AI Structured Summary
Not yet generated for this judgment
Judgment
The question to be answered in this case is whether the Kolkata
Metropolitan Development Authority (KMDA), the respondent no.2 can, as
the lessor of the subject land demand any penal charges for delayed
construction by the lessee Siddhartha Co-operative Housing Society Ltd.
the petitioner and for the extension of time granted by them to it, to
complete it.
The facts are these.
On 8th March, 2001 the said respondent by a lease deed granted a 99
year''s lease to the petitioner of the subject land with a condition that they
had to complete the construction on it within three years. There is no doubt that the petitioner made considerable delay in submitting the
building plan for sanction. In fact, it was submitted for sanction in 2006
and sanctioned in September of the same year. Although in May, 2009 the
respondent authority was contemplating determination of the lease by
issuing a show cause notice dated 5th May, 2009 asking the petitioner why
the lease should not be determined, it took no steps in that direction. It
extended the time to complete the construction upto 31st December, 2011.
On 5th January, 2012 they wrote to the petitioner stating that since the
time period for completion of the work had been extended from 8th March,
2004 till 31st December, 2011, they were required to pay Rs. 37,53,974 to
the authority as penal charge for delayed construction. Again by a letter
dated 5th October, 2012 time was extended till 30th September, 2012,
subject to payment of Rs. 42,48,216/- as penal charges. Again by the letter
dated 19th October, 2012 time to make construction was extended till 31st
March, 2013 upon making payment of Rs. 45,87,258 as penal charges.
On 20th January, 2016 another notice was issued by the respondent
authority demanding Rs. 1,95,14,488 from the petitioner as penal charges
from 8th March, 2004 to 29th February, 2016.
The idea of claiming penal charges has its genesis in the 9th meeting of the
Land and Flat Allotment Committee of the authority held on 21st January,
2009 in Kolkata. Agenda-6 noted that often, the lessees ask for extension
of time to complete the construction. Imposition of penal interest would
compel them to complete it within time. The committee felt that suitable modifications in the Land and Flat Allotment Policy should be made,
approved by the Pricing Committee. The meeting of the Pricing Committee
was held on 12th February, 2009. It resolved that if construction was not
started within time or completed within time, penal charges would be
imposed at the rates mentioned in the table. On 27th March, 2009 the
decision was ratified at the 159th meeting of the authority. Significantly,
the decision included penalty in "past cases".
The writ petitioners have challenged in this writ application the successive
notices claiming penal charges.
Now, the question is: was this demand justified? Now, what is the nature of
this penal charge imposed and demanded by the respondent authority? It
is more in the nature of a tax than anything else because the state
machinery, the respondent authority is asking for money from the
petitioner without rendering any service. If they had rendered service and
asked for compensation it would more appropriately be termed as a fee.
Article 265 of the Constitution of India enacts that no tax shall be levied or
collected except by authority of law. Under Schedule-VII List-II, of our
Constitution being the State List, the state legislature has got the power to
impose taxes on lands and buildings (Entry-49). Under Entry-5 it has the
power to create local authorities like the respondent and delineate its
powers. Entry-66 empowers the State legislature to prescribe fees in
respect of any matter in the list excluding court fees. If you consider the
respondent to be falling under the description of the Municipalities in Article-243 of the Constitution, under that Article the legislature of a State
may by law authorise, a municipality to, levy collect and appropriate inter
alia taxes and fees.
Learned Counsel for the respondent referred to Section-18 of the said Act
which provides that the powers and functions of the Kolkata Metropolitan
Development Authority shall be as provided in Section 13 of the Act.
Thereafter, he cited Section-13 (1) (ii) (h) and (l) of the Act which empowers
the authority to manage such property as felt necessary by it and to inter
alia lease or transfer such property. Section 13 (1) (ii) (l) empowers the
authority to perform any other function which was connected to the
functions entrusted with it under the above sub-section 13(1) (ii) of the Act.
In my opinion, these are only the general powers granted to the
development authority to acquire and manage properties under its control.
It does not authorise it to impose any tax or penal charges.
As discussed earlier, tax and penal charges can only be imposed by
sanction of the legislature. The power to tax or to realise a charge akin to a
tax or fee must be expressly conferred by the legislature. The above
provisions, in no manner authorise the development authority to levy penal
charges.
It follows and it goes without saying that the authority had no power to
issue any kind of tax or charge retrospectively.
Now, the other question which falls for consideration of this court is
whether by virtue of the lease deed or the contract between the parties the said authority had the power to levy penal charges. Learned Counsel for
the authority relied on 2 (b) of the lease deed which said that the lessee
would be liable to pay to the authority "charges as may be imposed by the
authority from time to time in respect of demised land". This clause of the
agreement, in my view, related to charges that may be payable by the
lessee for enjoyment of the property like maintenance charges, facility
usage charges so on. This clause did not in my opinion authorise the lessor
to impose penal charges of substantial sums of money for delay in
completing the construction envisaged in the lease deed. The authority
could have specifically mentioned that those penal charges would be
payable and realisable, in the lease deed. For that no legislative sanction
was necessary. It would have been a condition of the contract. Due to
inadvertence or oversight this contingency was not in the mind of the
authority when this lease was drawn up. Now, unilaterally, without the
consent of the lessee, charges cannot be imposed by the lessor.
The authority has to seek a legislative mandate for this purpose or
modification of the lease deed or enter into an independent contract with
the petitioner.
For all those reasons, this writ application succeeds. The demand notices
mentioned in the prayers of the petition are quashed. The respondents are
restrained from enforcing against the petitioner the demand of Rs.
1,95,14,488 mentioned in prayer (a) of the petition. This writ application is
allowed to the above extent.
Certified photocopy of this Judgment and order, if applied for, be supplied
to the parties upon compliance with all requisite formalities.
