The petitioner had applied for transfer of 4.67 acres of land from outlet No.112910/L to outlet No.117335/L on the Kot Bhai distributary. The
application was allowed by the Divisional Canal Officer, Bathinda Canal Division, Bathinda, vide order dated 29.07.2009 (Annexure P-1). The said
order was challenged by respondent No.4 in appeal and the Superintendent Canal Officer, Sirhind Canal Circle, Ludhiana, vide order dated 02.11.2010
(Annexure P-2) allowed the same and remanded the case to the Divisional Canal Officer for a fresh decision. Thereafter, the Divisional Canal
Officer, re-decided the case vide order dated 04.06.2014 (Annexure P-5) and allowed the transfer based upon the report dated 05.04.2011 (Annexure
P-3) of Ziledar and recommendation dated
12.09.2011 (Annexure P-4) of Sub Divisional Officer, Teona Canal Sub Division, Gidderbaha. He found that the existing water-course to the land of
the petitioner from outlet at RD No.112910/L is damaged, because of which the land of the petitioner is not receiving adequate irrigation. The order of
the Divisional Canal Officer, has, however, been upset by the Superintending Canal Officer, on an appeal filed by respondent No.4.
Learned counsel for the petitioner submits that from the map/plan (Annexure P-7), it is evident that the land sought to be transferred is situated at a
greater distance from the existing outlet RD No.112910/L and is very close to outlet No.117335/L. Thus, the transfer would facilitate irrigation of his
land. Moreover, from report dated 05.04.2011of the Ziledar, it is evident that the irrigation of the land already being irrigated through outlet
No.117335/L will not be adversely effected. The recommendation dated 12.09.2011 of the Sub Divisional Officer, is also to the same effect. Thus, the
order of the Superintending Canal Officer, is perverse as it is based upon an apprehension that the transfer of the land of the petitioner will result in
strained relations between the residents of two villages.
Learned State counsel submits that the order of the Superintending Canal Officer, is not very happily worded. In the written statement, it has been
specifically averred that transfer of additional land to outlet No.117335/L will impose a strain on it adversely affecting irrigation of the land presently
being irrigated through the said outlet. Moreover, maintenance of the water-course is the responsibility of the residents and in case, the water-course
has been damaged, the petitioner is to blame therefor. He can get the same repaired to increase the flow of water to his land. The transfer of the land
of the petitioner to outlet No.117335/L is not technically feasible as it would adversely affect irrigation of the land being irrigated through the said
outlet.
Having considered the rival submissions of the learned counsel for the parties, I am of the opinion that the Superintending Canal Officer, has failed to
apply his mind to the issue in dispute. According to the petitioner, the report of the Ziledar and the recommendations of the Sub Divisional Officer
established that land being irrigated through outlet No.117335/L will not be adversely effected, whereas, according to the written statement of the
State, it emerges that the irrigation of the said land would be adversely effected. The learned Superintending Canal Officer, has not properly
considered this aspect of the matter and the issue being technical in nature needs to be decided by a person having technical knowledge.
Thus, the writ petition is allowed and the impugned order dated 05.08.2015 (Annexure P-6) passed by the Superintending Canal Officer, is hereby set
aside. The matter is remanded to the Superintending Canal Officer for a fresh decision after hearing the parties and examining the core issue as
mentioned hereinabove. The proceedings be completed within a period of six months from the date of receipt of certified copy of this order.