) by the insured, the payment of the amount due shall be made
within seven days from the date of acceptance of the offer by the insured. In the case of delay in the payment, the insurer shall be liable to
pay interest at a rate which is 2 per cent above the bank rate prevalent at the beginning of the financial year in which the claim is reviewed
by it.â€
Relying upon the above, it is contended that the petitioner was entitled to interest on the delayed payment inasmuch as the report of the Surveyor
had been received by the respondent in August 2013, whereas the payment of Rs.20,41,60,835/-was released only on 16.12.2013 and the remaining
amount of Rs.1,88,78,410/- was released only on 09.05.2014 i.e. much beyond the period of 7 days as stipulated in Regulation 9(6) quoted above.
Learned counsel for the respondent has drawn my attention to paragraph 27 of the Statement of Defence filed before the Arbitrator which shows
that even after the Surveyor Report, the petitioner could not show the documents which would satisfy that they had made payment to vendors. These
documents were produced only under the cover of emails dated 13.12.2013 and 18.03.2014 and immediately after completion of formalities like NOC
from Banker with whom the property in question was endorsed, payment had been released in favour of the petitioner on 16.12.2013 and 09.05.2014
respectively. It is therefore, submitted that there was no delay on part of the respondent in releasing the amount of claim in favour of the petitioner.
The Arbitrator has rejected the said claim. His findings are in paragraph 67 of the Award, which is quoted herein below:-
“67. I have considered the submissions. Even though there was a delay in release of amount of claim, the delay was not on account of
any lapse on the part of the Respondent. It was incumbent on the Respondent to follow certain procedure of conducting survey and making
proper assessment of loss before the amount is released. For the purpose of enabling expeditious settlement, it was for the Claimant to
produce all the relevant documents/materials in time before the Surveyor. It is seen from the records that the initial payment of Rs.10 crores
was received by the Claimant within a period of less than six months, despite delay in submission of the requisite documents by the Claimant
for finalization of survey report which could be finalized only in August 2013 i.e., after 14 months. The payment of Rs. 10 crores within five
months of the fire i.e. much prior to the finalization of Survey Report, was made only with a view only to help the Claimant. Therefore, the
delay in payment / settlement was not occasioned by the delay caused by the respondent but by the Claimant. It is settled law that no person
can take advantage of his own wrong. Hence, the claim put forth by the claim on account of interest for delayed payment does not merit
consideration.â€
The Arbitrator has, therefore, found that the delay in releasing the payment was due to failure of the petitioner to produce the relevant
documents/material in time before the Surveyor. The Arbitrator has come to a finding that the delay in releasing the amount of claim was not on
account of any lapse on the part of the respondent. I, therefore, find no merit in the said claim of the petitioner on this head or the finding of the
arbitrator to be perverse in any manner.
In view of the above, I find no merit in the present petition and same is accordingly dismissed with no order as to cost.
