High CourtsSINGLE BENCH(2017) 08 CAL CK 0027

Sikaria Divinity Private Limited vs State of West Bengal

Calcutta High Court · Decided on 18 August 2017

HON’BLE JUDGES
I.P. Mukerji
RESULT
Allowed
CASE NUMBER
543 of 2017

AI Structured Summary

Not yet generated for this judgment

Judgment

434 paragraphs · 5,178 words
1.

The river Hooghly, while flowing down the plains of Bengal towards the sea,

has branched out, upstream of Chuchura in the Hooghly District, to form a

beautiful island in the middle of the river, measuring about 75 acres. It is

called "Sabuj Dweep". It has trees and plants of many kinds and

recreational facilities which attract thousands of tourists over the year. The

land belongs to the Department of Tourism, Government of West Bengal.

This department conceived of the idea of developing the island into a eco-

tourism resort. On 14th August, 2015 it entered into a contract with the

petitioner which was described as a "concession agreement". The petitioner was entrusted with the construction and development of a "project",

according to the plans, designs and project report prepared by the

respondent, taking all the approvals, permits etc. and by complying with

the laws so as to ensure "bio-diversity". It was for 32 years to be renewed

for a further period of 32 years. The petitioner was required to make an

initial payment of Rs. 70 lakhs followed by an annual fee.

This application under Section 9 of the Arbitration and Conciliation Act,

1996 has been made further to an arbitration clause in the agreement.

The petition is in two volumes. All the papers that would have been

necessary to dispose of the Section 9 application are included in the

petition. Extensive arguments have been made. I propose to dispose of this

application, on these papers without inviting affidavits. It goes without

saying that the allegations made in the petition, are denied by the

respondent.

2.

We have to take our starting point as 8th March, 2017. On that day the

Principal Secretary Tourism Department wrote to the Managing Director of

the petitioner telling him that his government had invested more than Rs.

9 crores in the project. They had set up the jetty, built roads made

available drinking water and power supply to the island. It blamed the

petitioner for not starting the work on time and for the delay in proceeding

with it. What is most important is that the Principal Secretary granted the

petitioner six months'' time to complete some "pin pointed few basic components" of the project, mentioned in the annexure to the letter. In this

annexure the following works were specified:

"1. The entire place has to be divided into 2 segments (i) Picnic spot on the right side (ii) Cottage on the left side

2.

Two/Three common wash room.

3.

20 double bedded room with a dormitory facility separately.

4.

Food court for bit high end in segment-(ii) & day to day food court in segment--(i)

5.

Two watch towers

6.

Proper landscaping

7.

Display of local hand crafts with artisans.

8.

Swimming pool for segment--(ii)

9.

Games for both side.

10.

New vessel for carry vehicles with jetty in segment--(ii)

11.

Path way.

12.

Generator facility.

13.

Signage on high way

14.

Cultural activities area.

15.

Parking place for vehicle arriving in island in segment--(ii).

15.

Eco friendly vehicle for access to cottage from jetty in segment--(ii)

16.

Battery operated car for joy rode.

17.

CCTV."

3.

The petitioner replied to this letter on 12th April, 2017 by expressing their

commitment to finish the seventeen items mentioned in the above

annexure by 31st August, 2017. They added that they had started the

construction of double bedded wooden cottages. They also said that an

item wise schedule was attached to the letter but I do not find any such

schedule. On 29th May, 2017 the petitioner reported to the Secretary of the

Tourism Department that the work was progressing in accordance with the

schedule submitted on 12th April, 2017. This time a progress chart was

attached to the letter. According to this chart construction of two jetties on

the main island, improvement of 1.5 kilometres of PWD road from Somra

Bazar Station, Sukhriya Ghat at Hooghly were completed. Some other

works were shown to be partly completed.

4.

Suddenly on 8th June, 2017 a show cause notice was issued by the

Director of Tourism to the petitioner alleging the following acts of default

on their part in the performance of the agreement.

"a. No plantation is done for soil erosion.

b. No safety officer is there in the work site.

c. there are no labour camps onsite with sanitation and hygiene facilities.

d. Absence of noise level monitoring.

e. Absence of embankment around the project.

f. Total built up area is 24773 sqm. So it may require environment clearance g. Cooking facility of workers is there and it is learnt they are using wood by feeling the branches of trees.

h. Constructions of houses are going on with eucalyptus (majority) is foundation and structure.

i. There is one tube well for water source at the site. j. As per DPR total project cost for the entire project is 36924.69 lakhs and total contribution by the promoter is Rs. 10,017.51 lakhs and Rupee Loan would be cause for Rs. 18998.68 lakhs.

Sikaria Divinity (P) Ltd. proposed that project cost & investment would be funded through a mix of equity and debt out of which and amount of Rs. 18998.68 lakhs is proposed to be raised as debt.

Except copies of extract of the minutes of the Board meeting dated 13.01.2016 and extract of extra-ordinary General Meeting dated 02.02.2016 nothing else is submitted as to its financial capacity."

5.

In addition it was alleged that the petitioner was damaging the

environment, did not have the acceptable financial standing, failed to

perform their obligation under Article 6.10 (iii) of the agreement, did not

maintain a proper office and so on.

6.

The notice was stated to be issued under Article 11.4 (a) (1) of the

agreement asking the petitioner to rectify the alleged breach within thirty

days failing which the agreement would be terminated.

On 20th June, 2017, without any reference to this show cause notice the

petitioner wrote to the District Magistrate, Hooghly that the work was

progressing according to the work schedule submitted by the letter dated

12th April, 2017 and that the end of August, 2017 or the first week of

September, 2017 could be targeted by him as the possible time for

inauguration of the project by the Hon''ble Chief Minister. On 30th June,

2017 the petitioner replied to the show cause notice dated 8th June, 2017,

meeting each and every charge levelled in it. According to the petitioner

most of the work alleged to have been left undone was the responsibility of

the state instrumentalities. An expert had already been appointed by them

to monitor the noise level, no worker was cooking any food at the site as

there was no facility to do the same. Use of eucalyptus tree was in

accordance with the PWD manual.

7.

On 7th July, 2017 this application was filed by the petitioner for inter alia

the following reliefs:

"(a) Injunction restraining the respondent whether by itself or its men,

agents, servants, assignees or otherwise howsoever from interfering with

the peaceful exercise of the rights and discharge of obligation by the

petitioner in accordance with the agreement.

(b) Operation of the show cause notice dated June 8, 2017 be permanently

stayed."

8.

Even before the application could be moved the Director of Tourism issued

a notice dated 11th July, 2017 terminating the contract.

What are the reasons ascribed in the termination notice dated 11th July,

2017 have to be seen.

9.

What appears from an examination of this document is that maintenance

of the natural environment suddenly became a prime concern of the

government. The petitioner was accused of doing activities which "endanger

the environment and the eco system". They had caused "soil erosion" their

labour force was "cutting trees and using the same for fire wood" there was

"no solid waste management". The employees of the petitioner were

accused of "destruction of environment" and damage to the "eco system of

Sabuj dweep in general and flora and fauna in particular". Their work had

"seriously affected the biodiversity of the island and adjoining areas". A

proper hygiene standard was not adhered to and so on.

ARGUMENTS:-

10.

The first point raised by Mr. Mitra for the petitioner was that this

termination notice was issued when the application was awaiting

consideration of this court for passing an interim order. It was issued to

make the application infructuous. It was per se bad.

11.

Secondly, on 8th March, 2017, the Principal Secretary Tourism Department

of the Government of West Bengal had forwarded to the petitioner by letter an agenda of the project to be completed within the next six months. How

could the contract be terminated by the Director of Tourism without even

referring to even one of the 17 items as not having been completed by the

petitioner or not completed to the satisfaction of the government? From

time to time by letter dated 12th April, 2017, 29th May, 2017, the petitioner

had sent the government and particularly the Principal Secretary a status

report showing which portion of the work was completed, what work was in

progress and what part of it was required to be done by the government or

by the state agencies. According to Learned counsel the government was

fully satisfied with the progress of the work done by the petitioner. That is

why they did not write a single letter controverting the progress reports

submitted by the petitioner or stating that the petitioner was in breach of

the contract.

12.

It was argued that the show cause notice issued on 8th June, 2017, was

extraordinary in the sense that there was no allegation of breach of the

agreement by the petitioner. Peripheral issues like soil erosion, absence

noise level monitory, absence of embankment, cutting of trees by the

workers, financial incapacity of the writ petitioner, absence of a public

relation office and complaint register in the project site etc. were raised,

calling upon the petitioner to answer the accusation and close the breach

failing which the contract would be terminated.

13.

It was also said that this letter was replied to by the petitioner 30th June,

2017, dealing with each and every allegation specifying the items of work completed by the government or its agency and which part of the work was

required to be completed by the petitioner and what portion of it had

actually been accomplished.

14.

Mr. Mitra submitted that under this project possession of 75 acres of land

was handed over to his client for 32 years with a renewal clause extending

to another 32 years. He added that the entire island was handed over to

his client under the agreement to do landscaping work, maintain it, make

construction thereon, set up recreational facilities arrange for

transportation from the banks of the river to the island and so on. The

petitioner was required to pay the initial consideration as provided in the

agreement and an annual fee. It had the right to levy charges for use of the

facilities and appropriate the same, obviously to run the project site

profitably. Learned counsel submitted that the work came within the

purview of Section 14 (3) (c) of the Specific Relief Act, 1963 which is as

follows:-

"(3) Notwithstanding anything contained in clause (a) or clause (c) or clause

(d) of sub-section (1), the court may enforce specific performance in the following cases.

(C) where the suit is for the enforcement of a contract for the construction of any building or the execution of any other work on land:

Provided that the following conditions are fulfilled, namely:

(i) The building or other work is described in the contract in terms sufficiently precise to enable the court to determine the exact nature of the building of work;

(ii) The plaintiff has a substantial interest in the performance of the contract and interest is of such a nature that compensation in money for non-performance of the contract is not an adequate relief; and

(iii) The defendant has, in pursuance of the contract, obtained possession of the whole or any part of the land on which the building is to be constructed or other work is to be executed."

15.

He said that the scope of the work was specifically defined in the

agreement. The petitioner had a substantial interest in the contract by

reason of its duration and extent. Compensation in money would not be an

adequate relief.

16.

Mr. Chowdhury, Additional Government Pleader, for the respondent

repeated the contents of the show cause notice and the termination notice

stating that the petitioner was making large scale destruction of the

environment. Their employees were cutting down the trees. They were used

for building cottages and using wood to light fire to cook their food etc.

They were also accused of making the whole place dirty. The petitioner was

unable to prevent soil erosion, preserve the embankment. They did not to

have a financial ability to complete the rest of the project.

17.

Mr. Chowdhury submitted that this was a contract which could not be

ordered by the court to be specifically performed. It was by its nature

determinable. In the unlikely event of the petitioner succeeding, they could

be compensated by award of damages. The principles on which damages

were to be awarded were specified in detail in the contract. If the court

granted an order of injunction restraining the respondent from giving effect

to the termination notice, it would amount to an order indirectly ordering specific performance of the contract by the respondents. He invited the

court''s attention to Section 14 of the Specific Relief Act, 1963 and

submitted that the contract in question matched the description of the

contract in sub-Section (1) (a) (b) (c) and (d) thereof, which according to the

Act stipulated they could not be specifically enforced. He said that

compensation in money was an adequate relief ( Section 14 (1)(a)). The

contract ran into so many minor details and involved performance of

continuous obligations which the court could not supervise and which the

court could not order to be performed specifically ( Section 14 (1) (b) (c)).

I shall discuss the law cited by learned counsel for the parties at the time

of discussing their submissions.

DISCUSSION:

18.

Let me first discuss the prima facie case of the parties. On 8th March, 2017

the Principal Secretary, Tourism Department, Government of West Bengal

had given the petitioner six months time to complete the seventeen items of

work mentioned in the annexure to that letter. Between 12th April, 2017

and 29th May, 2017 the parties corresponded. The effect of this was that

the petitioner pledged to complete those seventeen items of work by 31st

August, 2017. They had also submitted progress charts showing the items

of work which had been completed by them, those in relation to which the

work was in progress and the rest that could only be completed by the government or its agencies. I have not found any letter or e-mail of the

Tourism Department to the effect that they were dissatisfied with the

progress of work. However, on 8th June, 2017 a show cause notice was

issued to the petitioner by the Director of Tourism Department on

absolutely collateral issues as mentioned above.

19.

There was not a single line in this show-cause accusing the petitioner of

breach of their obligations under the letter dated 8th March, 2017.

Therefore, I take it that the respondent was satisfied with the petitioner''s

performance of the agreement.

20.

Meanwhile, the petitioner on 20th June, 2017 wrote to the District

Magistrate, Hooghly that by the end of August, 2017 or the first week of

September, 2017 the Hon''ble Chief Minister could be requested to

inaugurate the project. On 30th June, 2017 the petitioner replied to the

show cause notice as stated above.

21.

It does seem quite extraordinary to this court that when there was no

earlier allegation against the petitioner that it was damaging the

environment, such an allegation could suddenly be raised from June,

2017. Equally, unbelievable appears to be the accusation against them

that they were so unfriendly to the environment that the agreement had to

be terminated. No documents have been brought on record to show that

there was destruction of flora or fauna or the ecology by the petitioner.

Furthermore, when on 8th March, 2017 six month''s time had been given to

the petitioner to complete the list of work mentioned in the annexure to that letter, the Director of Tourism could not have terminated that

agreement. Particularly, when there was no allegation against them that

they were unable to proceed with or complete the seventeen items of work

specified by the Principal Secretary. In my opinion, the aspersion on the

petitioner that they were damaging or destroying the environment,

disturbing the ecological balance, bio-diversity etc. is suspicious. Prima

facie the court does not find any evidence in support of it or believe it.

Hence, in my prima facie opinion, the petitioner is not and the respondent

is in breach of the contract. Prima facie the termination of the contract is

wrongful.

22.

Is it a case where an injunction should be granted setting aside the notice,

terminating the contract, issued by the respondent?

The principles governing the grant of an order of injunction are contained

in Order 39 Rules 1 & 2 of the Code of Civil Procedure and sections

37, 38, 39, 40 & 41 of the Specific Relief Act, 1963.

23.

In order to merit consideration for grant of an injunction the prima facie

case of the petitioner has to be established. To a very large extent the

strength and weaknesses of the case of the parties have to be assessed by

the court on the available evidence to come to a provisional conclusion as

to whether the petitioner, on a balance of probabilities, has a better case

than that of the respondent. Once the petitioner has been able to establish

a prima facie case the court proceeds to consider the balance of

convenience and the irretrievable injury factor. This means that the balance of convenience must be in favour of an order being passed in

favour of the petitioner and that irretrievable injury will be caused to him if

the order is denied.

27.

More often than not, it is not possible for the court to adjudge the prima

facie case immediately. In that event the petitioner has to satisfy the court

that he has raised a fair question or a substantial question to be tried. In

those circumstances, the court will pass an order of injunction so as to

hold the scales even pending trial of the case.(see Fellows v. Fisher

reported in (1975) 2 AllER 829 and 834 and American Cyanamid v.

Ethicon reported in (1975) 1 AllER 504 and Hubberd v. Pitt reported in

(1975) 3 AllER 1 (CA)).

25.

It is settled law that in case where damages provide the remedy an interim

order of injunction cannot be granted. Conversely in contractual matters

only in a suit for specific performance of an agreement could the court

grant an order of injunction. This common law principle is well spelt out in

Section 41 (e) of the Specific Relief Act, 1963. It is also trite that the court

will not grant an order of injunction in a contract which is, by its nature

determinable, and for breach of which damages are an adequate relief, or

in a contract performance of which entails constant supervision by the

court or one which runs into minute details. This is so because the court

will not order specific performance of such a contract (see Sections 14 (1)

(a) (b) (c) and (d) of the Specific Relief Act, 1963).

Now, consider the following facts.

26.

The duration of the contract was stated to be 32 years, renewable for

another 32 years. The contract specifically stated that the petitioner would

enjoy exclusive possession of the project site with blanket rights of

developing the island and making construction thereon and "operating and

managing the project". Article 3 (4) (see page 120 of the petition) even went

to the extent of saying that the petitioner would get possession of the

island free from all encumbrances, charges etc immediately on execution of

the agreement. Such was to be the extent of control of the petitioner that

they could "demand collect and appropriate charges from the users of the

project" (see Article 2 (2) (d)). It was like an unfettered charter granted to

the petitioner, on the island. All these rights the petitioner acquired on

payment of an initial amount of Rs. 70 lakhs. They were required to pay an

annual concession fee to operate in the island which would increase by 5 %

every year. In spite of my best efforts I have not been able to find the

annual concession fee payable by the petitioner to the respondent in any

conspicuous place of the agreement.

27.

Therefore, Mr. Mitra appearing for the petitioner was right when he said

that the contract in question came within the exception to the principles

laid down in Section 14, provided in sub- section 3 (c) thereof. Indeed, the

petitioner has a substantial interest in the land as well as in the project.

What difference in status is there between the petitioner and a lessee of a

land? A lease is a transfer of a right to enjoy the property for a certain

length of time in consideration of money paid or promised to be paid periodically (see Section 105 of the Transfer of Property Act, 1882). The

petitioner is in exclusive possession of the island free from any

encumbrances under the agreement. The petitioner under that instrument

is to be in possession for 32 years and can expect to have a further period

of 32 years on payment of an annual fee. It has all the incidents of a lease.

The only problem is that a lease over one year is supposed to be registered

whereas this document is not. Therefore, the interest of the petitioner is

quite substantial. Furthermore, they were entrusted with the execution of

works on the land which are clearly definable.

28.

In my prima facie opinion compensation in money is not an adequate relief

if the respondent is found to be in breach of the contract. This is so

because it is not at all very easy to estimate the profit that the petitioner

would earn out of the project in the next 32 years and the 32 years

following it. I prima facie hold that this contract is capable of being

performed specifically.

29.

The above principles of law are very well-known and have been laid down

and reiterated by the Supreme Court and the High Courts from time to

time. It is only the difference in facts which have resulted in divergent final

orders being passed by the court.

30.

Let me now deal with the cases cited by Mr. Chowdhury. In Indian Oil

Corporation Ltd. v. Amritsar Gas Service and Others reported in (1991)

1 SCC 533, the court was involved with an LPG distributorship agreement

granted by Indian Oil Corporation to the respondents. It held that the contract was determinable by nature. A contract is determinable when

either party has an option of terminating it giving limited notice to the

other party. (See also Rajasthan Breweries Ltd. v. The Stroh Brewery

Company reported in 2000 (3) ARBLR 509 (Delhi) cited by Mr.

Chowdhury). In those circumstances, the court held that the award made

by the arbitrator granting restoration of the distributorship was erroneous

in law. The respondents could best be entitled to compensation for loss of

earning for the period of notice. Hindustan Petroleum Corporation

Limited And Others v. Super Highway Services And Another reported in

(2010) 3 SCC 321 arose out of a writ application under Article 226 of the

Constitution of India. In that case the court held that termination of the

dealership agreement by the appellant was wrongful. As we all know in a

writ application the court adjudges whether any public law has been

violated by the respondent. It passes its orders accordingly. In that case

the court held that the action of the appellant was arbitrary, illegal and in

violation of the principles of natural justice. Similar was the decision of the

Supreme Court in the public law domain in Bharat Petroleum

Corporation v. Jagannath and Company and Ors . reported in (2013)

12 SCC 278. This case has no application here as the petitioner has

availed of a remedy obtainable on infringement of private law and not

public law by approaching this court under Section 9 of the Arbitration and

Conciliation Act, 1996.

31.

As I have said before, different facts result in different decisions. In Magma

Leasing Limited v. Credit Rating Information Services of India Limited

reported in (2001) 3 CHN 654, this court held that a contract for credit

rating could not be ordered to be performed specifically and that the

agency aggrieved by the termination of the contract had its remedy in

damages.

32.

In the case filed by Cox & Kings concerning the contract given by IRCTC

to them to run Maharaja Express jointly with the railways, the court held

that the contract could not be specifically performed and refused to set

aside the termination of the contract by the railways (see Indian Railways

Catering & Tourism Corp. Ltd. v. Cox & Kings India Ltd . reported in

(2012) 1 Arb LR 184. Similar was the view of the Delhi High Court with

regard to termination of an agreement for construction of bus shelters in

the case of Green Delhi BQS Ltd. v. Delhi Transport Corporation

reported in 2010 SCC OnLine Del 1360. In Jindal Steel and Power

Limited v. SAP India Pvt. Ltd . reported in (2015) 221 DLT 708 the

facts of the case which involved software licences. The court held that it

was a determinable contract and refused to pass an order of injunction.

Mr. Chowdhury relied on the definition of a works contract in Larsen And

Toubro Limited And Another v. State of Karnataka And Another

reported in (2014) 1 SCC 708. He submitted that the word "work on land"

in Section 14 (3) (c) of the Specific Relief Act, 1963 is to be given the same

meaning. I do not think his analogy is correct. The phrase has to be given a very wide meaning so as to include construction work, landscaping work,

beautification work, excavation and so on.

SUMMARY OF FINDINGS:

33.

Hence, the summary of my findings is as follows:-

a) Prima facie, the petitioner is in firm possession. This possession has

been granted to them for 32 years, renewable for another 32 years. The

petitioner has already started substantial construction work in the

island free from all encumbrances. The petitioner''s earning was assured

by the agreement that they would be able to retain a percentage of the

turnover. Therefore, the petitioner was performing works on land and

construction of building within the scope of Section 14 (iii) (c) of the

Specific Relief Act, 1963.

b) In the letter of the Principal Secretary Tourism Department dated 8th

March, 2017 there was no hint that the respondent was contemplating

terminating the contract. Time was extended upto 7th September, 2017

for the petitioner to complete the seventeen items of work mentioned in

the annexure to the letter.

c) Thereafter, from time to time the petitioner kept the respondent

apprised of the progress of the work. By the progress report the

petitioner had even expressed the hope that by the end of the August or

the first week of September this year the project could be inaugurated

by the Hon''ble Chief Minister. There is not a single letter of the respondent disagreeing with the progress report furnished by the

petitioner.

d) There was no whisper from the respondent upto the beginning of June,

2017 that the petitioner was damaging the environment.

e) It was only by the show cause notice dated 8th June, 2016 that the

petitioner was charged with causing damage to the environment.

f) The petitioner explained in detail by their letter dated 30th June, 2017

that they had not damaged the environment. Still, on 11th July, 2017

the contract was terminated alleging damage to the environment by the

petitioner. Ironically, no allegation was made that the petitioner was

otherwise in breach of the contract.

g) Although the Director of the Tourism Department as the concessioning

authority had the power to terminate the contract, he ought not to have

done it without the concurrence of the Principal Secretary. Furthermore,

since the Principal Secretary Tourism Department had granted the

petitioner six month''s time to complete the contract upto 7th September,

2017, at least, time upto 7th September, 2017 ought to have been given

to the petitioner to complete the work.

h) Prima facie the allegation against the petitioner that they were

destroying or damaging the environment appears to be without any

evidence.

i) Prima facie the petitioner has been performing the work in accordance

with the pace expected under the letter dated 8th March, 2017.

j) Prima facie the contract is not determinable by nature.

k) Prima facie an award of damages is not the proper remedy for breach of

this contract by the respondent.

l) The contract is definable and capable of being specifically performed

under the supervision of the court.

m) Prima facie the respondent is and the petitioner is not in breach of the

contract.

n) This application is pending in this court from 7th July, 2017. Because of

pendency of this application little or no progress could be made by the

petitioner in performing the work.

o) I do not say that the respondent has lost the right to terminate the

contract. But I do say that the termination of the contract on 11th July,

2017 was wrongful and illegal.

34.

In those circumstances, I pass the following order:

The termination notice dated 11th July, 2017 is set aside. Ordinarily,

the petitioner ought to have been granted time upto 7th September,

2017 to complete the work. Since, this application has been pending in

this court for nearly 45 days, the petitioner will get advantage of this

period. The respondent is restrained by an order of injunction from

terminating the contract till 7th September, 2017 and for a further

period of 45 days thereafter.

35.

After this period the contract can only be terminated for any alleged

breach of the petitioner after the date of this order. The petitioner will be

entitled to resume the work forthwith.

36.

The respondent is directed to co-operate with the petitioner.

The Principal Secretary Tourism Department is directed to ensure that

the officers under him do not misuse their power in dealing with this

contract.

37.

This application is accordingly allowed.

38.

Certified photocopy of this Judgment and order, if applied for, be

supplied to the parties upon compliance with all requisite formalities.