AI Structured Summary
Not yet generated for this judgment
Judgment
The case of the petitioner, inter alia, is that on April 6, 1988,
he was appointed as an Assistant Engineer in the Kolkata
Municipal Development Authority (KMDA, for short). On December
13, 2005, he was promoted to the post of Executive Engineer and
was associated with the construction of 30 million gallon per day
at Kalyani Water Treatment Plant. He was also discharging other duties attached to his office. With effect from July 27, 2009, he
was again promoted to the post of Superintending Engineer and
subsequently, with effect from December 31, 2012, he was
promoted to the post of Additional Chief Engineer. From May 1,
2014, he has been acting as Chief Engineer-in-charge, Water
Supply Sector. From August 27, 2014, he has also been
functioning as the Chief Engineer-in-charge, Material Sector.
On June 3, 2015, the Chief Executive Officer, KMDA i.e., the
respondent no. 2 issued a charge-sheet against the petitioner alleging that while serving as the Superintending Engineer from
July 27, 2009 to December 30, 2012, he invited an online tender
for certain purposes near Sodepur Railway Station under Panihati
Municipality at an arbitrarily high rate of an estimated amount of
Rs. 2,81,76,400/- and issued the work order to M/s. Protomac
Construction treating the organization as the lowest bidder with
tender amount of Rs. 2,79,70,421/-. That was detected by the
Chief Engineer, Water Supply and a revised notice inviting tender
with an estimated amount of Rs. 1.75 crores was invited in
cancellation of the earlier one.
The petitioner in his reply denied the charges against him. He
requested the respondent authority to supply copies of all the
documents as mentioned in Annexure - A-II to the said charge-
sheet as well as some other documents and records. It has been
the allegation of the petitioner that the charges levelled against him
are not on the face of them maintainable as he has no power or
authority to sanction or accept any tender of a value exceeding
rupees two crores. The said tender was accepted and approved by
the Works and Tender Committee which consisted of four senior
IAS Officers, all the DGOs and all the Chief Engineers of KMDA
and KMW. The petitioner states that four IAS officers were i)
Finance Secretary to the Government of West Bengal, ii) the
Principal Secretary, Urban Development Department, Government
of West Bengal, iii) the Principal Secretary, Municipal Affairs
Department, and iv) Chief Executive Officer, KMDA. His notes,
suggestions etc., were never placed by the petitioner before the
members of the said Committee. He has no authority in accepting
or rejecting any tender exceeding rupees two crores in value. As
the IAS officers are not technical persons members of the
engineering cadre had been made permanent invitees and the decision was taken by the Board for deliberation. The petitioner
was not a member of the said committee.
An enquiry proceeding was initiated and the petitioner
appeared before the inquiring authority on August 17, 2015 and
pleaded not guilty to the charges framed against him. The
inquiring authority had directed the petitioner to submit the
written submission after obtaining the copy of the documents
detailed in Annexure III to the charge-sheet from the disciplinary
authority. The inquiring authority requested the disciplinary
authority to supply to him the documents, the petitioner also
requested the inquiry authority to be represented by an advocate.
On the next date of hearing i.e., on December 28, 2015, the
inquiring authority informed the petitioner that the Disciplinary
authority had intimated him that the petitioner was not entitled to
be represented by a lawyer. The petitioner found that several
documents mentioned in Annexure III to the charge-sheet were yet
to be received by him on the said date. The inquiring authority
recorded that the presenting officer expressed his inability to
supply to the copies of those documents to the petitioner and the disciplinary authority had not forwarded the copies of the said
documents to the Inquiring authority.
It is a grievance of the petitioner that the disciplinary
authority never informed him that his prayer for engagement of an
advocate had been rejected and he learnt it from the inquiring
authority at the second sitting of the enquiry that the disciplinary
authority had rejected his prayer.
The petitioner also states that the presenting officer Sri
Abhijit Saha was an Inspector of Police, State Vigilance
Commission and he is a trained police personnel and also trained
in the art of prosecution. On the contrary, the petitioner is an
engineer by profession and was not conversant with legal matters.
The petitioner suspects that the disciplinary proceeding against
him was initiated at the instance of some designing persons to
deprive him of his right of lawful promotion to the post of Chief
Engineer on the ground that a disciplinary proceeding was pending
against him. He also has alleged that the respondent authorities
are not willing to conclude the proceeding within a reasonable time
and wish to prolong and drag it so that the petitioner might be
denied his legitimate promotion.
The inquiring authority in the order dated January 28, 2016,
had recorded that the enquiry would not proceed further if the
documents wanted by the petitioner were not supplied to him. On
two successive dates of hearing, thereafter, the petitioner was
intimated by the inquiring authority that documents were not
supplied to him. Consequently, on February 29, 2016, the
inquiring authority observed that no further date would be fixed
and the petitioner would intimate the inquiring authority as soon
as he would receive the documents and thereafter the next date of
hearing would be fixed.
The petitioner earlier filed a writ petition, inter alia, praying
for a direction upon the respondent to rescind or revoke the
disciplinary proceedings drawn against him and to drop the
departmental proceeding. A learned single Judge of this Court by
an order dated April 28, 2016, disposed of the writ petition
observing that disciplinary proceedings should not be permitted to
continue endlessly. A period of more than 10 months had elapsed
from the receipt of the charge-sheet without any progress having
been made against the disciplinary action. The respondents were
directed to ensure that the documents relevant for the enquiry
were furnished to the petitioner within three weeks from the date whereupon the inquiry officer would conclude the enquiry within
six weeks therefrom without any adjournment to the parties,
except on unavoidable grounds. The disciplinary action should be
concluded within three months from the date of the order.
After this, the petitioner alleges the inquiring authority
concluded the enquiry in a haste without observing the rules of
natural justice. In spite of direction by this Court for concluding
the disciplinary action within three months from the date of order
of the High Court the disciplinary authority did not pass any final
order in the proceeding. A learned Advocate for the petitioner
requested the respondent no. 2 to pass a final order to the effect
that the disciplinary proceeding initiated against the petitioner had
been dropped or abandoned. By another letter dated August 16,
2016, the learned advocate for the petitioner again requested the
respondent to treat the purported disciplinary proceeding as
dropped.
On September 6, 2016, the respondent no. 2 who is the
disciplinary authority in the present case issued a show-cause
notice to the petitioner from which it is evident that the
disciplinary authority had agreed with the findings of the inquiring authority and proposes to impose a major penalty of reducing the
pay of the petitioner by three stages lower in the current pay band
for a period of three years under Regulation 76 (IV) of the KMDA
Service Regulations, 1975. During the period of penalty, he will not
earn any increment of pay. On the expiry of such period, the
reduction will have the effect of postponing future promotion of his
pay. The petitioner was asked to give his reply within 15 days from
the date of receipt of the show-cause notice.
The petitioner submitted his reply on September 19, 2016,
contending that the entire disciplinary proceeding was initiated
without jurisdiction. That the findings of the inquiring authority
were perverse and not based on any evidence. The petitioner was
not given any reasonable opportunity of defence. He alleged that in
his reply to the show-cause notice he also contended that after the
expiry of the period of three months, as directed by this Court, the
respondents had no authority or jurisdiction to proceed with the
disciplinary action. They have not considered the promotion of the
petitioner to the post of Chief Engineer which has been lying
vacant. Previously two juniors were promoted from the rank of
Additional Chief Engineer and they have also retired. But he
continues to be ignored on the plea of pendency of the disciplinary proceeding. As a matter of fact, apprehending that the petitioner
might not be considered for the promotion, his learned Advocate
had addressed letters to the respondent no. 2 in November and
December, 2015, requesting him to ensure that the case of
promotion of the petitioner to the post of Chief Engineer might be
considered in accordance with law. The petitioner is the senior
most Additional Chief Engineer and has been discharging the duty
of Chief Engineer-in-charge with effect from May 1, 2014.
The petitioner alleges that the respondents got sufficient time
to conclude the disciplinary proceeding but they have not done so
and have not passed any final order. But the disciplinary authority
kept the proceeding pending and in the process the respondents
have been continuing with promoting junior engineers to next
higher posts. The petitioner considers the series of steps taken by
the respondents to be violative of the fundamental rights under the
Constitution.
Therefore, by this writ petition, the petitioner has prayed for
a writ in the nature of mandamus commanding the respondents to
promote the petitioner to the post of Chief Engineer and to treat
the disciplinary proceeding against the petitioner as dropped or abandoned and to act in accordance with law. He has also prayed
for a declaration that the petitioner is entitled to be promoted to
the post of Chief Engineer with effect from September 2015.
On behalf of the respondents, the Chief Executive Officer of
KMDA, i.e., the respondent no. 2 has filed an affidavit wherein it
has been said that on receipt of certain complaints against the
petitioner, the Anti-Corruption Bureau of the State Vigilance
Commission made necessary investigation into the matter and on
perusal of the report of investigation and related documents
including the statement of the concerned employee, the Vigilance
Commission was of the view that there are materials for proceeding
against him, departmentally under the West Bengal Service
(Classification Control and Appeal) Rules, 1971. After preparing
the draft charges they sent the same to the respondent no. 2 by a
Memo dated May 13, 2015.
It has been alleged against the petitioner that while acting as
the Superintending Engineer, East Circle, he had invited an online
tender for designing supply and water supply carrier pipes near
Sodepur railway station at an arbitrarily high rate and had issued
work order in favour of M/s. Protomac Construction in a very lackadaisical manner which reflected lack of devotion to duties and
displayed gross misconduct.
Upon compliance of the required formalities, the disciplinary
proceeding was initiated against the petitioner and an enquiry was
started under Regulation 82 of the KMDA Service Regulation,
1975. The disciplinary authority appointed Sri Pranab Kumar Paul,
Deputy Commissioner of Departmental Enquiry, State Vigilance
Commission, Government of West Bengal as an inquiring
authority.
In terms of the direction given by this Court in the earlier
writ petition the disciplinary proceeding was required to be
concluded by July 27, 2016. The inquiring authority being the
Deputy Commissioner for departmental enquiries upon conclusion
of the enquiry submitted his report and findings to the State
Vigilance Commission which was forwarded by the Joint Secretary
of the State Commission to the disciplinary authority by a Memo,
dated July 14, 2016.
The respondent no.2 further states that the report submitted
by the inquiring authority was quite voluminous which had taken a few weeks for the disciplinary authority to go through the same
and to consider the findings on merit. The disciplinary authority
was satisfied that the inquiring authority had come to the
conclusion in his findings upon his judicious analysis and
documents. He having agreed with the findings with the inquiring
authority and held the delinquent officer to be guilty of the charges
and deserved a harsh punishment considering the serious nature
of charges.
Therefore, a second show-cause notice to the petitioner was
issued proposing to impose a major punishment of reduction of
pay by three stages lower in the current pay band for a period of
three years. The petitioner was given an opportunity to defend
himself by showing cause within 15 days of receipt of the said
notice as to why the punishment proposed would not be imposed
on him for the charges established against him in the enquiry. The
reply of the petitioner which was received on September 19, 2016,
not only contained voluminous documents but also involved
certain technical specifications and financial implications. For
dealing with the said reply in a better manner, the disciplinary
authority sent the same to the inquiring authority by a Memo,
dated November 3, 2016. The same was sent to the Joint Secretary, State Vigilance Commission for taking necessary action
from their end. Since no response to the memo was received from
the Joint Secretary till January 30, 2017, a reminder was issued
for doing the needful at the earliest as the timeframe fixed by the
Court had already expired.
The Joint Secretary, State Vigilance Commission by his
Memo dated February 10, 2017, informed the KMDA authorities
that all those documents had already been returned to the KMDA
and that the disciplinary authority was solely authorized and
competent to determine the penalty to be imposed upon the
charged officer and, therefore, requested him to take necessary
action on the strength of that. After receiving this communication
from the State Vigilance Commission, the respondent authorities
took some time to examine the explanation of the petitioner as also
the documents annexed to his reply. Upon consideration thereof,
the disciplinary authority agreed with the findings of the inquiring
authority and found him guilty of the charges of misconduct
having been duly established against him. The disciplinary
authority dared not to pass the final order due to the pendency of
the present petition where the petitioner questioned the
continuance of the proceeding itself. However, after it has been clarified by this Court in its order, dated April 6, 2017, that
pendency of the writ petition shall not debar the respondents to
pass by any order or final order in considering the case of the
petitioner without prejudice to the rights and contentions of the
parties, the disciplinary authority passed the final order on April
11, 2017, imposing the punishment as proposed by him in the
show-cause notice.
The respondent no.2 mentions these explanations in
justification for not being able to complete the disciplinary
proceeding within the time fixed by this Court. The delay in
completing the disciplinary proceeding is neither intentional nor
deliberate. The respondent no.2 tendered unqualified apology
before the Court.
I have heard Mr. Maitra, the learned Senior Counsel for the
petitioner and Mr. Bose, the learned advocate for the respondents
and have given my anxious consideration to the respective cases.
Although the writ petition contains a host of allegations on
merit against the disciplinary proceeding initiated against the
petitioner and the conduct of it, relief sought by the petitioner is not directed against the report of the enquiry or the order of the
disciplinary authority on merit. The petitioner''s prayer in respect of
the disciplinary proceeding is confined to treating the same as
dropped or closed or abandoned.
It is not understood why the Chief Executive Officer has filed
an affidavit merely explaining the delay in concluding the
departmental proceeding. On April 6, 2017, this Court directed the
respondent no.2 to file a report in the form of an affidavit in
response to the allegation made in the writ petition. It was further
directed that the report most specifically disclose the reasons for
not being able to complete the proceeding within the timeframe as
fixed by this Court. It did not mean that the affidavit should be
confined only to disclosure of reasons for the delay. The
respondents are, however, certainly entitled not to respond to the
material allegations in a petition in spite of being given an
opportunity to controvert the same. But in that case the material
allegations in the writ petition go unchallenged.
If one wants to examine the merits of the allegations in the
writ petition, there are plenty of them. If one is required to deal
with the grievance of the petitioner that documents were not supplied to him in time, or he was not allowed by the respondents
to have the assistance of an Advocate, etc. the points certainly lean
very heavily in favour of the petitioner.
Even if the KMDA Service Regulations do not permit the
representation of a delinquent officer by a lawyer unless there is
any specific bar to the contrary the authorities might have allowed
to him to be so represented as the presenting officer, the petitioner
was right in taking the point, was a senior police officer who was
more acquainted with the intricacies of both the prosecution as
well as the defence. It matters little that he was not a lawyer, for he
had the requisite training and expertise in this particular field,
both in the conduct of an enquiry as well as in the art of
examination and cross-examination of witnesses.
That there was an obvious dilly-dallying in providing the
copies of the necessary documents to the petitioner cannot be
doubted and it will be evident from the minutes of the proceeding
themselves. Ultimately this Court had directed the respondents to
furnish the relevant documents to the petitioner within three
weeks. By that time examination of the prosecution witnesses had
been closed. Such a belated supply of records must have rendered the petitioner significantly handicapped in both preparing his
statement of defence as well as the cross-examining the
prosecution witnesses.
But since the petitioner has not prayed for setting aside the
enquiry report or the order passed by the disciplinary authority on
merit, I refrain from making any further observation on the merits
of the case. The specific prayer is for a direction upon the
respondents to treat the disciplinary proceeding as abandoned or
withdrawn. Here the petitioner has primarily based his case on the
non-compliance of the order passed by this Court about the time
schedule fixed by it.
I have very closely considered the explanation given by the
respondent no. 2 in his affidavit. It does not really inspire much
confidence nor it does the explanation appear to be very either
convincing or acceptable. The reasons for the delay, as mentioned
in the affidavit, leave much to be desired as the conduct of the
respondents. On April 28, 2016, this Court had directed the
inquiry officer to conclude the enquiry within six weeks from the
date of furnishing the relevant documents to the petitioner which
was to be done within a period of three weeks from the date of the order. The petitioner has alleged that the Inquiry Officer was a
party to that writ petition and he was also served with a copy of the
order.
It appears that the respondents were crucially aware of the
outer limit fixed by this Court for conclusion of the entire
disciplinary proceeding. There was undoubtedly some delay on the
part of the inquiry officer in submitting his report but the Vigilance
Commission by a Memo dated July 14, 2016, had forwarded it to
the disciplinary authority. The stand taken in the affidavit of the
respondent no. 2 that the disciplinary authority had less than two
weeks to complete the disciplinary action may factually correct,
but the disciplinary authority cannot take advantage of it as
justifying its further delay. In the scheme of the timeframe fixed by
this Court, the time given to the disciplinary authority to conclude
the entire proceeding was four weeks. If there had been a delay of
two weeks in receiving the copy of the enquiry report and if the
disciplinary authority could conclude the disciplinary action within
a further period of two weeks beyond the timeframe fixed by this
Court, the petitioner perhaps would not have had much to impugn
the action of the respondent no. 2.
The statement made in Paragraph 10 of the affidavit and the
subsequent steps taken by him most certainly are not expected of
the disciplinary authority when the time fixed by this Court was
running out. They should have taken all the steps as expeditiously
as possible and not in a lackadaisical manner. The plea taken by
the respondent no. 2 that the report of the inquiry officer was
voluminous is not very easily an acceptable defence. The enquiry
report as annexed to the writ petition runs into 24 pages, each
page containing about 25 lines. The first few pages of the enquiry
report i.e., about 9 pages deal with the usual preliminaries, the
charge against the petitioner and the defence case, etc. These are
imperatives in any enquiry report. Though the disciplinary
authority has most certainly to go through the whole report, the
consideration of these preliminaries is not really a very time
consuming matter. The respondent no. 2 has also stated that he
had to consider the findings of the inquiry officer on merit. Such
findings have occupied not more than 16/17 pages of the report. It
is not understood why the disciplinary authority had taken a few
weeks to go through the findings and to consider the same on
merit. The explanation on this point is inadequate.
After the disciplinary authority agreed with the findings of
the Inquiry Officer, he issued a second show-cause notice to the
petitioner on September 6, 2016. In other words, the respondent
no. 2 had taken about seven weeks to go through and consider the
findings of the inquiry officer which runs into not more than 17/18
pages. The respondent no. 2 had given 15 days'' time to the
petitioner to show cause against the proposed punishment.
The petitioner kept himself to the time fixed by the
respondent no. 2. I would say he had given his reply even before
the expiry of 15 days.
The respondent no. 2 has again taken the plea that the reply
by the petitioner was voluminous. It is true that the reply was a
lengthy one, but it was quite natural under the circumstances,
particularly, in a case of a disciplinary proceeding being faced by a
very senior engineer of an organization where the delinquent officer
has to give reply to the enquiry report and in the process he had to
refer to different points and different items as emerging from
evidence adduced at the enquiry, both oral and documentary.
The next step taken by the respondent no. 2 was very
unusual and not expected of him as the disciplinary authority. He
thought as per his own statement in the affidavit that for dealing
with the said reply it would be sent to the inquiring authority again
and by a memo dated November 3, 2016, he did exactly the same.
Thereafter, for about three months the disciplinary authority did
not take any action of follow it up. It was only on January 31, 2017
that the KMDA authority decided to issue a reminder to the
Inquiring authority. In reply to the reminder, the inquiring
authority informed the KMDA authorities that the disciplinary
authority was solely authorized and competent to determine the
penalty to be imposed upon the petitioner and requested him to
take a decision.
If the disciplinary authority could take a decision on the
inquiry report and if he could agree with the findings, it is not
understood why the reply by the petitioner should require an
external help. The reply as annexed to the writ petition does not
really disclose that the petitioner had referred to any technical
engineering aspect of the matter which a non-technical man like
an administrative head was not competent to deal. It most
certainly refers to various aspects and items of the tender and reference was made to prices of different materials, evidence
adduced etc. If the disciplinary authority had felt any difficulty
because of the alleged technicalities involved in it there was no
point in sending it to the inquiring authority either. After all he too
does not appear to be a technical person; at least there is no
evidence to that effect.
That apart, why must the disciplinary authority send the
reply of a delinquent officer to the inquiring authority for dealing
with the same? The job of an inquiring authority ends with the
submission of the enquiry report and irrespective of whether the
reply of the delinquent officer contains any matter touching on any
technical aspect, it has to be dealt with by the disciplinary
authority and him alone. It is all the more so when the inquiring
authority had found the petitioner guilty of the charges. Why was
the reply then sent to the inquiring authority? Underlying in the
exercise was there not an effort to obtain a response from the
inquiring authority so that the reply of the petitioner may be
effectively countered and rejected. I have no hesitation in holding
that in this respect the disciplinary authority had abdicated his
authority in favour of the inquiry officer which he must not have
been done, either under the Regulations of the KMDA or under the service jurisprudence in general. Even if he had sent it to the
inquiring authority why did he wait for about 12 weeks to send a
reminder, when he was far out of the timeframe fixed by this
Court? I definitely discover a certain degree of laid back attitude in
the conduct of the proceeding, particularly in the manner the
respondent no. 2 had acted.
The act of the disciplinary authority was also not supportable
for a very different reason. The reply given by the petitioner was
against the report of the inquiring authority. The validity of that
report was to be decided by the disciplinary authority alone. The
respondent no. 2 had sent it to the inquiring authority against
whose finding the petitioner had made observations. If under these
circumstances the inquiring authority is requested to deal with the
reply of the petitioner, he is to decide the validity of the reply which
is against his own report. By this, the respondent no. 2 had sought
to make the inquiring authority as the judge in his own cause.
Otherwise, there was no justifiable explanation why the response
to a report should be dealt with by the maker of the report himself,
particularly when the inquiring authority was not expected to find
any fault with his own report.
Even if one accepts the explanation of the disciplinary
authority that because of the pendency of the writ petition the final
order was not passed, the inordinate delay at every step prior to
that clearly evinces that the timeframe fixed by the Court in the
earlier writ petition was not seriously attempted to be complied
with. If the reasons mentioned in the affidavit were really posing
problem to the disciplinary authority to conclude the proceeding
within the timeframe fixed by the Court, there was nothing
preventing him from approaching the Court at an appropriate
stage for extension of time to conclude the proceeding. That would
have been in fitness of things, a more appropriate response of the
respondents for establishing their bona fides. The respondents
have not taken any steps towards that which goes a long way to
raise a suspicion that they did not take the Court''s order very
seriously.
On the other hand, the petitioner has done everything within
his power. He even gave his reply within the scheduled date and
time. There was no lapse on his part. It cannot also be said that by
responding to the disciplinary authority''s letter, dated September
6, 2016, he had waived his right to raise the issue of delay
subsequently. He in his reply specifically reminded the respondent no. 2 about the timeframe fixed by the Court and the effect of not
complying with the same including the lack of jurisdiction on the
part of the respondent no. 2 to take further steps in the
disciplinary proceeding. After expressing his very firm views in the
matter, he had given his reply without prejudice to his rights and
contentions both in respect of the validity of the disciplinary
proceeding as well as the effect of not complying with the
timeframe fixed by this Court. Therefore, it is within the right of
the petitioner to agitate the issue of non-compliance of the court''s
order which he has done in the present case.
If one reads carefully the order passed by the Court on April
28, 2016 in the earlier writ petition as a whole, one would find it
hard to say that the direction of the Court that the disciplinary
action "should be concluded within three months from the date"
was merely directory or expressed the desire of the Court by which
time the disciplinary proceeding should be completed. Most
certainly it was more than that. The tone of the judgment has been
set out right from the paragraph 2 of the same where the learned
Judge emphasized the importance of concluding the disciplinary
proceeding within a stipulated period and the impermissibility of
continuing with it endlessly. In the said order, the expression ''should be'' has been used twice, viz., when the learned single
Judge had held in respect of the disciplinary proceeding in general
that they should be concluded within three to six months and
when it was said that the disciplinary action in the present case
should be concluded within three months from the date. In both
the cases the Court had used the expression in the sense of an
unalterable imperative. It cannot be said that Court was
expressing something which should be desirable under normal
circumstances. On the contrary, it was expressing its anxiety that
for a period of more than 10 months the disciplinary proceeding
did not make any progress. Judged in that background the
expression ''should be'' has an unmistakable sense of "must" in it.
The Court did not express any desire about the conclusion of the
disciplinary proceeding. Because of its failure to make any
progress for a very substantial period the Court decided to fix the
outer limit by which the disciplinary proceeding was to be
concluded. The direction was mandatory and not directory in
nature.
In the context of what the learned single Judge had earlier
directed, had there been a slight or negligible delay in concluding
the disciplinary proceeding the Court could have ignored it and might not have taken an exception to the delay occurred in
concluding the disciplinary proceeding. As per the timeframe, the
disciplinary authority was entitled to get two more weeks after the
submission of the enquiry report. But what he had done
afterwards was unsupportable on both the counts. It was bad from
the point of view of merit as well as in not sticking to the timeframe
fixed by him.
Any reasonable man thus will be left with no option than to
conclude that the disciplinary authority violated the Court''s order
in not being within the timeframe fixed by the Court, and too by a
gross delay. I quite agree with the stand taken by the petitioner
that after such an unreasonable delay the disciplinary authority
lacked the authority to pass the final order. Its conduct leads to
but one conclusion that the proceeding against the petitioner must
be treated to be closed or abandoned. I declare that any steps
taken by the respondent authorities beyond the timeframe fixed by
the Court was not in terms of the Court''s order beyond the
jurisdiction of the disciplinary authority and, therefore, is bad in
law. I further direct the disciplinary authority as well as the
respondent no. 1 not to give any effect or further effect to the order or orders passed by them subsequent to the expiry of the period
fixed by the Court.
It is further declared that in the absence of any other
disqualification and if the petitioner has fulfilled the eligibility
criteria in all respects, he shall be entitled to be considered for
promotion to the post of the Chief Engineer. If the said post is lying
vacant, the respondents shall consider the case of the petitioner
along with others within a reasonable timeframe. I make it clear
that in view of the petitioner''s persistent grievance that he has
been superseded repeatedly on the plea of pendency of a
disciplinary proceeding against him, this direction for
consideration of the case of the petitioner within a proximate
future is to be treated as mandatory. It is clarified that the
direction to consider the case of the petitioner for promotion has
nothing to do with the ultimate decision of the respondent no. 1 in
this regard. They shall be free to take the appropriate decision
strictly in accordance with law and the procedure laid down
therefor. But the fact that the petitioner was once proceeded
against and he was found guilty in the present enquiry proceeding
shall not be a relevant factor in considering his case for future
promotion.
The writ petition is thus allowed.
There shall be no order as to costs.
Urgent Photostat certified copy of this order, if applied for, be
supplied to the parties on priority basis upon compliance of all
requisite formalities.
