AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
148 paragraphs · 3,119 wordsS. Ravindra Bhat, J.
C.M. NO. 15154/2013 (for condonation of delay)
For the reasons mentioned in the application, C.M. No. 15154/2013 is allowed.
RFA (OS) 125/2013, C.M. NO. 15155/2013 & 15156/2013
This is an appeal from an order of the learned Single Judge declining the unsuccessful defendant''s (in the suit, and the appellant herein) leave to
defend a suit brought under Order XXXVII of the CPC (""CPC"") by Jindal Steel and Power Ltd. (hereinafter ""JSPL"") for recovery of a principal
sum of Rs. 2,98,39,060/- along with interest at the agreed rate of 10% per annum accrued thereon with effect from April, 2007 to March, 2008
and thereafter at 12% per annum from April, 2008 till the institution of the suit in February, 2010, thus amounting to a total amount of Rs.
4,00,44,341.20/-. As the Single Judge records, the pleading on behalf of the plaintiff is as follows:
XXXXXX XXXXXX XXXXXX
(i) that the defendant is the sole proprietor of M/s. Guru Mehar Construction;
(ii) that in December, 2000, the defendant approached the plaintiff with offer to conduct the excavation activities required by the Plaintiff at its
mining site near Dongamohua village, District Raigarh, Chhattisgarh;
iii) that after negotiations and deliberations, the plaintiff awarded to the defendant, the contract for hiring of heavy earth moving equipment and
services for excavation works for a total period of four years i.e. till March, 2005 vide Work Order dated 02.03.2001;
(iv) that vide letter dated 13.06.2005, the defendant requested the plaintiff to provide a one time soft loan of Rs. 7.17 crores recoverable over the
period of five years on the ground that the defendant needed to replace and revamp the existing equipments;
(v) that the plaintiff agreed to so provide financial assistance to the defendant as is evident from the letters exchanged between the parties and
disbursed the loan to the defendant and the defendant agreed to the plaintiff deducting instalments from the amounts becoming due and payable by
the plaintiff to the defendant on the basis of bills raised by the defendant for the work done under the aforesaid Work Order;
(vi) that thereafter the defendant vide its letter dated 16.06.2005 informed the plaintiff that he needed a soft loan of Rs. 500 lacs but since the
plaintiff had agreed to provide a sum of Rs. 300 lacs only, the said sum of Rs. 300 lacs would be repayable by way of monthly installments of Rs.
10 lacs along with interest over a period of 30 months starting from November, 2005;
(vii) that the plaintiff released a total sum of Rs. 563 lacs to the defendant from 18.06.2005 to 17.11.2005, out of which a sum of Rs. 450 lacs
was paid directly to the defendant and a sum of Rs. 113 lacs paid to SREI Infrastructure Finance Ltd. for and on behalf of the defendant towards
lease financing of equipment;
(viii) that the defendant vide letter dated 24.11.2005 admitted and acknowledged the receipt of the aforesaid loan amount and requested for the
same to be repaid over a period of five years instead of 30 months as agreed earlier and which was agreed to by the plaintiff;
(ix) that the defendant vide letter dated 19.07.2006 further requested for release of a sum of Rs. 200 lacs for meeting its working capital
requirement and further Rs. 275 lacs to make down payment to financiers from whom he had got the required equipments financed on leasehold
basis;
(x) that in response to the aforesaid request, the defendant was provided additional financial assistance of Rs. 100 lacs on 02.08.2006;
(xi) that thus during December, 2004 till August, 2006 total financial assistance of Rs. 663 lacs was provided by the plaintiff to the defendant;
(xii) that the plaintiff vide its letter dated 17.07.2006, on the request of the defendant, agreed to renew the Work Order for the period starting from
15.02.2006 till 31.03.2007 and a formal Work Order dated 04.08.2006 was issued by the plaintiff and accepted by the defendant;
(xiii) that the defendant failed to perform his obligations under the Work Order and the plaintiff vide its letter/notice dated 08.11.2006 terminated
the said Work Order and called upon the defendant to pay the sum of Rs. 548.64 lacs along with interest and also to pay the liquidated damages;
(xiv) that the defendant challenged the legality and validity of the termination and raised a claim to the tune of Rs. 436 lacs on account of non
adjustments and being due to him under the Work Order though not disputing the outstanding of Rs. 548.64 lacs in the loan account;
(xv) that the plaintiff denied the claim of the defendant of Rs. 436 lacs and claimed the amount of Rs. 2,98,39,060/- towards principal outstanding
loan amount and Rs. 163.86 lacs under the work order;
(xvi) that the plaintiff thereafter filed an Arbitration Application No. 53/2009 u/s 11 of the Arbitration and Conciliation Act, 1996 before this
Court. The said petition was dismissed vide judgment dated 03.12.2009 holding that the loan transaction was independent of the Work Order and
not arbitrable under the arbitration clause in the Work Order; and
(xvii) that hence this suit for recovery of principal outstanding of Rs. 2,98,39,060 under the loan account with interest as aforesaid.
The appellant had argued before the learned Single Judge that there was no formalized contract between the parties on the basis of which a
liquidated amount of money claimed in the suit could be decreed. Further, it was submitted that, at any rate, this represented a triable issue, for
which leave had to be granted.
In response, JSPL relied on a letter dated 13.06.2005 from the appellant to it (JSPL) requesting a ""soft"" loan of Rs. 7.17 crores recoverable
over a period of 5 years; a letter dated 16.06.2005 from JSPL confirming the agreement for the loan amount; a further letter dated 24.11.2005 by
the defendant/appellant acknowledging a loan to the tune of Rs. 4.50 crores, and payment of Rs. 50 lakhs made to a third party on his behalf; a
letter dated 19.7.2006 from the said defendant requesting a loan of Rs. 2 crores for working capital; a letter dated 22.11.2006 from him stating
that the loan amount was being recovered as against the running bills raised on JSPL; and a letter dated 05.01.2007 from the defendant not
denying the payment on the loan account; and finally, his reply in Arbitration Petition No. 53/2009, where the loan transaction was not denied, but
rather, the plea taken was that the issue is not arbitrable.
The plaintiff relied on the dictum in M/s. Rickmers Verwaltung GMB H Vs. The Indian Oil Corporation Ltd., , for the proposition that
15...it is the duty of the court to construe correspondence with a view to arrive at a conclusion whether there was any meeting of mind between the
parties, which could create a binding contract between them but the Court is not empowered to create a contract for the parties by going outside
the clear language used in the correspondence, except insofar as there are some appropriate implications of law to be drawn. Unless from the
correspondence it can unequivocally and clearly emerge that the parties were ad idem to the terms, it cannot be said that an agreement had come
into existence between them through correspondence. The Court is required (sic, to consider) what the parties wrote and how they acted and from
that material to infer whether the intention as expressed in the correspondence was to bring into existence a mutually binding contract. The intention
of the parties is to be gathered only from the expressions used in the correspondence and the meaning it conveys and in case it shows that there
had been meeting of mind between the parties and they had actually reached an agreement, upon all material terms, then and then alone can it be
said that a binding contract was capable of being spelt out from the correspondence.
Equally, reliance was placed on the decision in Corporate Voice (P) Ltd. Vs. Uniroll Leather India Ltd., , for the proposition that a suit under
Order XXXVII CPC may be entertained on the basis of letters exchanged between parties. Thus, it was argued by the learned senior counsel that
the letters exchanged between the two parties here clearly establishes a liquidated debt due to JSPL.
Contrary to this, learned counsel for the defendant argued that the termination of the work order by JSPL was illegal, and that this issue required
to be tried. In these circumstances, it was argued that the judgment of this Court dated 31.08.2012 in GE Capital Services India v. Mayflower
Healthcare Pvt. Ltd. [CS(OS) 2859/2011], comes in the way of such suits, as the Court noted that the balance due at the foot of the account is
not the same as the original loan document, which contains a different amount, and thus, such a suit is not maintainable under Order XXXVII CPC.
In the course of hearing, on 23.01.2013, the Court directed the defendant to appear for recording of his statement, and to produce his books of
account, i.e. ledger and balance sheet for the relevant years and till date, showing the loan account with JSPL and to state how much money on the
loan account, according to him, was due to JSPL without adjustment of his counter-claim. This was ordered by way of an examination under
Order X, CPC. Accordingly, the defendant appeared and in the words of the Single Judge,
10...produced a bunch of documents comprising (sic) of 30 sheets containing inter alia the balance sheet of M/s. Guru Mehar Construction, sole
proprietary (sic) of the defendant and in which the sum of Rs. 2,98,39,060/-, being the principal amount claimed in the suit, was shown as loan
outstanding to the plaintiff as on 31.3.2011...
In view of this admission of the amount claimed by JSPL in the suit, the learned Single Judge held that the question of liability was now only an
academic exercise and accordingly, the Court would not pronounce on technicalities. Therefore, the learned Single Judge declined leave to defend,
and decreed the suit.
Learned counsel for the appellant impugns this order, and argues that Order XXXVII CPC is exhaustive in respect of the classes of cases to
which it applies. It is argued that despite admitting that the suit does not fall within any of the recognized heads, nonetheless the learned Single
Judge grants relief by way of the summary procedure. Learned counsel further contended that no finding is returned as to the existence of a written
contract, which could possibly be the basis of a decree in a summary suit. It was further contended that it is settled law that when the applicability
of Order XXXVII CPC itself is in question, the grant of leave to defend is to be as a matter of routine. This, it is argued, is especially so, since the
defence presented was not ''moonshine'', so as to justify the application of Order XXXVII CPC. On the question of the liability admitted in the
balance sheet, learned counsel argues that the entry in itself, without considering the circumstances surrounding such entry, cannot be the basis of
establishing liability. Finally, it was argued that the Single Judge failed to consider whether the plaint was barred by limitation, and thus, liable to be
rejected under Order VII Rule 11 CPC, which a Court must do even in summary proceedings.
While it is correct that Order XXXVII CPC is applicable only to the limited circumstances mentioned in Rule 2, and that the Court cannot
extend the scope of application of the summary procedure to other cases, the argument that the present case does not fall within Rule 2, sub-rule
(b)(1) (""suits ... arising on a written contract"") is incorrect. It is clear that a suit based on an agreement through exchange of letters is amenable to
being decided under Order XXXVII; Corporate Voice, (supra), states that:
The letters exchanged between the parties and their Counsel, which are on record have not been disputed. It is also not disputed that plaintiff
sent and defendant received the estimates, invoices and the bills. It is also not disputed that letters, purported to have been written by the plaintiff
were duly received by the defendant and some of them were duly replied including notice got sent by the plaintiff.
Indeed, that was also the plea taken by JSPL: that the exchange of letters in this case establishes an agreement for the amount claimed. Not
only have these letters not been contested by the appellant, but, instead of probing this route further in order to establish the debt (no doubt based,
ultimately, on the exchange of letters), the learned Single Judge relied on the admission in the balance sheets presented by the defendant before the
Court. On that question, of admissions of debt through balance sheet, while the circumstance surrounding the entry may be relevant for other
purposes, the fact that the amount claimed in the present suit is admitted as a debt due, as a loan, from JSPL, is sufficient in order for the Court to
reach a finding that the liability is established.
This Court in Espn Software India (P) Ltd. Vs. Modi Entertainment Network Ltd., , noted that:
Admission in balance-sheet is per-se an admission of liability....
XXXXXX XXXXXX XXXXXX
This entry clearly states that an amount of Rs. 8,00,04,000/- is due and payable by the respondent in accordance with the terms of the
contract. This document has been signed by the directors of the company and its Company Secretary on 31.10.2002.
Similarly, in Bhajan Singh Samra Vs. M/s. Wimpy International Ltd., , the Court noted:
Having heard the parties, this Court is of the opinion that the petitioning-creditor has to satisfy the Court that the debt on which the petition is
based was due and payable on the date of the petition. Certainly a time barred debt cannot be the basis of a winding up petition. However,
admission of a debt either in a balance sheet or in the form of a letter duly signed by the respondent, would amount to an acknowledgement...
Similar findings have also been recorded by the Calcutta High Court in Bengal Silk Mills Co. Vs. Ismail Golam Hossain Ariff, , and Rajah of
Vizianagaram Vs. The Official Liquidator, Vizianagaram Mining Company Limited, Vizagapatam, . Indeed, the entry admits such liability towards
JSPL for the amount claimed, and no explanation that may be provided, or circumstance surrounding the entry, can alter the fact of that liability.
Thus, while this admission establishes liability, the fact is traced to the exchange of letters mentioned above, thus bringing the case within Order
XXXVII CPC.
The above discussion clearly shows that the facts of the case and the approach of the Learned Single Judge is in accord with the decision of
the Supreme Court in Mechelec Engineers and Manufacturers Vs. Basic Equipment Corporation, , that no leave to defend must be granted if
XXXXXX XXXXXX XXXXXX
(a) ....the Defendant has no defence or the defence set up is illusory or sham or practically moonshine then ordinarily the Plaintiff is entitled to leave
to sign judgment and the Defendant is not entitled to leave to defend.
Here, after the liability has been admitted, and the basis of the liability (the letters exchanged between the parties) also remains unquestioned,
the exercise of proceeding to trial would be reduced to a mere formality. Therefore, the learned Single Judge, in our opinion, justifiably held that
the defendant''s lack of explanation on the one hand, and the averments made were so weak and untenable, as to disentitle the grant of leave.
Finally, on the question of interest, the learned Single Judge noted that JSPL could not provide any details of an agreement between the parties
for interest at the rates that have been claimed. Nor was any independent justification provided for the same. Accordingly, the learned Single Judge
granted the rate of interest at 8% per annum from 01.04.2008, being the year in which JSPL instituted the arbitration application against the
defendant, which he opposed. On this issue, learned counsel for the appellant/defendant argued that since the Single Judge admitted that no
agreement was reached on the question of interest, the same cannot be the subject of summary proceedings. Here, learned counsel argues that the
reliance on Khera Handloom Supply Vs. O.B. Exports and Others, and Rama Vision Ltd. Vs. Babbar Vision India Pvt. Ltd., , is misplaced, since
those cases pertain to dishonoured cheques, which are distinct from the present facts and circumstances.
This Court is of opinion that neither Khera (supra) nor Rama Vision (supra) is limited only to cheques or negotiable instruments. In Khera
(supra), the Court, in fact, noted as follows:
4...Can by any stretch of imagination it be said that in the absence of any agreement to pay interest, the plaintiff is debarred from claiming interest in
a suit under Order 37 of the Code. I am of the view that there is nothing to indicate in the language of Order 37 of the Code which may disentitle
the plaintiff to claim interest from the defendant (sic). On the other hand it seems rather clear from a bare perusal of Order 37 Rule 1 Sub-rule (2)
of the code that summary suits under this order can be filed based on Bills of Exchange. Hundies and Promissory notes where there is even no
promise to pay interest at a certain specified rate. Therefore, simply because there was no agreement between the parties to pay interest at the
specific rate of 18% per annum will not debar the plaintiff from filing a suit under Order 37 of the Code...
That case, therefore, does not create any distinction between Order XXXVII CPC suits based on cheques or based on written contracts, neither
does the text of Order XXXVII CPC give any credence to such a distinction, given that both a written contract or a cheque, are only the source of
the liability, which, in both cases, is liquidated and established as between the parties.
For the reasons indicated above, this Court finds that the appeal is liable to be dismissed, as there is no infirmity with the Order of the learned
Single Judge and the leave to defend was correctly denied. The judgment and decree of the learned Single Judge is consequently not liable to be
interfered with. The appeal is dismissed without any order as to costs. The Court fees shall be paid within two weeks. C.M. No. 15156/2013 is
accordingly disposed off in the above terms.
