AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
1,149 paragraphs · 19,900 wordsThe judgment-debtor is the applicant.
The judgment-debtor has filed this application ostensibly under
Section 48 of the Arbitration and Conciliation Act, 1996 but essentially for
having a ''second look'' at the foreign award, notwithstanding an earlier order
dated 4th September, 2014, by which the question of maintainability
including enforceability of the foreign award was decided.
The earlier challenge was oral.
This time an application has been filed disclosing further grounds of
challenge to the enforceability of the award. The present application highlights a cosmetic difference between the expression "maintainability"
and "enforceability" used in the order dated 4th December, 2014.
The award-holder has filed an application for enforcement of a foreign
award in November 13, 2013.
Initially, the execution application was not accompanied by the
original award and a certified copy of the agreement for which a leave was
given to the decree-holder to produce the said documents, pursuant thereto
on 16th January, 2014, the original award and a certified copy of the
agreement were produced in Court. Justice I.P. Mukerji by an order dated
16th January, 2014 recorded the production of the said two documents and
photocopies of the said documents were taken on record without prejudice
to the rights and contentions to the judgment-debtor. The said order was
passed in presence of the judgment-debtor. The question of maintainability
of the application was kept open.
On 18th September, 2014, the judgment-debtor was directed to file an
affidavit disclosing the particulars of the bank accounts and the amounts
lying on to the credit of judgment-debtor in each of such bank accounts with
supporting documents mentioned in Paragraph 26 of the Affidavit in support
of the tabular statements. The said direction was passed without prejudice
to the rights and contentions to the judgment-debtor with regard to the
maintainability of the execution application. The judgment-debtor although
had filed an affidavit in terms of the earlier order but in the affidavit, the
judgment-debtor did not furnish any proof as required under Section 48 of
the Arbitration and Conciliation Act, 1996 questioning the enforceability of the said award nor any independent application was filed challenging the
enforceability of the foreign award. In absence of any such application being
filed, the judgment-debtor was invited to make submission with regard to
the enforceability of the foreign award as by that time the original award and
the certified copy of the agreement were taken on record. The expression
"maintainability" in both the earlier orders was intended to mean and, in
fact, meant enforceability of the award. The judgment-debtor has also
understood the earlier orders in the same manner as would be evident from
the submissions made and recorded in the order dated 4th December, 2014.
It is significant to note that in the affidavit filed in terms of the order dated
18th September, 2014, the judgment-debtor did not dispute the agreement
or the award and not a single sentence was mentioned raising any objection
with regard to the enforceability of the award. Thereafter, when the
execution application was taken up for hearing on 4th December, 2014, I
permitted the respondent notwithstanding the objection raised by the
decree-holder that no challenge in writing has been made with regard to the
enforceability of the award to argue on the maintainability of the award
meaning thereby the enforceability of the award.
The judgment debtor raised five objections with regard to the
enforceability of the said award.
The said objections are recorded in the order dated 4th December,
2014. The said objections as recorded in the order are reproduced below:-
"The first objection raised is that no prayer for declaration has been made in the application that the foreign award is enforceable. It is submitted that unless prayer is made seeking a declaration as to the enforcement of the award, the Court cannot assume jurisdiction. In this regard, the learned Senior Counsel has referred to a Single Bench decision of the Bombay High Court in the case of Toepfer International Asia Pvt. Ltd. Vs. Thapar Ispat Ltd., reported in 2000 (1) Arb. LR 230(Bombay) Paragraph 19.
The second objection is that a civil suit is pending between the parties in which there is a categorical observation both by the learned Single Judge as well as the Division Bench that any action taken by the parties to the suit during the pendency of the suit shall subject to and abide by the result of the suit. It is submitted that a cross appeal was preferred by the decree-holder and this observation of the learned Single Judge was not interfered with and accordingly the execution application is premature and unless the suit is decided, the award does not attain its finality.
The third objection is that the arbitration clause has not been properly invoked. It is submitted that arbitration clause is a two-tier clause. Before the arbitration clause could be invoked, the parties are required to first make an attempt to amicably settle their disputes and only upon failure, the parties could refer their disputes to the arbitration as per GAFTA clause for rice and arbitration rules 125. It is submitted that there is no averment in the petition that before invoking the arbitration clause there was any attempt to settle the disputes amicably. Since this stage has not been reached, the invocation of Arbitration Clause is void ab initio. In this regard, the learned Senior Counsel has referred to an unreported decision of a Single Bench of this Court in AP 112 of 2008 [ Waidhan Engineering & Industries Private Limited vs. The Board of Trustees For The Port of Kolkata ] decided on 5th May, 2010.
The fourth objection is that even if it is assumed for the sake of argument that this amicable settlement was not followed, even then Rule 3.1 was not followed with regard to the appointment of the sole Arbitrator. It is submitted that it was incumbent upon the decree-holder to inform the respondent about the appointment of a sole arbitrator and it was only on refusal to accede to such request that other procedures prescribed under the rules shall follow.
The fifth and the last objection appears to be that the nominee arbitrator of the respondent was appointed de hors the provisions of GAFTA Rules and accordingly the procedure adopted is irregular from the very beginning and the award is not enforceable."
These objections were considered and rejected. The relevant
observations in this regard are:-
"In order to appreciate the objections raised by Mr. Mitra, it would be fruitful to refer to the grounds on which the Court can interfere with regard to the enforcement of the foreign award. The grounds are mentioned in Section 48, which states:
"Section 48.
Conditions for enforcement of foreign awards.-
(1) Enforcement of a foreign award may be refused, at the request of the party against whom it is invoked, only if that party furnishes to the court proof that -
(a) the parties to the agreement referred to in section 44 were, under the law applicable to them, under some incapacity, or the said agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law of the country where the award was made; or
(b) the party against whom the award is invoked was not given proper notice of the appointment of the arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
(c) the award deals with a difference not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration: Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, that part of the award which contains decisions on matters submitted to arbitration may be enforced; or
(d) the composition of the arbitral authority or the arbitral procedure was not in accordance with the agreement of the parties, or, failing such agreement, was not in accordance with the law of the country where the arbitration took place; or
(e) the award has not yet become binding on the parties, or has been set aside or suspended by a competent authority of the country in which, or under the law of which, that award was made.
(2) Enforcement of an arbitral award may also be refused if the Court finds that -
(a) the subject matter of the difference is not capable of settlement by arbitration under the law of India; or
(b) the enforcement of the award would be contrary to the public policy of India. Explanation. - Without prejudice to the generality of clause (b) of this section, it is hereby declared, for the avoidance of any doubt, that an award is in conflict with the public policy of India if the making of the award was induced or affected by fraud or corruption.
(3) If an application for the setting aside or suspension of the award has been made to a competent authority referred to in clause (e) of sub-section (1) the Court may, if it considers it proper, adjourn the decision on the enforcement of the award and may also, on the application of the party claiming enforcement of the award, order the other party to give suitable security."
Of the various grounds referred to in Section 48, the real objections raised by Mr. Mitra come very close to section 48 (b) of the said Act with regard to the prior notice of the appointment of arbitrator. On the basis of the disclosures made in this petition it appears that the decree-holder invoked the arbitration Clause by a communication dated 28th July 2011. The subsequent communications disclosed in these proceedings would show that after giving opportunity to the judgment- debtor to appoint an Arbitrator, the Tribunal had exercised its power under Rule 3.3.
Mr. Bose has referred to the preamble and the other provisions of the Act in order to impress upon the maintainability of the petition. The preamble to the Section, in my mind, is like a window to a room which gives a vision that one could get in by entering a particular room. It is the edifice on which the structure is built. The preamble set outs the object which is supplemented in the statement of objections and reasons. The legislature has consciously done away with the various statutes regarding enforcement of a foreign award. The legislative intent underlying the Act is to minimize the supervisory role of the courts in the arbitral proceedings and very limited interference. The objection raised by the petitioner appears to be more in quagmire of despondency and a desperate attempt to resist execution of an enforceable award rather than a real challenge thrown to the maintainability of the said petition. There is no document disclosed by the respondent to show that any objection was raised either with regard to the initiation of proceeding or thereafter. The only explanation offered was that such proceeding is vexatious, harassive and involves probative costs. This argument was not accepted by the Division Bench. In any event, when the notice invoking the arbitration was issued there was no reply to the said notice. Mr. Mitra submits that the disputes shall be required to be submitted to GAFTA, London for arbitration and the decree-holder would not be entitled to invoke the clause unilaterally for appointment of an arbitrator.
In my opinion, this submission cannot be accepted. It is an institutionalized arbitration, the rules provide the manner in which the parties are to act in matters relating to arbitration. Elaborate procedures and mechanisms are provided in the Act for conduct of the arbitration. Rule 3 of GAFTA Rules deals with appointment of the Tribunal. It clearly shows that the disputes shall be heard and determined by a Tribunal or three Arbitrators (appointed in accordance with Rule 3.2) or, if both parties agree by a single Arbitrator (appointment in accordance with Clause 3.1). Once the petitioner has named an arbitrator and sent the notice to the opposite party it was open to the opposite party either to accept the said name or to disagree with the same, not later than 9th subsequent day after serving of the said notice, failing which the consequences mentioned in the other rules shall follow. On the basis of the materials on record it cannot be said that GAFTA Rules have not been followed with regard to the appointment of the Arbitrator. In fact the judgment-debtor was informed about the exercise of option and by reasons of failure of the said judgment-debtor to appoint the arbitrator the Dispute Resolution Service on 22nd September, 2011 appointed the nominee arbitrator on behalf of the judgement-debtor. Even otherwise, it is always open for either of the parties to waive a particular procedure. Mr. Mitra would submit that mere silence would not amount to waiver or acquiescence. There cannot be any dispute with regard to the same but this is a factual matter which can be decided only on evidence. It is too late in the day to argue that there is procedural irregularity or the judgment-debtor has not waived its right. Moreover, having regard to the fact that a suit has been filed, it is very clear that question of amicable settlement of dispute by negotiation was farfetched.
In such facts and circumstances, this Court is of the view that the objection raised by Mr. Mitra with regard to the maintainability of the petition cannot be accepted. Such objection is overruled. This execution application is held to be maintainable."
A Special Leave Petition was preferred against the said judgment being
SLP No.5612/2015. The Special Leave Petition was dismissed on 27th
February, 2015. A bare reading of the Special Leave Petition shows that the
order dated 4th December, 2014 was treated by the award-debtor as an
order passed in relation to enforceability of the award.
It would be clear from the Special Leave Petition and the grounds
taken thereunder that the award-debtor has understood the findings of this
Court as a finding on Section 48 of the 1996 Act. If any point that was
available to the respondent was not urged when an opportunity was given to
the applicant/judgment-debtor to raise all objections with regard to the
enforcement of the award it shall be deemed to have been waived and
operate as a constructive res judicata. The order dated 4th December, 2014
is final in so far as the objections under Section 48 of the 1996 are
concerned. It cannot be re-opened after two years by filing an application
when the applicant notwithstanding a remedy available to it did not file any
such application and allowed execution proceeding to continue. In fact,
notwithstanding any application being filed by the judgment-debtor to
question the enforcement of the foreign award, the said applicant was
permitted to take all possible defences available to the applicant and it was
only on consideration of such objections, the order dated 4th December,
2014 was passed.
A review application filed was also dismissed.
In view of the aforesaid, the objection raised with regard to the
composition of the Arbitral Tribunal and that the procedure for appointment
of Mr. R. Eikel as second Arbitrator on behalf of the petitioner by GAFTA
was not in accordance with the agreement of the parties (GAFTA Rules) and
the petitioner was not given proper notice of appointment of Eikel as the
Arbitrator on their behalf is final and cannot be reopened. In fact, this
argument runs counter to the pleadings made in the plaint. The petitioner
cannot be allowed to re-agitate the said point, on which the objection was
already considered in the order dated 4th December, 2014. In the Special
Leave Petition, same point was urged. The Hon''ble Supreme Court did not
interfere with the order dated 4th December, 2014.
Mr. Anindya Kr. Mitra, the learned senior Counsel appearing on behalf
of the applicant/award-debtor submits that the said order is not conclusive
with regard to the enforcement of the foreign award as at the stage of
receiving an application for execution of a foreign award, the Court is only
required to find out that the party applying for enforcement of a foreign
award, has produced before this Court the original award or a copy thereof
duly authenticated, the original agreement for arbitration or a duly certified
copy thereof or such evidence, as may be necessary, to prove that the award
is a foreign award. The Court on satisfaction that the requirements of
Section 47 of the Arbitration and Conciliation Act, 1996 are fulfilled permits
an application to be filed for execution of the foreign award. However, the
enforcement of the foreign award is a step subsequent to acceptance of the
execution application and could be refused at the instance of the award debtor on the grounds enumerated in Section 48 of the said Act. The
learned Senior Counsel submits that although in the order dated 4th
December, 2014, some aspect of Section 48 of the Arbitration and
Conciliation Act, 1996 was considered but the said order is not conclusive
as it has not decided various other points that are required to be taken into
consideration under Section 48 of the 1996 Act. It is submitted that the
earlier order has taken care of Sections 48(b) and 48(d) but other issues
have not been touched and, accordingly, the said order cannot be treated to
be a res judicata inasmuch as the said order is only interlocutory in nature
and an interlocutory order cannot be treated as a res judicata when the
matter now is required to be finally decided on merits.
Although at this stage, the Court could have easily declined to
consider the objections raised at such a belated stage and find considerable
substance in the argument made on behalf of the award-holder that this
application is barred by issue estoppel, cause of action estoppel and
constructive res judicata, however, an opportunity was given to the
petitioner/applicant to argue with regard to the enforceability of the award.
On other points as I felt that if the award is contrary to public policy of India
it should not be enforced.
Before I deal with the objections raised in relation to the enforceability
of the award, a brief narration of facts necessary to understand and
appreciate the nature of objections are stated below.
The award-holder entered into a contract dated 25th October, 2010 for
sale of 15000 metric tons +/- 5% at Buyer''s option, Non Basmati Parboiled Rice 15% (Maximum) broken, 2009-10 or latest crop, Thailand origin at the
rate of USD 450 per metric ton. The contract contains stipulation that the
quantity would be final at the Port of loading as per official weight certificate
issued by SGS at the seller''s cost meaning thereby the award-holder. The
award-debtor under the contract was required to open an irrevocable,
confirmed, unrestricted letter of credit in US Dollar in favour of the award-
debtor within 5 working days from the date of signing of contract through
Standard Chartered Bank (India) for the value of the goods to be shipped
under the contract.
The contract is a FOB contract. The contract stipulates that 100%
value of the contracted cargo shall be payable on receipt of the shipping
documents by the L/C negotiating bank at 30 days sight. The contract
mentions about 16 shipping documents to be submitted for receiving
payment under the L/C. The contract in "Other Terms" provided that all
other terms and conditions not in contradiction with the stipulated terms of
the contract shall be governed by GAFTA 48 and disputes to be resolved by
Arbitration as per GAFTA 125 in London.
The goods were meant for Government of People''s Republic of
Bangladesh. In ''special instruction'' it was mentioned that "except invoice,
packing list and shipment, appropriation in all documents" consignment to
be shown as "to order" notifying "M/s. Director General of Food,
Government of People''s Republic of Bangladesh, 16 Abdul Ghani Road,
Dhaka". The buyer opened a Letter of Credit on 3rd November, 2010
through its banker Standard Chartered Bank and the same was communicated to the award holder on 5th November, 2010. On a request
being made on 5th December, 2010 by the award holder for amendments in
the contract and in the letter of credit, the terms of the contract was
amended on 7th December, 2010 by which the following amendment to the
parent contract was agreed upon:-
"1. Quantity Now to be read as 15000 Metric Tons - 5% more or less in Buyer''s option, final at loading as per official weight certificate issued by ISC at Seller''s cost.
Specifications Clause II - To be amended to 17 Pct Max I/O 15 Pct.
Clause IV - To be amended to 6 Pct. Max I/O 3 Pct in total.
All other specifications will be remain unchanged.
Payment Value @ US$ 440.00 per MT of the contracted cargo payable at 30 days after shipment date and balance amount @ US$ 10.00 per MT will be payable after receipt of quality inspection report of destination port.
Shipment By 31/12/2010
Documents Required Certificates under Sl. No.G, I, J & K issued by ISC are acceptable I/O existing."
The contract stipulates that the shipment shall be by 15th November,
2010. The original L/C dated 3rd November, 2010 mentioned date and
expiry of L/C as 21st December, 2010 and latest date of shipment as 30th
November, 2010 respectively. All the three shipments were made after 21st December, 2010. In order to extend the shipment both contract and L/C
were amended.
Under the amended contract dated 7th December, 2010, shipment was
to be made by 31st December, 2010. The buyer, accordingly, amended the
Letter of Credit on 9th December, 2010 by extending the period of shipment.
The validity period of the Letter of Credit after first amendment was 15th
January, 2011 and the latest date of shipment was mentioned as 31st
December, 2010. Within the validity period of the Letter of Credit the buyer
could manage to arrange for only two vessels. The first two shipments of
small quantity of goods were made on 27th December, 2010 and 31st
December, 2010. Since the third consignment could not be shipped, a
further amendment to the Letter of Credit was made on 31st December, 2010
by which the latest date of shipment was extended until to 15th January,
2011 with new date of expiry of L/C on 30th January, 2011. The validity of
the Letter of Credit thereafter was not extended neither the latest date of
shipment beyond the aforesaid dates.
Seller shipped the consignment as follows:
1,610.00 mt on board of MV Study Falcon on 27 December, 2010
3,430.00 mt on board of MV Genius Mariner on 31 December,
2010
8,689.55 mt on board of MV Tuman Gang [sic] on 17th January
2011
For each single shipment invoices had been issued by Sellers in
accordance with the addendum to the Contract displaying the first
instalments at each USD 440.00 per metric ton, totalling at USD
6,041,139.30, as follows:
Invoice No.2021C/2010/PB/LMJ dated 27 December 2010 for
USD 708,416.10
Invoice No.2021D/2010/PB/LMJ dated 31 December, 2010 for
USD 1,509,234.30
Invoice No.2021E/2011/PB/LMJ dated 17th January 2011 for USD
3,823,488.90.
On 17th January, 2017, the buyer arranged for a North-Korean Vessel,
namely, MV Tu Man Gang for shipment of 8689.55 MTs after the last date of
shipment expired on 15th January, 2011. At the time of the said loading,
there was no valid and subsisting Letter of Credit. The award-holder on 26th
January, 2010, informed the buyers to arrange for the remaining quantities
to be shipped against the contract and requested them to make arrangement
latest by 31st January, 2011 followed by an intimation by the sellers on 27th
January, 2011 to the buyers that the negotiating bank, namely, Standard
Chartered Bank, Bangkok declined to negotiate the documents related to
partial shipment of 8,698.55MT on the board of MV Tu Man Gan for the
reason that the said vessel is a North-Korean vessel. At this stage question
arose with regard to the extension of the Letter of Credit by amending Letter
of Credit including the latest date of shipment. On 26th January, 2011, the award-holder pointed out to the buyer that the Letter of Credit had expired
and it is at this stage, the buyers in view of the problem faced by sellers in
negotiating the documents requested the sellers on 27th January, 2011 to
present the export documents as per contractual terms to Bank of Baroda,
Kolkata. The buyers confirmed that they would accept the documents on
presentation. This consignment was not covered under the Letter of Credit.
This arrangement was confirmed by the award-debtor in an e-mail on 27th
January, 2011 stating that:-
"upon receipt of documents Bank of Baroda will send a SWIFT message to your bank in Bangkok confirming the acceptance of documents and payment thereof."
The buyers on 1st February, 2011 wrote to Bank of Baroda as under:-
"With reference to above, we understand that you have received the original shipping documents valued USD 3,823,488.90 from M/s. Sleepwell Industries Co. Ltd., Thailand for 8,689.55 MT of Non-Basmoti Parboiled Rice.
We hereby accept the documents under your import intimation Ref No.1152FIBC006711 dt.01/02/2011 and authorized you to remit USD 3,823,488.90 by debiting out current account equivalent in INR on maturity date, i.e. on 16/02/2011 under advice to us.
Please release the original shipping documents at the earliest."
The sellers received the message from the Bank of Baroda, Kolkata on
3rd February, 2011 stating that the collection bill of the seller for USD 3,823,488.90 has been accepted by the buyers. The buyers, however, did
not accept the sellers'' offer to take delivery of the remaining quantity of
about 2000 MT. The sellers, accordingly, informed the buyers on 4th
February, 2011 that the contract for the remaining quantities is foreclosed
and the contract should be treated as completed. The buyers, however, by
its e-mail dated 5th February, 2011 did not accept the decision of
cancellation of balance quantity and had agreed to establish fresh L/C for
the balance quantity of about 2000 MT. The buyer alleged that the cargo as
loaded on the vessel was of inferior quality for which their ultimate buyer
was not accepting the cargo. The buyers asked the sellers to depute their
representative to Mongla, Bangladesh to check the quality.
The buyers by their e-mail dated 8th February, 2011 asked for details
of the person visiting Mongla to check the quality. The buyer alleged that
the preliminary report on the quality is not satisfactory. The seller
responded to the said e-mail on the same day, that is, on 8th February, 2011
and asked for the report as to the exact nature of the complaint. The seller
on 10th February, 2011 informed the buyer that the surveyors have
confirmed by their e-mail dated 9th February, 2011 that the rice shipped
strictly conformed to the contractual specifications.
The required invoices for the amended balance payments at each USD
10.00 per metric ton, totalling at USD 137,148.20, were provided by sellers
as follows:
Invoice No.2021C/2010/PB/LMJ dated 15th February, 2011 for USD 16, 083.90
Invoice No.2021D/2010/PB/LMJ dated 15th February, 2011 for USD 34,265.70
Invoice No.2021E/2010/PB/LMJ dated 15th February, 2011 for USD 86,808.60
The sellers also reminded for the payment. The sellers on 15th
February, 2011 issued the invoices in respect of the balance payment of
2.22% in respect of the three shipments. On 15th February, 2011, the
sellers received a message from Bank of Baroda that they have been
informed by the buyers that they have prepared only 90% of the due
payment, that is, 90% of the invoice value of USD 3,823,488.90 to which the
sellers'' bank, that is, Bangkok Bank objected to in a return e-mail dated
16th February, 2011. The Bank of Baroda was requested to remit the
complete invoice amount. In between, on 14th February, 2011, the award-
holder agreed to accept provisional payment of 90% of the value of the
invoice amounting to USD 3,823,488.90 submitted to bank of Baroda and
balance 10% to be settled after inspection and finalization. LMJ was
requested to arrange to remit 90% funds to Bangkok Bank. On the same
date, another e-mail was sent by the seller to LMJ giving particulars of two
persons who would visit Mongla Port for carrying out the necessary
inspection. LMJ on receipt of the said communication, accordingly,
instructed his banker for release of payment. Ultimately, the seller received
90% payment of the invoice of USD 3,823,488.90 on 21st February, 2011.
The correspondence and e-mail both dated 14th February, 2011, however,
were not disclosed in the arbitration proceeding and serious exception was
taken by the petitioner in this proceeding for non-disclosure of the said two documents. The seller thereafter on 9th March, 2011 requested the buyer to
pay the balance of 10% to which the buyers replied the next date advising
sellers, inter alia, that also with the first two partial shipments, quality
problems did indeed arise. Nevertheless and so did buyer''s advice, a final
settlement would only be done upon finalization of the quality in
Bangladesh. Within the same message, the buyers informed the sellers that
the balance payment for MV Tu Man Gang would be effected as soon as the
final accounts of the Bangladesh would be received.
On 31st May, 2011, Buyers through their bank, the Bank of Baroda,
informed Sellers that the balance of 10% of the invoice in reference with the
shipment on board of MV Tu Man Gang will only be effected after completion
of a joint inspection of the landed cargo at the port of discharge.
On 3rd June 2011, Sellers through their bank, the Bangkok Bank,
replied that the weight and the quality were final at loading port Bangkok as
per certificate issued by the surveyor ISC nominated by Buyers themselves.
Subsequently, Sellers rejected a joint inspection in the country of
destination, i.e. Bangladesh.
Sellers on 10th June 2011 sent to Buyers a further reminder for
payment of the unpaid invoices. Only on 29th June 2011 Buyer replied and
stated, inter alia, that the goods shipped under the contract "were not of the
prescribed specification and the dead, damaged and discoloured grains were
in much excess of the maximum limit of 3% specified" in the contract.
Further, Buyers stated that both parties to the Contract agreed, at
least by Sellers email dated 4th February 2011 and by "mutual discussions
which had taken place" to a "discount of USD 10.00 per metric ton" and that
sellers would "reimburse" Buyers for "expenses and other miscellaneous
costs incurred" by Buyers " for effecting the final sale to" Buyers sub-buyers.
Sellers replied on 11th July 2011 and denied, inter alia, that the
"specification for dead, damaged and discoloured rice was restricted to a
maximum of 3% but rather at 6% by way of addendum to the contracts.
Sellers further denied within this message to Buyers that the rice
shipped was of inferior quality and that thus a quality report was shown to
Sellers. "such was irrelevant as it was provisional and subsequent."
Sellers on 28th July 2011 claimed arbitration and appointed Mr. R.
Barber as Arbitrator, Buyers failed to respond and Sellers requested GAFTA
to appoint an arbitrator on their behalf in accordance with GAFTA
Arbitration Rules 125. GAFTA duly appointed Mr. R. Eikel as second
Arbitrator on 22nd September, 2011.
On 25th June 2012 GAFTA appointed Mr. C. Debattista as the third
Arbitrator and Chairman of the Tribunal.
The first objection raised on behalf of the petitioner is that the
impugned award was induced and/or affected by fraud and, therefore, is in
conflict with the Public Policy of India. It is submitted that the Public Policy
of India has received consideration by which High Courts including the
Hon''ble Supreme Court means:- i) Fundamental policy of Indian law;
ii) Patent illegality going to the root of the matter;
iii) Wednesbury principle of reasonableness;
iv) Natural justice;
v) Non-judicial approach;
vi) Against terms of the contract.
In this regard reliance has been placed on the decisions of the Hon''ble
Supreme Court in Associate Builders Vs. Delhi Development Authority
reported at 2015 (3) SCC 49 Paragraphs 40 to 42 and Delhi
Development Authority Vs. R.S. Sharma and Co., New Delhi reported at
2008 (13) SCC 80 Paragraph 21.
The learned Senior Counsel has referred to the Explanation to Section
48(2) of the Arbitration and Conciliation Act, 1996 and submits that in view
of the suppression of two communications of the claimant both dated 14th
February, 2011, the said award is required to be declared null and void. It
is submitted that the two communications, one is by way of a letter dated
14th February, 2011 and e-mail of the same date, the claimant accepted that
they had sent inferior quality of rice and had promised that they would send
the representatives to destination Port in Bangladesh for joint inspection of
the consignment of rice. The existence of the said two documents although
is not in disputes by suppressing the said letter and the e-mail, the claimant
was emboldened to make false statement in Paragraph 19 of the claim
submission that states: "The sellers were under tremendous pressure as the payment of the invoice was not being released by the buyers despite the fact that they had received the cargo. The seller, therefore, under pressure agreed for release of 90% payment of the invoice of USD 3,823,488.90 which was received by them on 21st February, 2011."
The above statement is in conflict to the letter of February 14, 2011 by
which the claimant proposed and agreed that they will accept 90% payment
provisionally against their bill of exchange and the balance will be paid after
joint inspection and settlement of claim. However, as soon as 90% payment
was received by the claimant against the bill of exchange from Bank of
Baroda on 21st February, 2011 the claimant omitted to send their
representatives for joint inspection and finalization of the claim.
Suppression of the said letter and e-mail both dated February 14, 2011 is
an act of fraud upon the Arbitral Tribunal and it vitiates the award. In this
regard, reliance has been placed on Paragraph 5 of the decision of the
Hon''ble Supreme Court in S.P. Chengalvaraya Naidu Vs. Jagannath &
Ors. reported at (1994) 1 SCC 1.
The petitioner deliberately concealed from the Arbitral Tribunal that it
had not raised any invoice for payment of balance 2.22 of the agreed value of
the goods. On the contrary, in the claim submission at Paragraph 16, they
falsely represented before the Arbitral Tribunal that they have raised three
invoices for the balance 2.22% and enclosed fictitious copies of the non-
existent invoices to the claim submission. The claimant also suppressed
form the Tribunal that the claimant did not receive payment of the balance
2.22% under the subsisting letters of credit though the entire payment of 97.78% of the first two consignments was obtained by operation of letter of
credit.
The claimant did not raise any claim for payment of the balance 10%
from Bank of Baroda under the bill of exchange, because they avoided
holding of joint inspection and finalization at 10% and settlement after joint
inspection as agreed by the claimant by its letter and e-mail dated February
15, 2011. This letter of 15th February, 2011 was relied upon by the
claimant for misleading the Arbitral Tribunal into thinking that buyer had
instructed Bank of Baroda to release of 90% of the 3rd invoice without
mentioning that it was because the claimant''s agreement to accept 90%
payment of the 3rd invoice on the terms and conditions as confirmed by the
letter of 14th February, 2011. The claimant suppressed the letter dated 14th
February, 2011 and only disclosed the letter of 15th February, 2011 before
the Arbitral Tribunal with a view to mislead the Tribunal.
The claimant did not raise any invoice for the balance 2.22% of the
sale price payable under the L/C and balance 10% receivable under the Bill
of Exchange and hence no dispute could have arisen regarding balance
2.22% of the sale price of fictitious invoices and 10% of the 3rd invoice but
still obtained the ex parte award by suppression that there was no pre-
existing dispute regarding the same.
For the same amount a claim of 10% of the balance price of 3rd
shipment was made before the Arbitral Tribunal a suit has been filed being
Suit No.196 of 2011 against Bank of Baroda only and no leave has been
obtained to file a claim for the same amount from the Tribunal. The petitioner has deliberately suppressed on the Tribunal that parallel
proceedings are initiated for realization of the said amount in respect of an
alleged cause of action against the petitioner. The petitioner was also not
made a party in the said suit.
The award has been obtained by the claimant by suppression of
breach of the agreement as recorded in the letter of 14th February, 2011 of
the claimant that the balance 10% to be settled after inspection and
finalization by practicing fraud upon the Tribunal.
The second objection is that the Tribunal has made out a new case for
the parties what is impermissible in law.
The learned Senior Counsel has submitted that the seller did not even
contend before the Tribunal or in their claim submission that a certificate of
inspection report of the destination Port was to be procured by the buyer.
The case that the buyer was to produce certificate of inspection of the
destination port Bangladesh was not even made out in the claim submission
of the claimant. No dispute was referred to or raise even before the Tribunal
by the claimant that the buyer was to provide certificate of inspection of the
discharge port.
However, the Arbitral Tribunal proceeded on the basis that the buyer
was obliged to provide certificate of invoices of discharge port. The Tribunal
has made a new case for the parties, which is not permissible in law. The
Tribunal proceeds on a wrong assumption and has gone beyond the scope of
submission to arbitration. The award, therefore, is without jurisdiction. Another new case was made out by the Tribunal with regard to the
requirement of certificate of analysis. It is submitted that Arbitral Tribunal
made out a case that the buyers under clause 6.1 of GAFTA Sampling Rules
124 were obliged to provide certificate of analysis. It was not the case of the
claimant and even in the claim submission that under the GAFTA Sampling
Rules buyer was obliged to provide certificate of analysis. Even in the claim
submission it is not averred by the claimant that under GAFTA Sampling
Rules 124 the buyer was obliged to provide certificate of analysis. This new
case made out by the Arbitral Tribunal in paragraph 6.2.1 of the award is
also in violation of principles of natural justice. The buyer was never
informed that such new case would be made out by the Arbitral Tribunal in
their award.
The new cases made out by the Arbitral Tribunal were beyond the
scope of submission to arbitration and, accordingly, not enforceable under
Section 48(1)(c) of the Act.
The Tribunal has no jurisdiction to make out a new case or to
consider the dispute not raised by the claimant in their claim submission.
In this regard reliance is placed on Mathuradas Goverdhandass Vs.
Khusiram Benarshilal reported at 53 CWN 873 and Jasraj Inder Singh
Vs. Hemraj Multanchand reported at AIR 1977 SC 1011.
The third objection is that the award is perverse.
The Arbitral Tribunal''s uncalled for reliance on GAFTA Sampling
Rules 124 clause 6.1 is wholly perverse. The contract as amended and recorded in the award in Paragraphs 6, 15, 6.16 and 6.17 does not provide
that the buyer was to obtain quality inspection report of the destination port
and to hand over the same to the seller nor does the amendment provide
that if the quality inspection report of the destination port is not provided
that if the quality inspection report of the destination port is not provided by
the buyer, the seller will be entitled to balance amount of price. GAFTA
Sampling Rules 124 Clause 6.1 is not applicable in this case. GAFTA
Sampling Rules 124 does not provide that the buyer is to acquire the quality
inspection report. It was not even the case of the claimant that said GAFTA
Sampling Rules provide that a quality inspection report was to be provided
by the buyer.
It is submitted that in paragraph 6.18 the Tribunal has quoted GAFTA
Sampling Rules 124, without holding that the said clause 6.1 provided that
the certificate of analysis was to be sent to the seller by the buyer. The
finding in paragraph 6.20 that "with respect to clause 6.1 of the GAFTA
Sampling Rules 124 buyer was obliged to provide certificate of analysis" is
without any reasons and is not supported by paragraph 6.18 of the award.
It is not a case of interpretation of GAFTA Rules No.6.1 by the Tribunal, who
have not analysed or interpreted Clause 6.1 of the Rule. Suddenly, the
Tribunal have made an observation in paragraph 6.20, without any reason
in support of their assumption, which is not really a finding. It is totally
unreasonable, contradictory and wholly perverse.
The award is contrary to the terms of the agreement to be read with
Letters of Credit as required under English Law and, therefore, makes the award contrary to public policy. The award proceeds on the basis that the
buyer failed to forward the certificate.
The contract is governed by the English law. It is nowhere provided
that the buyer is to produce the certificate, but the correspondent L/C
amended contemporaneously with amendment of the Contract enjoin that
the quality analysis report is to be produced by the holder of L/C (the seller)
for receiving payment of the Balance amount. L/C was accepted by the
seller.
The Tribunal failed to apply its mind to the Letters of Credit which
was on record and also the Bill of Exchange. Non-consideration of material
on record vitiates the Award.
The Arbitral Award does not contain any reason for assuming that the
discharge port quality inspection report would be required to be furnished
by the buyer.
In short, obtaining an award for balance price without presentation of
quality inspection report of the destination port and without inspection and
finalization as proposed and agreed by the seller should shock judicial
conscience. The award is totally contrary to Wednesbury principle of
reasonableness and would shock judicial conscience.
The learned Senior Counsel has referred to the contract terms set out
at page 5 of the claim submission which reads:-
"all other terms/conditions not in contradiction with the above as per GAFTA Contract No.48."
The amendment of the contract is also admitted by the claimant in the
claim submission and also by the Tribunal in Paragraph 6.17 of the award.
There is no explanation, reason or justification given by the Arbitral
Tribunal on the basis of which it holds that the buyers were obliged to
provide the certificate of analysis. Clause 6.1 of the GAFTA Sampling Rules
No.124 nowhere provides that the buyers were obliged to provide the
certificate of analysis.
There is a complete non-judicial approach. The findings of the
Arbitral Tribunal in paragraphs 6.18, 6.20 and 6.22 is contradictory to its
own finding given in paragraphs 6.15, 6.16 and 6.17 of the award which
would demonstrate that the Tribunal lacked judicial approach in the matter.
The Arbitral Tribunal has failed to apply its mind and has not at all
considered that since GAFTA Contract No.48 is in contradiction with the
amended contract and the letter of credit, GAFTA Contract No.48 would not
be applicable in the instant case. Consequently, GAFTA Sampling Rules
No.124 would also be in applicable. Therefore, the inference drawn by the
Arbitral Tribunal in paragraphs 6.18, 6.20 and 6.22 of the award is on the
fact of its untenable as it is against the specific contract terms.
Furthermore the Arbitral Tribunal has omitted to consider that GAFTA
Sampling Rules if in contradiction with the terms of the contract would not
be applicable. The terms of the contract read with letter of credit clearly
mean that certificate of quality inspection report of the destination port was to be acquired by the seller. Accordingly, reliance on the GAFTA Sampling
Rules is perverse, contrary to the terms of the contract and void.
The fourth objection is that award suffers from patent illegality as it
fails to appreciate that it was the obligation of the buyer to provide the
certificate of analysis under Clause 6.1 of the GAFTA Sampling Rules 124 is
perverse, unreasonable and suffers from patent illegality and cannot be
sustained on the basis of the materials on record.
There is a patent illegality in the award which goes to the root of the
matter. There is no finding that the issuing bank wrongfully refused to
honour their L/C. There is no finding that the seller presented the
document as required under LC for payment of the balance 2.22%.
Therefore, the award is vitiated by patent illegality which goes to the root of
the matter. A seller would approach the buyer for payment only if the
issuing bank wrongfully refuses to honour the LC which was not claimed by
the seller in the claim submission.
The seller having not submitted the required agreed documents it is
required both under the contract and under the L/C cannot insist for
payment under the L/C. The non-submission of the required documents as
prayed between the parties would absolve the buyer from making any
payment in respect of the balance amount. The seller having not complied
with the terms cannot insist that notwithstanding such compliance either
the bank or the buyer would be liable to pay for the balance of amount. In
this regard, the learned Senior Counsel has relied upon the decision of the
House of Lords in Shamsher Jute Mills Ltd. v. Sethia (London) Ltd. reported at (1987) 1 Lloyds Law Report 388 at Pages 390-393 which
considers W.J. Alan & Co. v. El Nasr Export & Import Co. reported at
(1972) 2 All ER 127 and Ficom S.A. v. Sociedad Cadex Limitada
reported at (1980) 2 Llyod''s Law Report 188. Therefore, the award suffers
from patent illegality going to the root of the matter.
This illegality goes to the root of the award.
The learned Senior Counsel has, thus, concluded that it would be
evident from the aforesaid that the award is contrary to Public Policy of
India as envisaged under Section 48(2)(b) and Explanation therein.
Therefore, the award is not enforceable in India.
The learned Senior Counsel has relied upon the decision of the
Hon''ble Supreme Court in Oil and Natural Gas Corporation Ltd. Vs.
Western Geco International Ltd. reported at 2014 (9) SCC 263
Paragraph 38 in support of the contention that the objection with regard to
the enforceability of the award on the ground of public policy can be raised
even without any pleading. Although in the instant case, it is admitted that
the grounds of challenge on public policy may not have been properly
pleaded and not exactly in the manner in which the matter has been argued.
Per contra, Mr. Tilak Kumar Bose, the learned Senior Counsel
representing the decree-holder submits that the instant application is not
maintainable on the ground of res judicata estoppel, cause of action
estoppel and/or principles analogous thereto. It is submitted that the
public challenge to the enforceability of the foreign award as opposed to public policy is not as wide as Section 34 of the Arbitration and Conciliation
Act, 1996 as held in Shrilal Mahal Ltd. Vs. Progetto Grano SPA reported
at (2014) 2 SCC 433.
It is submitted that in Shrilal Mahal (supra) it has been categorically
held that the public policy grounds available for setting aside of the
domestic award under Section 34 are not the same "public policy grounds"
mentioned under Section 48 of the Arbitration and Conciliation Act, 1996.
Mr. Bose has requested this Court to consider the fundamental and
preliminary objections before considering the merits of the matter.
It is submitted that the contract is a FOB contract. The fundamental
basis of a FOB contract is that the seller loads the goods at the loading port
and thereafter the seller is not informed the respondents for the goods. The
moment, the goods are loaded on board the vessel, obligation of the seller
ceases. That is why in the list of "documents required" mentioned in the
contract, one fundamental document is missing, namely, the contract of
insurance. In FOB Contract, it is the obligation of the buyer to select the
vessel and have a contract of insurance having prepared. The Sleepwell was
the seller and the LMJ was the buyer of the goods. LMJ is causing delivery
of the goods to its ultimate buyer which is Government of Bangladesh.
Sleepwell has no privity with this ultimate buyer and for that reason there is
not even mentioned of a discharge port in the contract. Mr. Bose referred to
the various features of the original and amended contract and submits that
the buyer under the contract is to open a Letter of Credit. It is the
obligation of the buyer not only to have a credit opened but to ensure that such Letter of Credit is valid and subsisting. Mr. Bose has referred to the
pleadings in the statement of claim as well as the findings of the arbitral
tribunal in Paragraph 6.25 and Paragraph 6.26 to contend that no fresh
Letter of Credit was established for the balance quantity of 2000 MT in the
old contract. LMJ by the letter dated 5th February, 2011 informed the
Sleepwell that extension of existing L/C from Standard Chartered Bank was
not acceptable and that fresh L/C shall have contemplated for balance 2000
MT. This 2000 MT is the balance quantity that had remained undelivered
out of the contractual quantity of 15000MT. Mr. Bose has referred to the e-
mails dated 26th January, 2011 and 27th January, 2011 to show that it is an
admitted position that the Letter of Credit had expired and, accordingly, the
question of submitting any document to the negotiating banker under the
L/C even for the earlier of shipments covered by the Letter of Credit could
not and does not arise inasmuch as the third shipment is not covered by
any L/C but by the Bill of Exchange. Mr. Bose has emphasized on the
finding of the arbitral tribunal that the contract came to an end since no
new L/C was established after the latest date of shipment under the
amended L/C expired on 15th January, 2011 and the shipment was done on
17th January, 2017.
In responding a submission made on behalf of the applicant regarding
non-receipt of invoices it is submitted that the said issue is wholly irrelevant
inasmuch as LMJ has not filed any defence to the claim submission nor did
LMJ participate in the arbitration proceeding. If such a challenge had been
thrown by LMJ in arbitration certainly the claimant would have been called upon to answer such issues before the Arbitral Tribunal. The existence or
non-existence of the invoices was never an issue before the Arbitral
Tribunal. The claimant has in its possession an email message dated 25th
February, 2011 by which various invoices were again submitted by the
claimant. However, this being not an issue arising out of the award and
beyond the scope of the application under Section 48 of the Arbitration and
Conciliation Act, 1996, such documents has not been disclosed. If called
upon, the claimant is willing to disclose such documents. The arbitral
tribunal, however, has not relied upon the invoices at all. Instead, the
arbitral tribunal has passed the award on the basis of the value of the
goods. The total value of the goods was 450 USD per MT. The first three
invoices representing 97.78%, represented 440 USD per MT. The balance
three invoices represented 2.22% of the value of the goods and this
constituted balance 10 USD per MT.
Mr. Bose submits that the claim on account of bill of exchange is for
97.78% of value of goods loaded on MV Tu Man Gang. It is clear from the
contract as well as the amendment dated 7th December, 2010 that recovery
of 97.78% of value of goods was never dependant on any "Quality Inspection
Report", yet only 90% of 97.78% of the goods has been recovered from Bank
of Baroda. The balance claim of 10% was referred to arbitration and this
has been awarded along with balance 2.22% of the value of goods in respect
of all three shipments.
In responding to the arguments that the balance 2.22% of the price of
the goods in respect of all of the shipments could not have been awarded as the Letter of Credit was a complete discharge of payment and the seller
having agreed to present quality inspection report and having failed to do so
can no longer demand payment, it is submitted that there was no valid
Letter of Credit opened by the buyer under which the seller could have
obtained payment at least since January, 2011. The last date of shipment
was 15th January, 2011. The first two shipments were on 27th December,
2010 and 31st December, 2010. Under the contract payment of the first
instalment (440 USD per M.T.) was payable 30 days from the date of
shipment. Obviously, the balance USD 10 per MT was to be paid
subsequently after receipt of quality inspection report at destination port.
The claimant by several emails asked for valid Letter of Credit. Mr. Bose has
referred to the emails dated 26th January, 2011, 27th January, 2011, 4th
February, 2011 and 5th February, 2011.
In the meantime, the validity of the entire Letter of Credit by reason of
shipment on MV Tu Man Gang became questionable. It is LMJ who
suggested that the document should now be presented outside Letter of
Credit. By the time the original documents under MV Tu Man Gang in
respect of 97.78% were released, even the validity period of the Letter of
Credit, which was valid till 30th January, 2011, expired. It is preposterous
to argue that for MV Tu Man Gang, the documents relating to 97.78% of the
goods could not be negotiated under the Letter of Credit, but for the balance
2.22% of goods under the same shipment documents can be validly
negotiated under the same Letter of Credit. Similarly, by the time the
second instalment i.e. 2.22% of the value of goods for the first two shipments could be realized under the Letter of Credit, dispute with regard
to the Letter of Credit had already arisen. Even the validity period of Letter
of Credit expired on 30th January, 2011.
The arbitral tribunal has correctly, therefore, not referred to the terms
of the Letter of Credit. The arbitral tribunal was aware of the fact that the
shipment period was till 15th January, 2011 and that shipment on MV Tu
Man Gang was done after last date of shipment. The discussions and
findings of the arbitral tribunal, therefore, are correctly based on
construction of the contract.
It is submitted that it is the buyer''s obligation to furnish quality
inspection report at the destination port. The construction of the contract
will show that a FOB seller never has any obligation at a destination port. It
is pertinent to mention that from the contract itself, it would appear that the
documents which were to be furnished by the seller were all related to the
loading Port. The contract of insurance was on account of LMJ
International Ltd. The risk in the goods had passed to LMJ the moment the
goods were loaded at the Load Port by the seller. Thereafter, it was between
LMJ arranged for shipment to the Port in Bangladesh. It was the choice of
LMJ. The moment LMJ on 1st February, 2011 accepted the bill of exchange
and asked for release of export documents and finally got the documents,
the property in the goods were transferred to LMJ. The claimant retained no
right, title and interest in respect of the goods. In fact, LMJ caused delivery
to another third party, namely, Government of Bangladesh. It is, in this context, submitted that it has to be examined as to whose obligation it was
to furnish "Quality Inspection Report" at the destination Port.
The fact that it was the obligation of the buyer to provide the Quality
Inspection Report at the discharge Port is also evident from the documents
on record. LMJ has never furnished the final Quality Inspection Report at
the discharge Port. The attention of this Court is drawn to the letter of
Bangkok Bank dated 5th June, 2011, the letter of Sleepwell dated 10th June,
2011 and its reply by LMJ dated 29th June, 2011. It is submitted that the
arbitral tribunal on interpretation of the contract at Paragraph 6.8 held that
no Quality Inspection Report has been presented by the buyers despite
various reminders from sellers. This finding of the arbitral tribunal cannot
be faulted.
With regard to the composition of the Arbitral Tribunal the learned
Senior Counsel has relied on the findings arrived at by this Court earlier in
the order dated 4th December, 2014 by which it was held that the
composition of the Arbitral Tribunal does not suffer from any infirmity. It is
submitted that this finding is final and cannot be reopened in this
application.
However, he has submitted that the notice invoking the arbitration is
dated 28th July, 2011. The email referred to in the said letter is
lmjajit1@gmail.com. Receipt of this email is not disputed. There is yet
another letter dated 28th July, 2011. The letter relates to the second
contract, but there is a similar one for the first contract which has not been
annexed. The said letter is addressed to lmjajit1@gmail.com. The letter specifically refers to Rule 3.2(a) and (b) of the GAFTA Rules, 125 and
appointment of Mr. R.A. Barber as Arbitrator on behalf of the claimant. This
letter is also not disputed by LMJ. In fact, Paragraph 31 and 32 of the
application reads as follows:
"31. By a cryptic letter dated 28th July, 2011, the award holder informed the petitioner.....
By a letter also dated 28th July, 2011, the award holder purported to appoint one R.A. Barber...."
It is submitted that the allegation of LMJ that the letter dated 23rd
August, 2011, was not received is without any basis and no credible
evidence is forthcoming. By the letter dated 23rd August, 2011, GAFTA
Tribunal was reminded that the requisite nine day period mentioned in Rule
3.2(b) of the GAFTA Rules had expired and that the arbitrator on behalf of
LMJ had to be appointed. A copy of the said letter was also sent to LMJ at
the same email address.
Rule 20(3) of GAFTA Rules states that for the purpose of the GAFTA
Rules, the date when the ''nine consecutive days'' should start will not be
taken into account. Thus, even after 28th July, 2011, the nine consecutive
days thereafter expired on 6th August, 2011. After 6th August, 2011 the
claimant became entitled to request GAFTA to appoint arbitrator on behalf
of LMJ. By the letter dated 23rd August, 2011, the claimant requested
GAFTA to appoint arbitrator on behalf of LMJ since the requisite nine day
period had already expired.
The subsequent letter dated 19th September, 2011 also addressed at
the said email address, lmjajit1@gmail.com, is not a notice under Rule 3.3 of
the GAFTA Rules. Necessary request to GAFTA had already been made on
23rd August, 2011. The subsequent letter dated 19th September, 2011 was
merely a reminder particularly since the ex parte order of injunction which
LMJ had obtained in the Civil Suit had been vacated on 9th September,
2011. Rule 20 of the GAFTA Rules has no manner of application so far as
the letter dated 19th September, 2011 is concerned. The letter dated 19th
September, 2011 was not issued "pursuant to these rules".
Mr. Bose has submitted that the objection to enforcement of the
award was rejected by the order dated 4th December, 2014. LMJ raised
various issues regarding enforcement and chose not to raise various other
issues, some of which have been argued presently. There are other issues
which still remain dormant in the section 48 application which were neither
raised on 4th December, 2014 nor during the course of argument of the
present application.
The fact that objection regarding "enforcement" was being considered
and had been rejected on 4th December, 2014 has been clarified in a
subsequent order dated 17th March, 2015. From the order dated 4th
December, 2014, a Special Leave Petition was filed which was rejected on
27th February, 2015. In the Special Leave Petition, LMJ always treated the
order dated 4th December, 2014 as disposing of objections regarding
enforcement.
A Review Petition was filed. In the Memorandum of Review also LMJ
treated the order dated 4th December, 2014 as disposing of objection
regarding enforcement. The order dismissing the review petition is dated 8th
June, 2015. The words ''maintainable'' and ''enforcement'' both, however,
appears in the order dated 4th December, 2014 and LMJ now wants to
contend that enforceability was not decided on 4th December, 2014. It is
pertinent to mention that the word ''maintainable'' does not appear anywhere
in Section 48 and the only two relevant words are ''recognition'' and
''enforcement''. In any event, LMJ is estopped from contending that the
objection regarding enforceability was not considered on 4th December,
2014.
In distinguishing the decisions relied upon by the applicant on the
question of res judicata it is submitted that it is preposterous to argue that a
matter regarding enforceability which has been decided by a learned Single
Judge against which Special Leave Petition and review have been dismissed
will not attain finality. Regarding whether principles of res judicata apply, it
is submitted that even from the guidelines of res judicata outlined in Syed
Mohd. Salie Labbai & Ors. Vs. Mohd. Hanifa & Ors. reported at (1976) 4
SCC 780 and the four guidelines mentioned therein, the present application
is barred under the principles of res judicata.
The two cases, namely, Kanshi Ram Vs. Bansi Lal reported at AIR
1977 HP 61 (Paragraphs 6 and 7) and Sm. Muktakesi Dawn & Ors. Vs.
Haripada Mazumdar & Anr. reported at AIR 1988 Cal 25 (Paragraph 6) were all cases involving orders of injunction for which principles of res
judicata usually do not apply.
Apart from the question of res judicata, the application is also barred
under the principles of estoppel. Principles of estoppel may be similar to
that of res judicata, although the strict requirements of res judicata may not
apply to principles of estoppel. It is barred by Issue Estoppel and Cause of
Action Estoppel. Issue Estoppel means, if an issue has been raised, the
unsuccessful party cannot raise the same issue again. Cause of Action
Estoppel means, if a party had a particular cause of action and has
exhausted that cause of action or failed to exhaust the same, then the same
cause of action cannot be agitated later. A brief guideline of Issue Estoppel
and Cause of Action Estoppel is given by the Apex Court in Bhanu Kumar
Jain Vs. Archana Kumar & Anr. reported at (2005) 1 SCC 787 as also by
the English Courts in Fidelitas Shipping Co. Ltd. Vs. V/O Exportchleb
(1966) 1 QB 630 and SCF Finance Company Ltd. Vs. Masri reported at
1987 (1) All E.R. 194. It is submitted that the present application under
section 48 is hit both by the principles of with "Issue Estoppel" and "Cause
of Action Estoppel".
LMJ had already resisted enforcement by raising the issue that the
award was not enforceable. There were many sub-issues under this. LMJ
on 4th December, 2014 raised some issues and chose not to raise other
issues. The same even applies now. There are many other grounds
mentioned in the present section 48 application which have not been raised.
If the law is that LMJ can go on raising new grounds whenever it wants to, then there will be no finality in the declaration that the award is enforceable.
This cannot be permitted.
It is argued that the fundamental issue is, whether the award is
enforceable or not. It has been declared to be enforceable on 4th December,
2014 and the LMJ is estopped from raising this issue again.
When an application for enforcement of a foreign award is filed, a
party who wishes to contest the enforceability of the said award has a cause
of action and this cause of action is to contest the enforceability. This he
may do merely by filing an affidavit or by filing an application or resisting
orally the execution application. The question is whether LMJ exhausted
this cause of action or not. If LMJ has exhausted this cause of action then
there is cause of action estoppels operating against LMJ.
Mr. Bose submits that the three English judgments referred to by LMJ
in support of the proposition that by reason of a valid Letter of Credit
opened by buyer LMJ, payment obligation has been discharged by the buyer
and the seller cannot look for payment other than under the Letter of Credit
are academic. Firstly, there was no valid Letter of Credit inasmuch as the
valid date of the Letter of Credit and the last date of shipment was 15th
January, 2011 whereas the bulk shipment of over 8000 MT was done on MV
Tu Man Gang only on 17th January, 2011 after the expiry of the last date of
shipment. By the time the goods were discharged and Quality Inspection
Report at the discharge port could have been made available by the buyer,
the validity of the Letter of Credit expired. In fact, it was the buyer''s
obligation to open the Letter of Credit. The buyer knew that documents could not be negotiated under the Letter of Credit. Presentation of
documents under the Letter of Credit, therefore, was not even a possibility.
In Shamsher Jute Mills Ltd. (supra) and Ficom S.A. (supra) can
both be distinguished by one sentence, viz. "the buyer had not taken
delivery of the goods" in such cases. A buyer who takes delivery of goods is
obliged to pay for the value of the goods.
Mr. Bose has referred to two standard and celebrated Books on Letter
of Credit, namely:-
(a) Jack on Documentary Credits where specifically mentioned the
situation "where the buyer has received the goods", and
(b) Guttridge and Megrah''s Laws of Bankers Commercial Credit where
the entire discussion on the various case laws referred to by LMJ have
been discussed and the buyer''s frustration of a Letter of Credit and
the consequence of breach are outlined.
The disputes regarding whether a Letter of Credit payment is
conditional or absolute arises only when there is a valid and subsisting
Letter of Credit opened by the buyer. This has not happened in this case.
Secondly, such issues arise only when a buyer refuses to accept delivery of
goods on the ground that documents are not in conformity with the Letter of
Credit. It is preposterous to argue that if a buyer accepts goods, it will not
make payment raising flimsy arguments like it was the obligation of seller to
hand over documents. Mr. Bose emphasized that in the instant case, it is on the basis of representation of LMJ that without receiving any payment,
export documents of MV Tu Man Gang were released and handed over.
Mr. Bose has distinguished the judgments relied upon by the
petitioner in relation to public policy by submitting that the said judgments
are all based on the definition of "Public Policy" appearing under Section 34
of the Arbitration and Conciliation Act, 1996 in respect of the domestic
award. The term "Public Policy" is to be given a narrow meaning when used
and applied in the context of a foreign award. Mr. Bose has referred to
Shrilal Mahal Ltd. (supra) and submits that the principles of public policy
applied in relation to foreign award governed by the Foreign Award
(Recognition and Enforcement) Act, 1961 had been extended by the Hon''ble
Supreme Court in the context of foreign awards under the Arbitration and
Conciliation Act, 1996. It is submitted that the same view has been
reiterated by Justice Sanjib Banerjee in an unreported decision in
Canadian Commercial Corporation Vs. Coal India Limited being G.A.
No.3547 of 2013 with E.C. No.281 of 2013 dated 21st September,
2016.
It is submitted that the judgment in S.P. Chengalvaraya Naidu
(supra) cannot assist the petitioner as a party who does not choose to
appear in the arbitration proceedings cannot raise such grounds of fraud.
The fact that Statement of Claim was served and received by LMJ is
admitted. If LMJ was so concerned about suppression it should have
pointed out the same to the Arbitral Tribunal.
Mr. Bose submits that LMJ not having contested the Arbitration
proceeding and filed the written statement is estopped from contending that
documents have been suppressed and such suppression amounts to fraud.
In any event, there has been no suppression. The letter dated 14th
February, 2011 clearly states that Sleepwell was accepting 90% of the Bill of
Exchange amount provisionally and the same was also conveyed to its
bankers who was initially insisting on 100% payment. It is only when
Sleepwell requested his banker 90% of the Bill of Exchange provisionally
from the bank of Baroda, that bank of Baroda released 90% of the Bill of
Exchange amount. The relevant documents have been disclosed in the
statement of claim.
I have considered the rival contentions.
Section 48 of the 1996 Act materially corresponds to Section 7 of the
Foreign Awards (Recognition and Enforcement) Act, 1961. Section
48(1)(a)(b)(c)(d) and (e) of the Act corresponds to provisions of Section
103(2)(a)(b)(c)(d)(e) and (f) respectively of the English Arbitration Act, 1996.
Sub- sections 48(2) and 48(3) of the Act correspond to sub- sections 103(2)
and 103(5) respectively of the English Arbitration Act. For the sake of
convenience and brevity Section 48 of the 1996 Act is set out below:-
"48. Conditions for enforcement of foreign awards.--
(1) Enforcement of a foreign award may be refused, at the request of the party against whom it is invoked, only if that party furnishes to the court proof that--
(a) the parties to the agreement referred to in section 44 were, under the law applicable to them, under some incapacity, or the said agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law of the country where the award was made; or
(b) the party against whom the award is invoked was not given proper notice of the appointment of the arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
(c) the award deals with a difference not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration: Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, that part of the award which contains decisions on matters submitted to arbitration may be enforced;
or
(d) the composition of the arbitral authority or the arbitral procedure was not in accordance with the agreement of the parties, or, failing such agreement, was not in accordance with the law of the country where the arbitration took place; or
(e) the award has not yet become binding on the parties, or has been set aside or suspended by a competent authority of the country in which, or under the law of which, that award was made.
(2) Enforcement of an arbitral award may also be refused if the Court finds that--
(a) the subject-matter of the difference is not capable of settlement by arbitration under the law of India; or
(b) the enforcement of the award would be contrary to the public policy of India. Explanation.--Without prejudice to the generality of clause (b) of this section, it is hereby declared, for the avoidance of any doubt, that an award is in conflict with the public policy of India if the making of the award was induced or affected by fraud or corruption.
(3) If an application for the setting aside or suspension of the award has been made to a competent authority referred to in clause (e) of sub- section (1) the Court may, if it considers it proper, adjourn the decision on the enforcement of the award and may also, on the application of the party claiming enforcement of the award, order the other party to give suitable security."
The grounds of challenge enumerated in the aforesaid section are
meant to be construed narrowly and do not permit review of the foreign
award on merits. The Courts are not expected in proceedings to re-apprise
and re-appreciate the evidence. In Shrilal Mahal Ltd. (supra) in paragraph
45 of the report, the Hon''ble Supreme Court has specifically held that
Section 48 of the 1996 Act does not give an opportunity to have a "second
look" at the foreign award in the award enforcement stage. The scope of
inquiry under Section 48 does not permit review of the foreign award on
merits. Procedural defects (like taking into consideration inadmissible
evidence or ignoring/rejecting the evidence which may be of binding nature)
in the course of foreign arbitration do not lead necessarily to excuse an
award from enforcement on the ground of public policy.
The scope of "Public Policy" in relation to enforcement of a foreign
award was considered in Renusagar Power Company vs. General Electric
Company reported at 1990 (92) Bom. L.R. 70, paragraphs 109 to 113.
In Renusagar (supra) the award was challenged on the ground that it
granted interest on interest and awarded heavy costs not entirely incurred
in arbitration proceedings. It was contended that allowing these claims is contrary to law. The Division Bench was considering whether the
enforcement of an award which grants compound interest is contrary to our
public policy. It was held that the challenge to enforcement of the foreign
award on the ground of public policy should receive a narrow interpretation.
It would not be enough to show that the award is contrary to our laws. The
Hon''ble Division Bench of the Bombay High Court made a distinction
between what is contrary to public policy and what is contrary to our laws.
The said decision accepts the observation of the United States Court of
Appeals, Second Circuit in Parsons & Wittemore Overseas Inc. Vs.
RAKTA reported at 508F 2d 969 (1974) that the public policy defence
should be construed narrowly and enforcement may be denied only where
enforcement, would "violate the forum State''s most basic notions of morality
and justice". The function of the Court basically would be the guardian of
the "fundamental moral convictions or policies of the forum". Thereafter the
Hon''ble Division Bench discussed the scope of public policy in the following
words:-
"80. The Courts, however, will recognize only public policy as embodied in the Constitution, the laws and judicial decisions. There may be matters of public policy which are not embodied in laws or judicial decisions or the Constitution. The Courts will not take cognisance of such matters. But what is contrary to law may not necessarily be contrary to public policy. It is only when a law embodies public policy that its violation will lead to an action which is contrary to public policy.
In the case of ( Murlidhar Agarwal v. State of Uttar Pradesh ), reported in A.I.R. 1974 S.C. 1624 the Supreme Court considered the public policy aspect of the Rent Control legislation. The Supreme Court has observed (pg. 28):
"The expression ''public policy'' has an entirely different meaning from ''policy of the law'' and one much more extensive............... It seems clear that the conception of public policy is not only now quite distinct from that of the policy of law but has in fact always been so except in some exceptional instances of confusion which have had no substantial effect on the general course of authority.
X X X X X
''public policy'' has been defined by Winfield as a principle of judicial legislation or interpretation founded on the current needs of the community."
In the case of ( Gherulal Parakh v. Mahadeodas Mairye ), reported in A.I.R. 1959 S.C. 781 the Supreme Court considered whether a wagering contract is contrary to public policy. It held that "the common law of England and that of India have never struck down contracts of wager on the ground of public policy; indeed they have always been held to be not illegal notwithstanding the fact that the statute declared them void" It said that there is no definite head or principle of public policy evolved by Courts or laid down by precedents which would directly apply to wagering contracts. Even if it is permissible for Courts to evolve a new head of public policy under extraordinary circumstances giving rise to incontestable harm to the society, wager is not one of such instances of exceptional gravity, for it has been recognized for centuries and has been tolerated by the public and the State alike. Applying the same principle to compound interest, one can say that granting of compound interest has been tolerated in several types of cases and the Courts have not evolved any public policy ground on which awarding of compound interest by the arbitrators can be invalidated. The Supreme Court in the above case observed at page 792 -
"The doctrine, as Lord Atkin remarked in a leading case, "should only be invoked in clear cases in which the harm to the public is substantially incontestable, and does not depend upon the idiosyncratic inferences of a few judicial minds.
X X X X X
.... ''public policy'', like any other branch of the Common Law, ought to be and I think is governed by the judicial use of precedents. If it is said that rules of public policy have to be moulded to suit new conditions of a changing world, that is true: but the same is true of the principles of the Common Law generally."
In Halsbury''s Laws of England, 3rd Edn. Vol. 8, pg.130, it is said that - "Any agreement which tends to be injurious to the public or against the public good is void as being contrary to public policy... It seems however that this branch of the law will not be extended. The determination of what is contrary to the so-called policy of the law necessarily varies from time to time. Many transactions are upheld now which in a former generation would have been avoided as contrary to the supposed policy of the law. The rule remains, but its application varies with the principles which for the time being guide public opinion."
In the present case, the awarding of compound interest by the arbitrators cannot be said to violate any public policy of this country. In the first place, there are several types of cases where even Courts award compound interest e.g. if there is an agreement between the parties to this effect. In fact, in all banking transactions which the Courts enforce the banks invariably charge on loans granted by them compound interest not merely with interest compounded annually but much more frequently such as every quarter. All these agreements are enforced by Courts and these have not been held as void on account of being contrary to any public policy. Had there been any public policy prohibiting charging of compound interest, the parties could not have, by an agreement between them, opted out of a matter, of public policy."
In an appeal from the said judgment by Renusagar, the Hon''ble
Supreme Court upheld the judgment of the Division Bench. The decision is
reported at AIR 1994 SC 860 (Renusagar Power Co. Ltd. Vs. General
Electric Co.). It was held that the defence of public policy should be
construed narrowly. It could be seen from the judgment that violation of the
Foreign Exchange Act and disregarding orders of superior courts in India
would be regarded as being contrary to the fundamental policy of Indian
law. In this context reference may be made to Paragraphs 50, 51, and 63 to
66 of the said report. The said paragraphs read:-
"50. In the field of private international law, courts refuse to apply a rule of foreign law or recognise a foreign judgment or a foreign arbitral award if it is found that the same is contrary to the public policy of the country in which it is sought to be invoked or enforced. The English courts follow the following principles:
"Exceptionally, the English court will not enforce or recognise a right conferred or a duty imposed by a foreign law where, on the facts of the particular case, enforcement or, as the case may be, recognition, would be contrary to a fundamental policy of English law. The court has, therefore, refused in certain cases to apply foreign law where to do so would in the particular circumstances be contrary to the interests of the United Kingdom or contrary to justice or morality." (See : Halsbury''s Laws of England, 4th Edn., Vol. 8, para 418.)
A distinction is drawn while applying the said rule of public policy between a matter governed by domestic law and a matter involving conflict of laws. The application of the doctrine of public policy in the field of conflict of laws is more limited than that in the domestic law and the courts are slower to invoke public policy in cases involving a foreign element than when a purely municipal legal issue is involved. (See : Vervaeka v. Smith10; Dicey & Morris, The Conflict of Laws, 11 th Edn., Vol. I p. 92; Cheshire & North, Private International Law, 12th Edn., pp. 128- 129). The reason for this approach is thus explained by Professor Graveson:
"This concern of law in the protection of social institutions is reflected in its rules of both municipal and conflict of laws. Although the concept of public policy is the same in nature in these two spheres of law, its application differs in degree and occasion, corresponding to the fact that transactions containing a foreign element may constitute a less serious threat to municipal institutions than would purely local transactions." (R.H. Graveson : Conflict of Laws, 7th Edn., p. 165).
In view of the absence of a workable definition of "international public policy" we find it difficult to construe the expression "public policy" in Article V(2)(b) of the New York Convention to mean international public policy. In our opinion the said expression must be construed to mean the doctrine of public policy as applied by the courts in which the foreign award is sought to be enforced. Consequently, the expression ''public policy'' in Section 7(1)(b)(ii) of the Foreign Awards Act means the doctrine of public policy as applied by the courts in India. This raises the question whether the narrower concept of public policy as applicable in the field of public international law should be applied or the wider concept of public policy as applicable in the field of municipal law.
Keeping in view the object underlying the enactment of the Foreign Awards Act, this Court has also favoured a liberal construction of the provisions of the said Act. In Renusagar case I it has been observed: (SCC p. 723, para 50)
"It is obvious that since the Act is calculated and designed to subserve the cause of facilitating international trade and promotion thereof by providing for speedy settlement of disputes arising in such trade through arbitration, any expression or phrase occurring therein should receive, consisting with its literal and grammatical sense, a liberal construction." (p. 492)
This would imply that the defence of public policy which is permissible under Section 7(1)(b)(ii) should be construed narrowly. In this context, it would also be of relevance to mention that under Article I(e) of the Geneva Convention Act of 1927, it is permissible to raise objection to the enforcement of arbitral award on the ground that the recognition or enforcement of the award is contrary to the public policy or to the principles of the law of the country in which it is sought to be relied upon. To the same effect is the provision in Section 7(1) of the Protocol & Convention Act of 1837 which requires that the enforcement of the foreign award must not be contrary to the public policy or the law of India. Since the expression "public policy" covers the field not covered by the words "and the law of India" which follow the said expression, contravention of law alone will not attract the bar of public policy and something more than contravention of law is required.
Article V(2)(b) of the New York Convention of 1958 and Section 7(1)(b)(ii) of the Foreign Awards Act do not postulate refusal of recognition and enforcement of a foreign award on the ground that it is contrary to the law of the country of enforcement and the ground of challenge is confined to the recognition and enforcement being contrary to the public policy of the country in which the award is set to be enforced. There is nothing to indicate that the expression "public policy" in Article V(2)(b) of the New York Convention and Section 7(1)(b)(ii) of the Foreign Awards Act is not used in the same sense in which it was used in Article 1(c) of the Geneva Convention of 1927 and Section 7(1) of the Protocol and Convention Act of 1937. This would mean that "public policy" in Section 7(1)(b)(ii) has been used in a narrower sense and in order to attract to bar of public policy the enforcement of the award must invoke something more than the violation of the law of India. Since the Foreign Awards Act is concerned with recognition and enforcement of foreign awards which are governed by the principles of private international law, the expression "public policy" in Section 7(1)(b)(ii) of the Foreign Awards Act must necessarily be construed in the sense the doctrine of public policy is applied in the field of private international law. Applying the said criteria it must be held that the enforcement of a foreign award would be refused on the ground that it is contrary to public policy if such enforcement would be contrary to (i) fundamental policy of Indian law; or (ii) the interests of India; or (iii) justice or morality.
V. Is the award contrary to public policy of India?"
The aforesaid decision was considered in Shrilal Mahal Ltd. (supra).
In the said decision it was held that the expression "Public Policy of India" in
Section 48(2)(b) has the same import as that of "Public Policy" in Section
7(1)(b)(ii) of Foreign Awards (Recognition and Enforcement) Act, 1961. The
Hon''ble Supreme Court held that contravention of law alone would not attract bar of public policy and something more than contravention of law is
required to be established to resist enforcement of a foreign award as
contrary to public policy of India. After considering the decisions in
Renusagar (supra) and ONGC Ltd. Vs. Saw Pipes Ltd. reported at (2003) 5
SCC 705, it is stated:-
"26. From the discussion made by this Court in Saw Pipes in paragraph 18, paragraph 22 and paragraph 31 of the Report, it can be safely observed that while accepting the narrow meaning given to the expression "public policy" in Renusagar in the matters of enforcement of foreign award, there was departure from the said meaning for the purposes of the jurisdiction of the Court in setting aside the award under Section 34.
In our view, what has been stated by this Court in Renusagar with reference to Section 7(1)(b)(ii) of the Foreign Awards Act must equally apply to the ambit and scope of Section 48(2)(b) of the 1996 Act. In Renusagar it has been expressly exposited that the expression "public policy" in Section 7(1)(b)(ii) of the Foreign Awards Act refers to the public policy of India. The expression "public policy" used in Section 7(1)(b)(ii) was held to mean "public policy of India". A distinction in the rule of public policy between a matter governed by the domestic law and a matter involving conflict of laws has been noticed in Renusagar3. For all this there is no reason why Renusagar should not apply as regards the scope of inquiry under Section 48(2)(b) . Following Renusagar3, we think that for the purposes of Section 48(2)(b), the expression "public policy of India" must be given narrow meaning and the enforcement of foreign award would be refused on the ground that it is contrary to public policy of India if it is covered by one of the three categories enumerated in Renusagar3. Although the same expression ''public policy of India'' is used both in Section 34 (2(b)(ii) and Section 48(2)(b) and the concept of ''public policy in India'' is same in nature in both the Sections but, in our view, its application differs in degree insofar as these two Sections are concerned. The application of ''public policy of India'' doctrine for the purposes of Section 48(2)(b) is more limited than the application of the same expression in respect of the domestic arbitral award.
We are not persuaded to accept the submission of Mr. Rohinton F. Nariman that the expression "public policy of India" in Section 48(2)(b) is an expression of wider import than the "public policy" in Section 7(1)(b)(ii) of the Foreign Awards Act. We have no hesitation in holding that Renusagar must apply for the purposes of Section 48(2)(b) of the 1996 Act. Insofar as the proceeding for setting aside an award under Section 34 is concerned, the principles laid down in Saw Pipes1 would govern the scope of such proceedings.
We accordingly hold that enforcement of foreign award would be refused under Section 48(2)(b) only if such enforcement would be contrary to (i) fundamental policy of Indian law; or (2) the interests of India; or (3) justice or morality. The wider meaning given to the expression "public policy of India" occurring in Section 34(2)(b)(ii) in Saw Pipes1 is not applicable where objection is raised to the enforcement of the foreign award under Section 48(2)(b) .
It is true that in Phulchand Exports, a two-Judge Bench of this Court speaking through one of us (R.M. Lodha, J.) accepted the submission made on behalf of the appellant therein that the meaning given to the expression "public policy of India" in Section 34 in Saw Pipes1 must be applied to the same expression occurring in Section 48(2)(b) of the 1996 Act. However, in what we have discussed above it must be held that the statement in paragraph 16 of the Report that the expression "public policy of India used in Section 48(2)(b) has to be given a wider meaning and the award could be set aside, if it is patently illegal" does not lay down correct law and is overruled."
It is pertinent to note that the agreement which contains arbitration
clause is not in dispute. It is also undisputed that the buyers have accepted
the goods. The buyer in spite of notice of the arbitration has failed to
participate. The attempt by the buyer to resist commencement of the
arbitration proceeding has also failed. The buyers now want to contend that
the award is vitiated by reason of non-disclosure of the letter dated 14th
February, 2011.
In my view, it is not open for a party who has consciously avoided a
proceeding and did not participate in the arbitration proceeding to allege at
the stage of enforcement that the award is vitiated by fraud by non-
disclosure of a document. It was incumbent upon the buyer to respond to
the several notices issued by the Tribunal and to submit its defence.
Although, the said letter may not have been produced but subsequent
correspondence between the parties were disclosed which clearly shows that
the claimant buyer has categorically denied its obligation to produce any
quality inspection report at the port of destination. The Tribunal was
conscious of the fact that payment was refused in view of alleged failure by
the seller to produce the quality inspection report at the port of destination
and dealt with the issue and arrived at a finding that the seller is not
responsible. The Tribunal has the jurisdiction to decide the issue and has
decided the issue in one way or the other. Interpretation of a contract is a matter for the arbitrator to determine, even if it gives rise to determination of
a question of law. Arbitration is consensual and some amount of laxity
should be given while scrutinizing an award. A sense of informality is
attached to such proceeding. It cannot be scrutinized with an Eagle''s eye or
as an appellate authority. The objection to enforcement of a foreign award is
extremely limited. Moreover, in view of the order passed by the Division
Bench in refusing to pass any order of injunction restraining
commencement and/or continuation of the arbitration proceedings it cannot
be said that the award was passed in violation of any order passed by a
superior Court. The relevant observations of the Division Bench in this
regard are:-
"The intention of the parties to have their disputes resolved by arbitration cannot be doubted. The parties have entered into such contract with their eyes wide open. They have decided that all disputes are to be resolved, adjudicated and decided by arbitral tribunal to be constituted under the GAFTA Rules. The principal ground for avoiding the said Tribunal is of forum inconvenience. The additional grounds appeared to be that there is no agreement between the plaintiff and the defendant to refer any dispute arising out of the said contract to arbitration either as per GAFTA Rules, 125 in London or otherwise. In deciding the said issue, the reference is required to be made to the contract containing such arbitration clause. There cannot be any dispute that the obligation to make payment or avoidance of any such payment is arising out of a transaction covered by the contract which contains the arbitration the arbitration clause.
In the instant case, there is no dispute that the said contract containing arbitration clause has been validly and duly executed by the parties. The ground to resist the said arbitration is that it involves prohibitive costs. The appellant was not compelled to execute the said agreement. The appellant precisely knew at the time of execution of the contract that in the event of any dispute arising out of the said contract, it would be governed by the GAFTA Arbitration Rules, 125. In absence of any demonstrable injustice or harassment being caused by reason of initiation of the arbitral proceedings or participation in such proceeding and having regard to the fact that the agreement is not in dispute, in our view, the plaintiff is not entitled to an order of injunction."
The buyer, of course, is not challenging the order on that ground. The
circumstances are such which clearly debars the buyer to challenge the
award on the ground that it is against public policy.
The buyer has argued that there has been a breach of natural justice
and the finding of the arbitral tribunal that the buyer was responsible to
produce the quality certificate at the port of discharge is contrary to the
terms of the contract which should shock the conscience of the Court and
such finding is against justice and morality. It is a settled law that
interpretation of the contract and appreciation of the evidence by the
arbitral tribunal cannot be reopened by arguing that the foreign award is
contrary to the contract and, therefore, its enforcement would offend public
policy of India. A party who has consciously and deliberately avoided a
proceeding knowing fully well that the result of the proceeding may be
adverse to its interest cannot complain of violation of natural justice. The
petitioner was under no disability and nothing has prevented the petitioner
to file its statement of defence along with documents. The petitioner is in
effect seeking a review of the foreign award on merit which is not permitted in this proceeding. Lord Mansfiled in Holman v. Johnson stated that the
principle of public policy is ex dolo malo non oritur action. No Court of law
will lend its aid to a man who founds his cause of action upon an immoral
or illegal act. The rule has been further illustrated by Russel by stating that
grounds of public policy on which an award may be set aside include: (1)
that its effect is to enforce an illegal contract; (2) that the arbitrator, for
instance manifested obvious bias too late for an application for his removal
to be effective before he made his award.
None of the above conditions apply in the instant case. The petitioner
is not alleging fraud or bias by the arbitrator.
Even under the domestic award, a possible view by the arbitrator on facts
has necessarily to pass muster as the arbitrator is the ultimate master of
the quantity and quality of evidence to be relied upon when he delivers his
arbitral award. Thus, an award based on little evidence or on evidence which
does not measure up in quality to a trained legal mind would not be held to
be invalid on this score. Once it is found that the arbitrators approach is not
arbitrary or capricious, and then he is the last word on facts. The
construction of the terms of the contract is primarily for an arbitrator to
decide unless the arbitrator construes the contract in such a way that it
could be said to be something that no fair minded or reasonable person
would do, of course, the arbitrator cannot wander outside the contract and
deals with the matters not forming the subject matter or allotted to him as
in that case he would commit jurisdictional error.
The judgment in Associate Builders (supra), which was passed in
relation to a domestic award also recognized and reaffirmed the settled law
that where a cause or matters in differences are referred o an arbitrator,
whether lawyer or layman, he is considered to be the sole and final judge of
all questions of law and of fact obviously with the limited grounds of
interference, namely, if it is opposed to fundamental policy of Indian Law,
interest of India, justice or morality and patent illegality. It is an admitted
position that the buyer did not participate in the proceeding nor has filed its
pleading. The Tribunal on the basis of the materials on record has arrived
at the following finding:-
"6.10. If we disregard the alternations envisaged by the Amendment to the Contract dated 7th December 2010, granting an even higher level for "Broken Grains" and "Dead, Damages and Discoloured Grains", the results provided by ISC were well within the parameters foreseen for the quality under the Contract.
6.11. The Tribunal therefore finds that the quality of the cargo shipped on the three vessels was within the amended contractual specifications.
6.12. In addition to the above, the relevant provision of the Quality Clause 5 of GAFTA Contract No.48, being a Tale Quale contract as such, states, inter alia:
"Certificate of Inspection at time of loading shall be final as to quality".
6.13. Consequently, and under consideration of the Payment Term of the Contract providing for payment "on receipt of the shipping documents", inter alia the above Pre-Shipment Certificates as issued by ISC and provided by Sellers, Sellers were duly entitled to trigger payment under the Contract.
6.14. We therefore find that Sellers'' claim for payment of USD 440.00 per metric ton for all three partial shipments succeeds.
6.15. In reference with the balance of USD 10.00 per metric ton for each partial shipment, as agreed under the Amendment dated 7th December, 2010, the Amendment provided that the "Balance amount @ US$ 10.00 per MT will be payable after receipt of quality inspection report of destination port".
6.16. This indeed establishes an alteration to the original provision of the Contract that the quality would be final at the port of loading, at least as far as the balance of USD 10.00 per metric ton is concerned. On interpretation and construction of the Contract itself and its Amendment dated 7th December, 2010, the Tribunal notes that the Amendment itself defines in "1. Quantity" that the weight in accordance with the Contract would be still "final at loading" while the amended Payment Term now states that "a balance amount of US$ 10.00 per MT" would only "be payable after receipt of a quality inspection report of destination port".
6.17. We therefore find that the Contract had been validly altered to the provision that Sellers could only have triggered payment of the balance of USD 10.00 per metric ton after presentation of a quality inspection report from the port of destination, i.e. Bangladesh.
6.18 As no such quality inspection report had been presented by Buyers, despite various reminders from Sellers, until the present day, the GAFTA Sampling Rules No.124, cl. 6:1 provide that a "certificate of analysis" should be sent to the other party "within 14 consecutive days" after dispatch of the samples to the analyst.
6.19. Buyers in their message of 5 February, 2011 firstly explained that the quality of the cargo on the last vessel, i.e. MV Tu Man Gang, was inferior.
6.20. The Tribunal therefore finds that Buyers, with respect to cl. 6:1 of the GAFTA Sampling Rules No.124 were obliged to provide a certificate of analysis latest 14 days after that message dated 5th February, 2011, therefore, latest 20 February, 2011."
The aforesaid finding, in my view, is in the realm of the interpretation
of contract and passed on appreciation of evidence. This finding cannot be
interfered with in this proceeding. The findings are not opposed to justice or
morality or contrary to the public policy of India. The said award is not
passed in contravention of any law of the land. Even the English decisions
on the basis of which it was argued that the buyer stands discharged
because of non-submission of the quality certificate at the port of
destination does not assist the petitioner.
In Shamsher Jute Mills Ltd. (supra) the issue was:-
"If an F.O.B seller who has contracted for payment under a letter of credit to be opened by the buyer ships the goods but fails to obtain payment under the credit because of a failure on his part to comply with its terms, may he recover the contract price or damages for non- acceptance against the buyer."
It appears from the judgment that there is no clear evidence to
establish that what exactly happened to the goods. Neither buyers nor
sellers derived any benefit. The sellers'' central contention was that a letter
of credit is conditional payment only. If, therefore, a seller duly ships the
goods and fails to obtain the payment under the letter of credit he is entitled
to recover the price directly from the buyer, at any rate once the letter of
credit has expired. The buyers appear to have agreed that a letter of credit
is a conditional payment only, but contend that it is under the parties''
contract the sole method of payment agreed. Justice Bingham on
consideration of the materials on record stated that "if the seller fails to obtain payment because he does not and cannot present the documents
which the terms of the credit, supplementing the terms of the contract,
require, the buyer is discharged: that was the Ficom case. In the ordinary
case, therefore, of which the present is an example, the due establishment of
the letter of credit fulfils the buyer''s payment obligation unless the bank
which opens the credit fails for any reason to make payment in accordance
with the credit terms against documents duly presented. I know of no case
where a seller who has failed to obtain payment under a credit because of
failure on his part to comply with its terms has succeeded in recovering
against a buyer personally. If this were an available road to recovery, many
of the familiar arguments about discrepancies in documents would be
unnecessary. Bearing in mind the likelihood that buyers will (as here) sell
on to sub-buyers, such a result would, I think, throw the course of
international trade into some confusion. It must in my view follow that the
sellers here, not having complied with the credit terms, cannot recover
against the buyers personally".
The aforesaid decision is distinguishable on facts inasmuch as the
award is passed on interpretation of the contract clause read with the
GAFTA sample rules. The Tribunal held that the buyer has failed to furnish
proof of inferior quality of food grains.
In Ficom S.A. (supra) the Court was concerned with a contract of sale
in which the terms of the letter of credit and in particular of the documents
to be presented under the letter of credit - were undefined in the sale
contract. In deciding the said issue, the following approach was adopted:- "I approach the matter in this way. It is plain on the authorities that parties to a contract of sale, under which payment is to be made by means of a letter of credit, can, by subsequently agreeing to terms of the letter of credit which differ from those specified in the sale contract, hereby vary their contractual obligation under the sale contract: see W.J. Alan & Co. Ltd. V. El Nasr Export and Import Co. [1972] 2 Q.B. 189; [1972] 1 Lloyd''s Rep. 313. A somewhat similar case may arise where the parties do not, in their sale contract, define the terms of the proposed letter of credit. Where that occurs the letter of credit, as subsequently agreed between the parties, may fill the contractual gap and so supplement the terms of the sale contract; if that is not done, for example, where the parties are unable to agree on the terms of a letter of credit to be issued under a contract of sale, then the dispute may have to be resolved by defining where possible by means of implication or by resort to any approved custom of the trade, the terms upon which the parties must be taken to have agreed that the letter of credit should in due course be issued."
In Gutteridge & Megrah''s Law of Bankers'' Commercial Credits, 8th
Edition, the learned Author made the following observation with regard to
the said decisions:-
"3-29 In Ficom SA v. Sociedad Cadex Limitada and Shamsher Jute Mills Ltd. V. Sethia (London) Ltd. non conforming documents were presented under the credit. In the former case the sellers then disposed of the goods for their own account and in the latter the goods appear to have been sold in satisfaction of freight or warehouse costs with neither seller nor buyer deriving any benefit. In both cases it was held that the seller could only obtain the price through the letter of credit. In Shamsher Jute, Bingham J. said:
If the seller fails to obtain payment because he does not and cannot present the documents which the terms of the credit, supplementing the terms of the contract, require the buyer is discharged: that was the Ficom case. In the ordinary case, therefore, of which the present is an example, the due establishment of the letter of credit fulfils the buyer''s payment obligation unless the bank which opens the credit fails for any reason to make payment in accordance with the credit terms against documents duly presented. I know of no case where a seller who has failed to obtain payment under a credit because of failure on his part to comply with its terms has succeeded in recovering against a buyer personally.
3-30 In the Shamsher Jute, Bingham, J. was dealing with a case where the failure to present documents required by the terms of the credit is the fault of the seller. In Saffron v. Societe Miniere Cafrika the seller shipped goods under an F.O.B contract in circumstances which enabled the buyer to obtain control of the goods upon shipment prior to issue of the bill of lading. The buyer then obtained a bill of lading made out in terms that prevented the seller from complying with the terms of the credit and as a result the seller could not obtain payment from the bank. The seller sued for the price. The High Court of Australia upheld the claim, saying:
The question could only arise in special circumstances, e.g. if the bank responsible for the credit were to become insolvent, or as here, where notwithstanding that the documents tendered were not in conformity with the letter of credit, the seller had lost control of the goods to the buyer.
The Court held that property in the goods had passed to the buyer and, the buyer not having restored dominion over the goods to the seller, the seller was able to maintain an action for the price. The seller had sold and delivered the goods to the buyer and was entitled to payment unless there was a term in the contract excusing payment. It held that on the facts there was no such term since the letter of credit was not confirmed and provided for part payment only of the price. The Court then considered what the position would have been if the letter of credit had been intended as the "primary source of payment" and said:
Had the issue been whether the letter of credit was intended as the primary source of payment, the answer would have been that it was. In that event, the further question would have arisen whether the circumstances in which that primary source failed excused the defendant from payment altogether. It would seem that the only possible ground upon which the seller could have been defeated in his claim for the price would have been that the seller was solely responsible for the failure of the primary source of payment."
(emphasis supplied)
The learned Authors have also discussed the consequences of breach
in the following Paragraphs:-
"3-42.Where the buyer fails to open a letter of credit in accordance with the contract of sale by the date required by the contract, this constitutes a repudiation of the contract and the seller is entitled to treat the contract as terminated and claim damages for non-acceptance of the goods.
3-43. Where the seller fails to perform an obligation which is a condition precedent to the buyer''s obligation to open the credit or fails to present conforming documents to the bank within the time stipulated in the credit, this constitutes a repudiation of the contract of sale and the buyer is entitled to treat the contract as terminated and claim damages for non-delivery of the goods.
3-44. If the seller presents conforming documents to the bank, this will discharge his obligations under the contract in relation to the documents and he will be able to recover the sum due under the letter of credit. This will usually be the whole contractual consideration, but it need not be. If it is not the seller is entitled to recover such further consideration from the buyer as is payable under the contract of sale. If, when the goods are delivered, they do not conform to the contract quality, the buyer may claim damages for breach of warranty, or if the facts justify it may reject the goods and claim damages for non-delivery or return of the price as for a consideration that has wholly failed.
3-45. If it transpires that the documents tendered to the bank are fraudulent (by, for example, the bill of lading being ante-dated) and the bank pays the seller, the buyer may be able to recover damages from the seller for breach of contract or, if the facts justify it in deceit." (emphasis supplied)
Jack on Documentary Credits, 4th Edition has also discussed this
aspect of the matter. The learned Author observed:-
"3.60 Whether the credit is conditional or absolute payment, if the seller presents documents to the bank that do not comply with the credit and are rejected the seller cannot sue the buyer directly unless the buyer has actually obtained the goods. This is so whether or not the goods conform to the contract. This is the clear outcome of both Soproma (1) and Shamsher Jute (2).
1 [1966] 1 Lloyd''s Rep 367: see para 3.50 above.
2 [1987] 1 Lloyd''s Rep 388: see para 3.54 above.
3.63 The buyer may receive the goods and yet the seller remain unpaid in two contrasting situations. One is where the credit provides for deferred payment and the documents are duly processed and taken up by the buyer in order to obtain the goods. The other is where the documents are not accepted, perhaps because the bank rightly rejects them, but the buyer nonetheless obtains the goods. He may, for example take delivery from the vessel without bills of lading by giving an indemnity to the shipowner. An equivalent result may obtain by reason of a fraudulent scheme devised by the buyer. He may for example have ensured that the letter of credit demands a document that the seller is unlikely to be able to provide, or he may have failed to extent the period of the credit to cover a later shipment to which the parties have agreed.
3.65 Where the documents have not been accepted and yet the buyer has received the goods one may be confined that the buyer will be held liable for the price. However, the legal basis for reaching this solution may be difficult to predict without knowledge of the precise circumstances. It might be held that by instructing the bank not to pay against the documents because of the discrepancies (the bank will usually request the buyer''s instruction), the buyer has waived and right to treat the credit as payment. Where, as is likely, the seller has retained the right to possession of the goods, he has an alternative to his action for the price, which is to sue in the tort of conversion for the value of the goods. The buyer will have converted the goods by taking them if he had no title to them and no right to possession. This remedy is of particular use where the market has risen so that damages may exceed the contract price. In such a situation if the buyer has himself sold the goods - perhaps for a higher price - the seller may alternatively pursue a restitutionary action to recover the amount received by the buyer as the proceeds of his tort. If the goods have been delivered to the buyer without the buyer having duly presented bills of lading, the seller, if he retains the bills, will have a cause of action against the carrier for misdelivery, in English law for conversion. For an example of such a claim being made against a carrier and admitted by him in exchange for an assignment of the seller''s rights under the credit, see Mannesman Handel AG v Kaunlaran Shipping Corpn."
The aforesaid decision was cited primarily that when the contract is
silent as to who would produce the quality certificate, terms of the letter of
credit can be looked into to fill up the gap, if any, in order to ascertain
whose obligation it would be to produce such certificate.
It is an admitted fact that when the third consignment was received
by that time the validity of the L/C had expired and the parties had agreed to replace the L/C by bill of exchange. There was no stipulation concerning
the said consignment that the payment is subject to production of the
Quality Inspection Report by the seller at the port of destination. Even for
2.22% there was no valid and subsisting L/C. The buyer nonetheless
obtained the goods. The findings of the Tribunal would show that the
buyers in spite of notice did not furnish any proof of inferior quality of the
goods. The Tribunal has interpreted the contract clause with regard to
furnishing a quality certificate at the port of destination to be the
responsibility of the buyer and, in absence of any document to show that the
goods were inferior in quality returned a finding in favour of the seller. The
Court in this limited jurisdiction and the narrower scope within which the
Court has to act under Section 48 of the Arbitration and Conciliation Act,
1996 is unable to accept the submission of the buyer that the said award is
contrary to public policy of India or opposed to justice and morality.
In the instant case, in so far as the seller is concerned, it is quite clear
that certificate at the port of loading is final. The reference to GAFTA Rules
for the purpose of interpretation of the relevant contractual terms to find out
who is responsible for the production of the quality certificate at the
destination port by the arbitral tribunal, in my view, is entirely within the
domain of the Tribunal and is within the realm of interpretation of the
contract. Even a Court in dealing with a domestic award would not touch
the award on this ground. In any event, such grounds of challenge are not
coming within the purview of Section 48 of the Act.
The Court unhesitatingly accepts the submission of Mr. Bose that the
English cases at this stage are academic as the Tribunal has proceeded on
the basis that the award-holder seller is an unpaid vendor and the seller has
discharged its obligation under the contract.
The application being G.A. No.3306 of 2016, accordingly, stands
dismissed.
Execution Case No.487 of 2013 stands adjourned for two weeks.
However, there shall be no order as to costs.
Urgent Photostat certified copy of this judgment, if applied for, be
given to the parties on usual undertaking.
