High CourtsSingle Bench

M/s Woodhill Infrastructure Ltd. vs Superintending Engineer

Uttarakhand High Court · Decided on 22 May 2026 · Citation: (2026) 05 UK CK 1183

HON’BLE JUDGES
Manoj Kumar Gupta, CJ
RESULT
Disposed Of
CASE NUMBER
Arbitration Application No. 32 Of 2025
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

13 paragraphs · 338 words

Manoj Kumar Gupta, CJ

1.

On 27.03.2026, the following order was passed :

1.

Mr. Rohit Arora, learned counsel for the applicant.

2.

Mr. B.S. Parihar, learned Additional Chief Standing Counsel for the State.

3.

Under the arbitration clause the arbitration has to be done by arbitral tribunal consisting of three arbitrators, one each to be appointed by the employer and the contractor and, the third arbitrator to be chosen by the two arbitrators so appointed by the parties. The applicant has appointed its arbitrator and has conveyed the same to the respondent vide notice dated 14.02.2025. However, the respondent has not appointed its arbitrator so far on the pretext that work is not complete and that the applicant owes certain amount to the department.

4.

The submission of learned counsel for the applicant is that the said plea could form subject matter of arbitration but on the said ground the respondent cannot refuse to appoint its arbitrator.

5.

The submission appears to have force.

6.

By way of last opportunity two weeks' time is granted to the respondent-department to name its arbitrator so that the two arbitrators appointed by the parties may appoint a presiding arbitrator and the arbitration could commence.

7.

Learned State counsel Mr. B.S. Parihar undertakes to communicate the instant order to the respondent so that necessary action is taken by the next date. He will also obtain instructions in this regard from the department and inform the Court accordingly.

8.

List after three weeks.

2.

In compliance of the said order, the Department has appointed K.P. Joshi, Chief Engineer Level-1 (Retd.), PWD, resident of Nawabi Road, Haldwani, Nainital as its Arbitrator. Under the agreement, the two named Arbitrators have to appoint a Presiding Arbitrator.

3.

As the parties have appointed their Arbitrators, the application is disposed of, by providing that the two named Arbitrators shall now appoint a Presiding Arbitrator, and the Arbitral Tribunal so constituted shall proceed to adjudicate the dispute between the parties.

4.

All pending applications stand disposed of accordingly.