AI Structured Summary
Not yet generated for this judgment
Judgment
This writ petition is filed by the petitioner seeking
following reliefs:
"It is therefore, most respectfully prayed that the writ petition filed by the petitioner may be allowed and by an appropriate writ, order or direction:-
(i) The order No. 4049 dated 17-11-17 (Annexure P-7) by which the petitioner was declared unsuccessful for bid no.3/17-18 and bid No.4/17-18 may be quashed and set aside.
(ii) That the order No. 4061 dated 17-11-17 (Annexure P-8) by which tender regarding bid No.3/17-18 was sanctioned in favour of the M/s Krishna & Company, may be quashed and set aside.
(iii) That the order No.2095 dated 17-11-17 (Annexure P-9) by which the tender regarding bid No. 4/17-18 was sanctioned in favour of the M/s JRC Construction may be quashed and set aside.
(iv) That the bid information No. 3/17-18 (item No. 4) regarding work of repair, restoration and modeling works from 0 K.M. to 23 K.M. at Balera Distribution System may be awarded to the petitioner firm.
(v) That the bid information No. 4/17-18 (item No. 1) regarding work of repair, restoration and modeling works of Palri Sub Minor distribution system of Sanchore Lift Canal, may be awarded to the petitioner firm
(vi) Any other order or direction, which may be deemed just and proper in the facts and circumstances of the case, may kindly be passed in favour of the humble petitioner."
The facts, which are not in dispute, are that the
petitioner submitted its bids pursuant to NIT Nos. 3 and 4 of
2017-2018 issued by the Office of the Superintending Engineer,
Narmada Nahar Pariyojna, Circle-II, Sanchore for item No.4 and
item No.1 respectively.
The petitioner was found successful in technical bids
in both the above referred NITs and thereafter the financial bids
were also opened and the petitioner''s bids were found lowest for
both the works. However, on 17.11.2017, the respondent-
department declared the petitioner''s bids unsuccessful in both
the NITs citing the reason that the petitioner does not qualify as
per clause 3.2(b) of the tender document as it does not have
requisite experience of executing similar nature of works. Being
aggrieved with this, the petitioner has filed this writ petition.
Learned counsel for the petitioner has submitted that
once the financial bids of the petitioner were opened and the
bids quoted by it were found lowest, the respondent-department
has no authority to cancel the bids of the petitioner for the
reason that the petitioner does not have requisite experience of
executing similar nature of works.
It is also contended that the respondent-department
has also illegally declared the respondent No.6 tender No.3 as
the L/1 by accepting the fresh bid of it by reducing bid amount
though the same is not permissible under the law. It is further
submitted that similarly the respondent-department has also
illegally accepted the fresh bid of respondent No.4 for NIT No.4
by reducing its bid amount.
Learned counsel for the petitioner has further argued
that the reason given by the respondent-department for
rejecting the bids of the petitioner in respect of the concerned
NITs is entirely false because from the works experience
certificate submitted by the petitioner along with bid documents,
it is clearly established that the petitioner is having requisite experience of completing similar kind of work for which it has
submitted the bids.
It is further contended that once the respondent-
department has considered the work experience of the petitioner
as suitable, it cannot review its decision and such an action of
the respondent-department is absolutely illegal and without
jurisdiction.
Learned counsel has, therefore, prayed that the
action of the respondent-department of rejecting the bids of the
petitioner submitted pursuant to the NIT No.3 and 4/2017-18
be set aside and the reliefs prayed for in this writ petition be
granted.
Reply to the writ petition is filed on behalf of the
respondent-State, wherein preliminary objection regarding the
availability of alternative remedy of filing an appeal as provided
under section 30 of the Rajasthan Transparency in Public
Procurement Act, 2012 (for short ''the Act of 2012'' hereinafter)
has been taken.
It is also submitted that as per Rule 72 of Rajasthan
Transparency in Public Procurement Rules, 2013 (for short ''the
Rules of 2013'' hereinafter), the procuring entity is having all the
jurisdiction to accept or reject any bid at any point of time prior
to award of contract and in view of the above, it is wrong to say
that after accepting the financial bid, the respondent-department
has no authority or jurisdiction to reject the said bid.
In reply to the writ petition it is averred that though
the technical bids of the petitioner were accepted and the
financial bids were also opened and the petitioner''s bids were
found lowest amongst the other bidders but the respondent-
department has received a complaint with the allegation that the
petitioner does not have the requisite experience in terms of
clause 3.2(b) of the tender document and its bids have wrongly
been accepted. Therefore, pursuant to the directions given by
the Superintending Engineer, Narmada Nahar Pariyojna, Circle-I
and II, re-examination of the petitioner''s experience was
conducted as per Rule 331 of Public Work (Finance and Account)
Rules, 1999 by a review committee and the review committee
has found that the petitioner does not possess the requisite
experience as prime contractor in completing at least one
contract of nature and complexity within last five financial years
and, therefore, the bids of the petitioners have been rejected.
An additional affidavit is filed on behalf of the
respondent-department in which it is clarified that as per clause
3.2(b) of the NIT No.3/17-18 and 4/17-18, the petitioner was
required to have experience of same nature amounting to Rs.88
lac in one work in relation to Bid No.3 and Rs.98 lac in one work
in relation to Bid No.4. It is averred that from the documents
submitted by the petitioner along with its bids, it is clear that the
petitioner was not having the requisite experience as per clause
3.2(b) of the tender document and, therefore, his financial bids
have rightly been rejected.
Heard learned counsel for the parties and perused the
material available on record.
So far as argument of the learned counsel for the
petitioner to the effect that the respondent-department has no
jurisdiction to reject the financial bids of the petitioner in respect
of the NITs 3/17-18 and 4/2017-18 after accepting the same is
concerned, the same is not liable to be accepted in view of Rule
72 of the Rules of 2013, which provides that the procuring entity
has right to accept or reject any bid at any point of time prior to
the award of contract.
Admittedly, in the present case, the contract has not
been awarded till the financial bids of the petitioner had been
rejected.
The another contention of the learned counsel for the
petitioner is to the effect that the reason for rejecting the
financial bids of the petitioner cited by the respondent-
department are entirely false, is also not liable to be accepted.
Clause 3.2(b) of the tender document specifically
provides that bidder shall have successful experience as prime
contractor in completing at least one contract of a nature and
complexity comparable to the proposed contract within the last
five financial years from the of publication of NIT of value not
less than 30% of G-Schedule amount. 30% of G-Schedule
amount has also been specified in clause 3.2(b) of the tender
document. In the tender document, the work of similar nature
of complexity comparable to the proposed contract has also
been clarified.
From the documents produced by the petitioner along
with this writ petition, it appears that though the petitioner is
having experience of completing similar nature of work for which
he has submitted its bids but the petitioner has not completed at
least one contract of a nature and complexity comparable to the
proposed contract within the last five financial years from the of
publication of NIT of value not less than 30% of G-Schedule
amount in both the tenders.
Learned counsel though has tried to convince this
Court that the work completed by the petitioner in last five years
of construction of a road i.e. Gramin Gaurav Path is similar to
the construction of a canal or the work for which the petitioner
has submitted its bids and the costing of the said work was
much more than 30% of the G-Schedule amount of the proposed
contracts, but I am not impressed with it because the
respondent-department has already clarified in the tender
document that which works will be treated as similar in nature
and complexity comparable to the proposed contract and this
Court cannot add something else in the said clarifications while
exercising extraordinary jurisdiction of this Court. It is the
prerogative of the procuring entity to treat the various works as
similar in nature and the said action of the procuring entity can
not be subject to judicial review.
The other contention of the learned counsel for the
petitioner to the effect that the respondent-department has
illegally accepted the fresh bids of the respondent Nos. 4 and 5
by reducing bid amounts is also having no merit in view of the
submission made by the learned counsel for the respondent-
department that after rejection of the bids of the petitioner, the
bids of respondent Nos. 4 and 5 were found responsive and the
department after interacting with them has persuaded them to
reduce their bid amounts and when they reduced it, the same
has rightly been accepted by the department.
In view of the above discussions, I do not find any
merit in this writ petition and the same is hereby dismissed.
There shall be no order as to costs.
Stay petition also stands dismissed.
