High CourtsSingle Bench

Satendra Kumar Singh vs State Of Bihar

Patna High Court · Decided on 23 December 2022 · Citation: (2022) 12 PAT CK 0072

HON’BLE JUDGES
Sunil Dutta Mishra, J
RESULT
Allowed
CASE NUMBER
Civil Revision No. 221 Of 2017

AI Structured Summary

Not yet generated for this judgment

Judgment

11 paragraphs · 752 words
1.

Heard learned counsel for the parties.

2.

This Civil Revision application under Section 13 of the Bihar Works Contracts Disputes Arbitration Act, 2008 (hereinafter referred to as “the Act”) has been filed to set aside in part the award dated 14.07.2016 passed in Reference Case No. 85 of 2014 passed by the Bihar Public Works Contract Disputes Arbitration Tribunal (in short “the Tribunal”).

3.

The brief facts of this case are that petitioner entered into an agreement No. 54 F2 of 2001-02 dated 24.03.2002 for the execution of the work, namely, “Construction of bashing ghat and protection of service road near Mahuari Village for G.C.B.C.”. The agreement value of the work was at Rs. 4,71,173/- and time of completion was 3 months. Due to dispute arises between the parties with respect to non-payment to the petitioner for the work done reference petition bearing no. 85 of 2014 filed by the petitioner before the Tribunal and the Tribunal passed the impugned award on 14.07.2016.

4.

The Tribunal in its impugned award held that the dues of petitioner amounting Rs. 2,23,103/- only is admitted, hence, the petitioner is entitled for the payment of the said dues. On the point of interest the petitioner has claimed the interest on dues amount from the date of cause of action, but the Tribunal held that the interest should be paid from the date of filing i.e. on 12.08.2014 simple interest at the rate of 10% per annum on awarded amount. The petitioner aggrieved on the point of interest i.e. rate and period awarded in award preferred this Revision application.

5.

Learned counsel for the petitioner has submitted that the Tribunal has wrongly declined to award the pre-reference interest i.e. from the date of cause of action arises to the petitioner for payment of dues amount till the filing of the reference case. He has further submitted that the petitioner is entitled to award of 18% interest as envisaged under Section 31(7) (a) (b) of the Arbitration and Conciliation Act, 1996 but the Tribunal has awarded interest only at the rate of 10% per annum.

6.

Learned counsel for the respondents has supported the impugned award and submitted that there is no illegality in the impugned award and the award is well reasoned.

7.

Learned counsel for the petitioner has submitted that this Revision application may be disposed of in terms of the Judgment and order passed by coordinate Bench of this Court on 24.04.2017 in C.R. No. 180/2016 wherein also the identical issue arose for consideration and determination. He has further submitted that vide Judgment dated 18.07.2017 passed in Civil Revision No. 213 of 2016, on similar issue the matter was remitted back to Arbitral Tribunal for deciding afresh on the issue pertaining to interest.

8.

Learned counsel for the opposite parties also agreed for disposal of this revision application by passing an order in similar line with the order dated 24.04.2017 passed in C.R. No. 180/2016.

9.

In the said Judgment/order dated 24.04.2017 the Court considered the relevant provisions and the Judgments of Hon’ble Supreme Court on the point and the matter was remanded back to the Arbitral Tribunal for decision afresh in accordance with law.

10.

In the present Civil Revision application the notes of discord between the parties, as mentioned above, pertains to the refusal by the learned Tribunal to pay the interest for the pre-reference period and the award of interest pendente lite at the rate less than 18% per annum. The entitlement of a person to interest, in case of money which is legally due has been recognized by the Constitution Bench in Secretary, Irrigation Department vs. G.C. Roy, (1992) 1 SCC 508.

11.

In view of the submission on behalf of the parties, the present Revision application is allowed in terms of the order dated 24.04.2017 passed in C.R. No. 180 of 2016 and the impugned award is quashed, only so far as the same relates to the issue of rate of interest and the period for which the petitioner may be entitled to interest in accordance with law. The matter is remitted back to the Arbitral Tribunal for decision afresh on the aforesaid issues pertaining to interest in accordance with law after granting opportunities to the parties for fresh hearing. It is also clarified that any observation(s) made in the Judgment/order dated 24.04.2017 in C.R. No. 180/2016 shall not prejudice the case of either of the parties which shall be decided on its own merits in accordance with law.