AI Structured Summary
Not yet generated for this judgment
Judgment
T.S. Sivagnanam, J.—By consent the main Writ Petitions itself are for taken up for disposal. In W.P. No. 24442/2009, the challenge is to
an order passed by the third respondent dated 16.11.2009 calling for fresh tenders in respect of a road contract and for a consequential direction
to permit the petitioner to complete the remaining road improvement work. In W.P. No. 24443/2009, the challenge is to an order dated
28.10.2009 passed by the second respondent by which the road contract work, which was awarded to the petitioner was cancelled and the
petitioner''s name was included in the list of blacklisted contractors.
The petitioner is a registered Class - I contractor with the Rural Development Department and is stated to be performing contracts for various
Government Departments, since 1970 and there has been no allegation against the petitioner. The third respondent by notification dated
10.01.2008 called for tenders from eligible contractors for certain contract work, which were road development works at an estimated cost of Rs.
34.46 lakhs. The petitioner''s submitted his tender on 31.01.2008 by quoting Rs. 34,28,259/- and after negotiation, the quote was accepted and
the contract was awarded in favour of the petitioner by the second respondent, by order dated 12.02.2008. The agreement was executed
between the petitioner and the department on 14.03.2008, after the execution of the agreement, it came to the notice of the petitioner that the site
condition was not conducive and therefore a request was made to the third respondent to pay additional amount for carrying out the work, which
was not within a scope of the agreement inspection was also conducted by the authorities on 15.01.2009 and subsequently on 19.01.2009 and
they assessed the value of the works done by the petitioner at Rs. 7,70,619/-.
On 22.04.2009 a sum of Rs. 2,21,441/- was given as part payment after deducting the fine amount of Rs. 1,71,413/-, which according to the
respondent was deducted for slow progress of work. The second bill was partly approved on 08.08.2009 and this was due to a recommendation
by the Assistant Executive Engineer, one Mr. Senthil Kumar to withhold 50% of the total bill amount. At that stage, the petitioner received a show
cause notice dated 16.10.2009, which was based on the letters of the Assistant Executive Engineer Senthil Kumar, dated 14.09.2009 and
02.10.2009 recommending for cancellation of the contract awarded in favour of the petitioner. The petitioner not being aware about such
recommendation of the Assistant Executive Engineer completed the Culvert work on 25.10.2009 for a value of Rs. 1,12,240/-. It is further stated
that though inspection for the Culvert was over on 26.10.2009, the petitioner''s bill was not settled. In the show cause notice explanation was
sought for the slow progress in work and stating that it is proposed to remove the petitioner''s name from the list of registered contractors. The
petitioner by reply dated 22.10.2009, submitted his explanation for the delay, which has been stated in his earlier representations dated
05.01.2009 & 13.07.2009 followed by another reminder dated 23.05.2009. It was further stated that the petitioner was not able to complete one
Culvert work as per schedule as he had to construct let out drainage for 20 metres in Tea Estate belonging to a private person, who had not
permitted the petitioner''s workman to enter the property. But, however the petitioner subsequently completed the work and these facts were well
within the knowledge of the Assistant Executive Engineer and Block Engineer. However, by the impugned order dated 28.10.2009, the
petitioner''s contract was cancelled and the petitioner was also blacklisted. Subsequently, a re-tender was called for by the third respondent by
notification dated 16.11.2009 and this re-tender notification is impugned in W.P. No. 24442/2009, the cancellation of the contract and blacklisting
by order dated 28.10.2009 is impugned in W.P. No. 24443/2009.
The petitioner would contend that the impugned order of cancellation of tender and blacklisting the petitioner is arbitrary and illegal and violative
of Article 14 and Article 19(1)(g) of the Constitution. That the order has been passed without proper application of mind and without assigning the
real reason and the order has been passed without observing the principles of natural justice, since no site inspection was conducted before
concluding that there is delay in execution of work. Further even in the show cause notice, it was pre-decided to blacklist the petitioner and such
pre-decision vitiates the entire proceedings. The various letters given by the petitioner explain the reasons for slow progress was not considered.
Further the site condition was not revealed to the petitioner, which involved additional expenses for the petitioner to transport gravel from outside.
The petitioner''s past blemishness conduct in performing various works for the Department from 1970 onwards was not taken into consideration
before the blacklisting. That due to pressure of the authorities, the petitioner was compelled to perform certain works, which were out side the
scope of the agreement. The fine amount of Rs. 5000/- per day is exorbitant and against the principles of natural justice and violative of Rule 57.1
and Rule 57.2. The petitioner has not been paid the bill and has been waiting for more than 8 months to get amount, the petitioner alone has been
singled out, when one other contractor by name Mr. Gopal, who was awarded the road improvement work from Kukkalthurai - Anna Nagar
K.M 0/0 - but did not complete the work on time, but allowed to carry out the work. On these grounds, the petitioner would contend that the
order of cancellation of the contract awarded, and blacklisting is illegal and the re-tender at the risk and cost of the petitioner is also arbitrary.
A counter affidavit has been filed by the third respondent stating that there were some remarks against the petitioner in respect of a scheme,
which was implemented during 2007-08. It is submitted that the impugned order of cancellation was issued after carefully monitoring the progress
of road work and after observing the procedures as required. It is further stated that the contractors is expected to inspect the road, availability of
stone jelly, gravel etc., and then quote his rates for tenders. It is further submitted that under the scheme, if the work is not completed the
Government will have to incur loss by way of additional interest amount and as per the agreement, the petitioner had to complete the work on or
before 14.06.2008 as per the program of work under Clause 23 of the agreement. The rate of progress for the first month 30%, second month
70% & third month 100% should be completed and that the petitioner did not commence the work, even after the expiry of the agreement period
of three months and the work was started only after the agreement period, after lapse of seven months from handing over the site and in terms of
Clause 54 of the tender notice time is the essence of the contract. It is further submitted that after following the proper procedure the contract was
determined and the petitioner was also blacklisted for the poor performance in the subject contract as well as considering the bad remark in an
earlier work. It is submitted that the writ petition is not maintainable, since it is a non-statutory contract and if at all the petitioner is aggrieved, he
can work out his remedies by invoking the arbitration clause in the agreement. It is further submitted that the proposed road is an important link
road and because of the interim order the re-tender cannot be called for and the public or put to great difficulty, since they have to take an
circuitous route. Therefore, it has been stated that the writ petition is devoid of merits.
Having considered the submissions on either side before examining the controversy in the present case, it is necessary to first consider whether
the petitioner would be entitled to invoke the extraordinary jurisdiction of this Court under Article 226 of the Constitution of India in the given facts
and circumstances. Admittedly the present contract between the petitioner and the third respondent is a non statutory contract and the only
difference being that one of the contracting parties is a limb of the Government of Tamil Nadu. In terms of Clause 55 & 56 of the agreement dated
14.03.2008 executed between the petitioner and the department contemplates settlement of disputes and resolution of disputes and the same reads
as under:
SETTLEMENT OF DISPUTES:
If any dispute or difference of any kind whatsoever shall arise between the engineer of employer and the contractor in connection with, or arising
out of the contract, of the execution of the works whether during the progress of the works or after their completion and whether before of after
the termination, abandonment or breach of the contract, it shall in the first place, be referred to and settled by the Engineer who shall within a
period of thirty days after being requested by the contractor to do so, give written notice of his decision to the contractor. Upon receipt of the
written notice of decision of the Engineer the contractor shall promptly proceed without delay to comply with such notice of decision.
If the Engineer fails to give notice of his decision in writing within a period of thirty days after being requested or if the contractor is dissatisfied with
the notice of decision of the Engineer, the contractor may within thirty days after receiving the notice of decision appeal to the employer who shall
afford an opportunity to the contractor to be heard and to offer evidence in support of his appeal. The employer shall give notice of his decision
within a period of thirty days after the contractor has given the said evidence in support of his appeal. Subject to arbitration, as hereinafter
provided, such decision of the Employer in respect of every matter so referred shall be final and binding upon the contractor and shall forthwith be
given effect to by the contractor who shall proceed with the execution of the works with all due diligence whether he requires arbitration, as
hereinafter provided or not if the Employer has given written notice of his decision to the contractor and no claim to arbitration has been
communicated by him by the contract within a period of thirty days from receipt of such notice the said decision shall remain final and binding upon
the contractor. If the Employer shall fail to give notice of his decision, as aforesaid, within a period or thirty days after being decision, requested as
aforesaid, or if the contractor be dissatisfied with any such decision then and in any such case the contractor within thirty days after the expiration
of the first named period of thirty days at the case may be required that the matter or matters in dispute be referred to arbitration as hereinafter
provided.
RESOLUTION OF DISPUTES:
Settlement of claims by Arbitration:
All disputes of differences in respect of which the decision is not final and conclusive if the claims monetary value is less than Rs. 2.00 lakhs
(Rupees Two Lakhs only) shall be referred for arbitration to a sole arbitrator. The District Collector, Trichy or the successor to his office. The
arbitration shall be conducted in accordance with the provisions of Indian Arbitration and Conciliations Act 1996 or any statutory modifications
thereof. The decision of the sole arbitrator shall be final and binding on the parties thereto. The arbitrator shall determine the amount of arbitration
to be awarded to either parties.
Performance under the contract shall continue during arbitration proceedings and payments due to the contractor by the owner shall not be
withheld. Unless they are the subject matter of the arbitration proceedings.
All awards shall be in writing and such a words shall state reasons for the amounts awarded.
Neither party is entitled to bring a claim to arbitration if the Arbitration has not been appointed before the expiration of thirty days after defect
liquidity period.
If the claims exceed monetary value of more than Rs. 2.00 lakhs (Rupees two lakhs only) the same shall be referred to the civil court having
jurisdiction for decisions.
Therefore in respect of all disputes and difference which may arise out of the contract, of the execution of the works even after their completion,
before or after termination is required to be settled/resolved in terms of the procedure agreed to by the parties under Clause 55 & 56 of the
agreement.
With this factual backgrounds, if the law on the subject regarding maintainability of writ petitions in contractual matters is examined. There are
several decisions of the Hon''ble Supreme Court dealing with this issue some of which are stated hereunder.
In National Highway Authority of India Vs. Ganga Enterprises and Another, , the Hon''ble Supreme Court held as follows:
The respondent then filed a writ petition in the High Court for refund of the amount. On the pleadings before it, the High Court raised two
questions viz.: (a) whether the forfeiture of security deposit is without authority of law and without any binding contract between the parties and
also contrary to Section 5 of the Contract Act; and (b) whether the writ petition is maintainable in a claim arising out of a breach of contract.
Question (b) should have been first answered as it would go to the root of the matter. The High Court instead considered Question (a) and then
chose not to answer Question (b). In our view, the answer to Question (b) is clear. It is settled law that disputes relating to contracts cannot be
agitated under Article 226 of the Constitution of India. It has been so held in the cases of Kerala State Electricity Board and Another Vs. Kurien
E. Kalathil and Others, , State of U.P. and others Vs. Bridge and Roof Co. (India) Ltd., and Bareilly Development Authority and Another Vs.
Ajay Pal Singh and Others, . This is settled law. The dispute in this case was regarding the terms of offer. They were thus contractual disputes in
respect of which a writ court was not the proper forum. Mr Dave, however, relied upon the cases of Verigamto Naveen Vs. Government of
Andhra Pradesh and Others, and Harminder Singh Arora Vs. Union of India (UOI) and Others, . These, however, are cases where the writ court
was enforcing a statutory right or duty. These cases do not lay down that a writ court can interfere in a matter of contract only. Thus on the ground
of mainta inability the petition should have been dismissed.
In Kerala State Electricity Board and Another Vs. Kurien E. Kalathil and Others, , the Hon''ble Supreme Court dealt with the question of
maintainability of petition under Article 226 of the Constitution and the desirability of exhaustion of remedies and availability of alternative remedies,
as also difference between statutory contracts and non-statutory contracts. In paras 10 and 11 of the judgment it was held as follows:
We find that there is a merit in the first contention of Mr Raval. Learned Counsel has rightly questioned the maintainability of the writ petition.
The interpretation and implementation of a clause in a contract cannot be the subject-matter of a writ petition. Whether the contract envisages
actual payment or not is a question of construction of contract. If a term of a contract is violated, ordinarily the remedy is not the writ petition under
Article 226. We are also unable to agree with the observations of the High Court that the contractor was seeking enforcement of a statutory
contract. A contract would not become statutory simply because it is for construction of a public utility and it has been awarded by a statutory
body. We are also unable to agree with the observation of the High Court that since the obligations imposed by the contract on the contracting
parties come within the purview of the Contract Act, that would not make the contract statutory. Clearly, the High Court fell into an error in
coming to the conclusion that the contract in question was statutory in nature.
A statute may expressly or impliedly confer power on a statutory body to enter into contracts in order to enable it to discharge its functions.
Dispute arising out of the terms of such contracts or alleged breaches have to be settled by the ordinary principles of law of contract. The fact that
one of the parties to the agreement is a statutory or public body will not by itself affect the principles to be applied. The disputes about the meaning
of a covenant in a contract or its enforceability have to be determined according to the usual principles of the Contract Act. Every act of a statutory
body need not necessarily involve an exercise of statutory power. Statutory bodies, like private parties, have power to contract or deal with
property. Such activities may not raise any issue of public law. In the present case, it has not been shown how the contract is statutory. The
contract between the parties is in the realm of private law. It is not a statutory contract. The disputes relating to interpretation of the terms and
conditions of such a contract could not have been agitated in a petition under Article 226 of the Constitution of India. That is a matter for
adjudication by a civil court or in arbitration if provided for in the contract. Whether any amount is due and if so, how much and refusal of the
appellant to pay it is justified or not, are not the matters which could have been agitated and decided in a writ petition. The contractor should have
relegated to other remedies.
Reference can also be made to State of Gujarat and Others Vs. Meghji Pethraj Shah Charitable Trust and Others, . In para 22 the Hon''ble
Supreme Court observed as follows:
We are unable to see any substance in the argument that the termination of arrangement without observing the principle of natural justice (audi
alteram partem) is void. The termination is not a quasi-judicial act by any stretch of imagination; hence it was not necessary to observe the
principles of natural justice. It is not also an executive or administrative act to attract the duty to act fairly. It was -- as has been repeatedly urged
by Shri Ramaswamy -- a matter governed by a contract/agreement between the parties. If the matter is governed by a contract, the writ petition is
not maintainable since it is a public law remedy and is not available in private law field, e.g., where the matter is governed by a non-statutory
contract. Be that as it may, in view of our opinion on the main question, it is not necessary to pursue this reasoning further.
In State of U.P. and others Vs. Bridge and Roof Co. (India) Ltd., , the Hon''ble Supreme Court dealt with the issue in paras 15 and 16 in the
following manner:
In our opinion, the very remedy adopted by the respondent is misconceived. It is not entitled to any relief in these proceedings, i.e., in the writ
petition filed by it. The High Court appears to be right in not pronouncing upon any of the several contentions raised in the writ petition by both the
parties and in merely reiterating the effect of the order of the Deputy Commissioner made under the proviso to Section 8D(1).
Firstly, the contract between the parties is a contract in the realm of private law. It is not a statutory contract. It is governed by the provisions
of the Contract Act or, maybe, also by certain provisions of the Sale of Goods Act. Any dispute relating to interpretation of the terms and
conditions of such a contract cannot be agitated, and could not have been agitated, in a writ petition. That is a matter either for arbitration as
provided by the contract or for the civil court, as the case may be. Whether any amount is due to the respondent from the appellant-Government
under the contract and, if so, how much and the further question whether retention or refusal to pay any amount by the Government is justified, or
not, are all matters which cannot be agitated in or adjudicated upon in a writ petition. The prayer in the writ petition, viz., to restrain the
Government from deducting a particular amount from the writ petitioner''s bill(s) was not a prayer which could be granted by the High Court under
Article 226. Indeed, the High Court has not granted the said prayer.
In India Thermal Power Ltd. Vs. State of M.P. and Others, , the Hon''ble Supreme Court observed as follows:
It was contended by Mr. Cooper, learned Senior Counsel appearing for appellant GBL and also by some counsel appearing for other
appellants that the appellant/IPPs had entered into PPAs under Sections 43 and 43A of the Electricity Supply Act and as such they are statutory
contracts and, therefore, MPEB had no power or authority to alter their terms and conditions. This contention has been upheld by the High Court.
In our opinion the said contention is not correct and the High Court was wrong in accepting the same. Section 43 empowers the Electricity Board
to enter into an arrangement for purchase of electricity on such terms as may be agreed. Section 43A(1) provides that a generating company may
enter into a contract for the sale of electricity generated by it with the Electricity Board. As regards the determination of tariff for the sale of
electricity by a generating company to the Board, Section 43 provides that the tariff shall be determined in accordance with the norms regarding
operation and plant-load factor as may be laid down by the authority and in accordance with the rates of depreciation and reasonable return and
such other factors as may be determined from time to time by the Central Government by a notification in the Official Gazette. These provisions
clearly indicate that the agreement can be on such terms as may be agreed by the parties except that the tariff is to be determined in accordance
with the provision contained in Section 43A(2) and notifications issued thereunder. Merely because a contract is entered into in exercise of an
enabling power conferred by a statute that by itself cannot render the contract a statutory contract. If entering into a contract containing the
prescribed terms and conditions is a must under the statute then that contract becomes a statutory contract. If a contract incorporates certain terms
and conditions in it which are statutory then the said contract to that extent is statutory. A contract may contain certain other terms and conditions
which may not be of a statutory character and which have been incorporated therein as a result of mutual agreement between the parties.
Therefore, the PPAs can be regarded as statutory only to the extent that they contain provisions regarding determination of tariff and other
statutory requirements of Section 43A(2). Opening and maintaining of an escrow account or an escrow agreement are not the statutory
requirements and, therefore, merely because PPAs contemplate maintaining escrow accounts that obligation cannot be regarded as statutory.
Therefore as per the law declared by the Hon''ble Supreme Court the present contract would not become statutory merely because it has been
awarded by the State. That apart a dispute resolution mechanism has been provided for under the contract itself and the petitioner being a party to
the said agreement, consciously agree to such procedure. Therefore, at this stage of the matter, the petitioner cannot be allowed to wriggle out of
the binding arbitration agreement between the parties. Therefore, the writ petition challenging the cancellation of such non-statutory contract cannot
be entertained.
Under the same impugned order dated 28.10.2009, the petitioner has been blacklisted from the list of contractors. Blacklisting a registered
contractor that too a contractor who has been registered with the department from 1970 onwards is of serious consequences to the petitioner and
before the same is resorted to the petitioner is entitled to the afforded adequate and effective opportunity to putforth his defence. In the instant
case, the aspect regarding the cancellation of the contract as well as blacklisting were rolled into a common show cause notice and a common
order came to be passed. This in my view may not be an appropriate procedure, since the matter pertaining to a blacklisting of contractor is an
independent issue, since a person who is the tender awarding authority would be entitled to cancel a contract awarded, but may lack the power to
blacklist the contractor, since his registration would be by another authority at a higher level. In any event the department may not resort to
blacklisting based on a solitary instance and several factors have to be gone into before such power is being invoked.
It is an admitted fact that black listing of a contractor is a serious matter as it involved civil consequences and the contractor is shut out from
being able to participate in any of the bids or auction. Therefore, the Honourable Supreme Court and this Court have consistently held that when a
department or an agency decides to black list a contractor, it is incumbent that the principles of natural justice should scrupulously followed.
The said proposition has been emphasised by the Honourable Supreme Court in the following decision;
(i) In Erusian Equipment and Chemicals Ltd. Vs. State of West Bengal and Another, the Honourable Supreme Court has held in paragraph 20 as
follows;
Blacklisting has the effect of preventing a person from the privilege and advantage of entering into lawful relationship with the Government for
purpose of gains. The fact that a disability is created by the order of blacklisting indicates that the relevant authority is to have an objective
satisfaction. Fundamentals of fair play require that the person concerned should be given an opportunity to represent his case before he is put on
the blacklist.
(ii) In Joseph Vilangandan Vs. The Executive Engineer, (Pwd), Ernakulam and Others, while following the jugdment in Erusian Equipment case
(cited supra), has stated that while conceding that the State can enter into contract with any person it chooses and no person has a fundamental
right to insist that the Government must enter into a contract with him, held that the fact that a disability is created by the order of black listing
indicates that the relevant authority is to have an objective satisfaction. Fundamentals of fair-play require that the person concerned should be given
an opportunity to represent his case before he is put on the black-list.
(iii) In Raghunath Thakur Vs. State of Bihar and Others, while considering a case where the person granted a right to vend liquor was placed in a
black listing in respect of future contracts, the Honourable Supreme Court has observed that even if the rules do not express so, it is an elementary
principle of nature justice that parties affected by any order should have right of being heard and making representations against the order. In that
view of the matter, the last portion of the order in so far as it directs blacklisting of the appellant in respect of future contracts, cannot be sustained
in law.
The decisions in the case of Raghunath Thakur and Erusian Equipment as referred supra have been followed by the Honourable Supreme
Court in B.S.N. Joshi & Sons Ltd. v. Nair Coal Services Ltd. and Ors. reported in (2006) 2 SCC 548 and reiterated the principles laid down.
Therefore in view of the ratio laid down by the Honourable Supreme Court as stated above an order of black listing has civil consequences for
future business of person concerned and the person affected by an order has a right of being heard and making a representation against any order
even though the Rules do not provide specifically.
The learned Special Government Pleader would submit that the petitioner had been afforded with an opportunity and a show cause notice was
issued, reply was received and thereafter, an order has been passed. Therefore, the learned Special Government Pleader submits that there has
been substantial compliance of principles of natural justice and the impugned order is perfectly legal and valid. On the other hand, the learned
Counsel appearing for the petitioner would submit that the impugned order is devoid of reasons .
It is relevant to note that the Honourable Supreme Court in a decision reported in S.N. Mukherjee Vs. Union of India, observed that in view
of the expanding horizon of the principles natural justice, the requirement to record reasons can be regarded as one of the principles of natural
justice which govern exercise of power by administrative authorities. The rules of natural justice are not embodied rules. The extent of their
application depends upon the particular statutory framework where under jurisdiction has been conferred on the administrative authority. With
regard to the exercise of a particular power by an administrative authority including exercise of judicial or quasi judicial functions the legislator,
while conferring the said power, may feel that it would not be in the larger public interest that the reasons for the order passed by the administrative
authority be recorded in the order and be communicated to the aggrieved party and it may dispense with such a requirement.
The respondents being an administering authority is bound to act fairly and reasonable and all the actions of the respondents have to satisfy the
touchstone of reasonableness. The requirement to record reason is incumbent and Courts have consistently held that an order devoid of reasons is
in violation of principles of natural justice and liable to be set aside.
Thus, in view of the law laid down by the Hon''ble Supreme Court, I am of the clear view that the petitioner has not been afforded adequate
opportunity before he was blacklisted and therefore, the impugned order to that extend has to be held to be illegal.
The impugned order in W.P. No. 24442/2009 is a re-tender notification dated 16.11.2009. This re-tender notification is a consequence of the
cancellation of the contract awarded to the petitioner. In the previous part of this order, it has been held that the remedy for the petitioner against
the cancellation of the contract is under Clause 55 & 56 of the agreement and Writ Petition is not the remedy. In such circumstances there will be
no justification for the petitioner to prevent the department from conducting a re-tender for the work. It is relevant to note that the work relates to a
road development work in Nilgiris District and it is common knowledge that owing to recent lands slides in the area, these works cannot be
withheld for indefinitely long period of time, that to the instance of the petitioner. It has been stated in the counter affidavit that the proposed road
work is an important link road and the public are suffering without proper link road and taking circuitous route for the conveyance of agricultural
products to market centres and the school going children are also put to great difficulty and if there is delay in completion of the road work on time,
it would result in escalation the cost and interest. In view of the said submissions, I am of the clear view that the petitioner is not justified in
withholding the re-tender pursuant to the notification dated 16.12.2009. It is needless to state that though this work is at the risk and cost of the
petitioner, such claim of risk and cost would be subject to the arbitration proceedings, which the petitioner is bound to raise in terms of the
conditions of the agreement. Therefore, I find that there are no valid grounds to quash the re-tender notification.
In the result the Writ petitions are disposed of with the following directions:
i) The writ petition filed challenging the impugned order dated 28.10.2009 in W.P. No. 24443/2009 challenging the cancellation of contract
awarded to the petitioner is not maintainable and the remedy for the petitioner is only under Clause 55 & 56 of the agreement dated 14.03.2008,
and accordingly the Writ Petition challenging that portion of the order canceling the contract is dismissed.
ii) The order of blacklisting of the petitioner from the list of registered Class I contractors under the same order dated 28.10.2009 is held to be
illegal and bad in law and in gross violation of principles of natural justice. Therefore, the impugned order dated 28.10.2009 in so far as it relates to
blacklisting the petitioner is quashed, leaving it open to the Department to initiate fresh action in accordance with law if so advised.
iii) The W.P. No. 24442/2009 filed challenging the re-tender notification dated 16.11.2009 is dismissed.
iv) The petitioner shall be entitled to invoke the procedure for settlement/resolution of dispute under clauses 55 & 56 of the agreement dated
14.03.2008 and in such proceedings, the petitioner would also be entitled to contest the cancellation of the contract, the justifiability of the fine
levied as well as the aspect regarding risk and cost contemplated on account of re-tender dated 16.11.2009, and all other matter which are
covered within the scope of Clause 55 & 56 of the agreement.
v) Consequently, the respondents are directed to proceed further with the re-tender notification dated 16.11.2009 and finalise the tender in
accordance with law.
vi) Consequently, connected miscellaneous petitions are also closed. No costs.
