High CourtsSingle Bench

M/S. Powertec Engineering Pvt. Ltd vs M/S. Mecon Ltd

Delhi High Court · Decided on 11 September 2019 · Citation: (2019) 09 DEL CK 0086

HON’BLE JUDGES
Jyoti Singh, J
ACTS & SECTIONS REFERRED
Arbitration And Conciliation Act, 1996 — Section 29A(4)
RESULT
Disposed Off
CASE NUMBER
Original Miscellaneous Petition (MISC.)(COMM.) No. 365 Of 2019, Miscellaneous Application No. 12545 Of 2019
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

12 paragraphs · 302 words

Jyoti Singh, J

I.A. No. 12545/2019 (Exemption)

Exemption allowed subject to all just exceptions.

Application stands disposed of.

O.M.P. (MISC.) (COMM) NO.365/2019

1.

This is a petition filed under Section 29A(4) of the Arbitration & Conciliation Act, 1996 (hereinafter referred to as 'the Act') for seeking extension of time to conclude the arbitral proceedings and to pass an Award.

2.

The inter se dispute arose between the parties with respect to the Memorandum of Understanding dated 20.09.2012. The Arbitral Tribunal entered into reference on 09.03.2018. The statutory period of 12 months for passing the award having expired, the mandate of the Tribunal was extended for a period of six months w.e.f. 09.03.2019, with the consent of both the parties, in the hearing dated 14.2.2019 before the Arbitral Tribunal.

3.

Oral arguments of the parties were concluded on 21.08.2019 with directions to the parties to file their written arguments, within two weeks therefrom. The extended period of 6 months came to an end on 08.09.2019. It is submitted that the learned Tribunal requires 4-5 weeks after receipt of the written arguments to pass the Award.

4.

Learned counsel for the petitioner has drawn the attention of this court to an order dated 21.08.2019 passed by the Arbitral Tribunal, wherein the parties have consented to extension of time by a period of 4-5 weeks w.e.f. 08.09.2019.

5.

Since there is a consent for extension of time, therefore, notice is not required to be sent to the respondent.

6.

In view of the averments made in the petition and the order dated 21.08.2019 passed by Arbitral Tribunal, the present petition is allowed and the time for completion of arbitration proceedings and making the award is extended by a further period of six weeks from 08.09.2019.

7.

The petition is disposed of in the aforesaid terms.