AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
47 paragraphs · 3,449 wordsDharam Chand Chaudhary, J.�Challenge herein is to an order Annexure P-13, passed by Principal Secretary (Power), Government of Himachal Pradesh in an appeal registered as case No. 10/03 filed under Sales Circular No. 15/2002 whereby the order passed by Board Level Dispute Settlement Committee on 5.3.2003 in case No. BLDSC/09/02 has been partly set aside and while accepting the appeal, partly directed the 1st respondent-Board as follows:-
"There is merit in the appeal which is partly accepted, as such the charges raised by the respondent do not seem to be in order. It is ordered that disputed amount as mentioned above be charged accordingly as under:
i) The consumer be billed for the month of December, 1987 on consumption basis up to 28.12.87 as the defect in PT developed on 29.12.87 only. The bill of Rs. 11,40,180.75 be revised accordingly.
ii) The consumption for the period 9/87 to 11/87 also be reviewed by taking actual consumption for this period. It should not be doubled. Accordingly the energy bill of Rs. 29,25,606.55 be reviewed.
iii) The charges for the period 6.86 to 11/86 may also be reviewed as the respondent did not maintain the apparatus in order."
Challenge is also to the order Annexure P-21, passed by Chief Secretary (MPP & Power), Government of Himachal Pradesh consequent upon the judgment of this Court in CWP No. 918 of 2007 holding thereby that whatever was due and admissible amount has already been ordered to be refunded to the petitioner by his predecessor vide impugned order Annexure P-13 and the petitioner is not entitled to the recovery of any other and further amount and even interest also being not awarded by his predecessor while deciding the appeal vide impugned order Annexure P-13.
The petitioner is a company having its head office at SCO No. 49-50, Sector 26, Madhya Marg, Chandigarh whereas registered office at village Jitwal Kalan, District Sangroor, Punjab. The petitioner-Company has installed its factory at Village Rampur Banjaran, near Dhaula Kuan, District Sirmaur, Himachal Pradesh and manufacturing steel billets and rolled products therein. The load of 6MW was sanctioned in favour of the petitioner-Company by the respondent-Board on 1.7.1986. Subsequently, it was enhanced to 12MW on 17.3.1990. The power to the factory premises is being supplied from Girinagar Power House on 33 KV line. The respondent-Board has installed the electricity meter in the factory premises of the petitioner, under Section 26 of the Electricity Act read with Rule 58 of the Indian Electricity Rules 1956 and Instruction No. 101 of the H.P. State Electricity Power Sales Manual. The petitioner-Company allegedly paid the amount under the bills raised by the respondent-Board on the basis of meter-reading from time to time.
The dispute is with regard to the bills to the tune of Rs. 11,40,188.25 Annexure P-1 raised, taking double of the unit consumed for the period from 1.12.1987 from 1.1.1988 during the period when potential transformers (PT) for 33 KV line was burnt due to insulation around 3.30 p.m. on 29.12.1997. In a suit preferred in the Civil Court at Paonta Sahib, in the interim, the respondent-Board was restrained from claiming this amount vide order Annexure P-3.
Similarly, bill raised in the month of January 1988 to the tune of Rs. 33,77,088/-, in the month of February 1988 to the tune of Rs. 17,84, 121 (Annexure P-4), in May 1988 to the tune of Rs. 29,25,606.55 and for Rs. 23,884.58 (Annexure P-6) were also claimed to be excessive and in addition to normal bills raised by the respondent-Board. The petitioner-Company could have not afforded to shut the shutter of its factory and deprived thousand families of their livelihood had left with no other option but to bow before the pressure and dictates of the respondent-Board. Withdrawal of the suit vide order Annexure P-7 was one of the consequences of such pressure and dictates of the respondent-Board. The petitioner-Company allegedly had paid the following bills to the respondent-Board under protest:-
Since the petitioner-Company was passing through severe financial crises, therefore, moved the Board Level Dispute Settlement Committee for refund of the excess amount along with interest @ 24% per annum. The Committee, however, rejected the claim of the petitioner-Company vide order Annexure P-10. The appeal preferred by the petitioner under Sales Circular No. 15/2002 was partly allowed vide order Annexure P-13.
In compliance of the order Annexure P-13 only a sum of Rs. 39,08,205/- was refunded to the petitioner by the respondent-Board against the due and admissible amount allegedly Rs. 85,98,200/- together with interest @18% per annum. When the entire amount was not paid to the petitioner, representation was made and the respondent-Board even was served with legal notice also, but of no avail. The petitioner, therefore, was compelled to file Civil Writ Petition No. 918 of 2007 in this Court, which was disposed of vide order Annexure P-18.
The 2nd respondent had re-considered the matter consequent upon the direction of this Court, however, not held the petitioner entitled to any other and further amount including the interest vide impugned order Annexure P-21. It has been claimed that neither Board Level Dispute Settlement Committee nor the appellate authority have taken into consideration various factors leading to raise inflated bills, which has resulted in miscarriage of justice to the petitioner, hence the writ petition for the grant of following reliefs:-
"a) Direct the quashing of the order Annexures P-13 and P-21 in so far as it is against the petitioner;
b) Direct the refund of the amount of Rs. 46,89,995.20 along with interest."
The respondent Board, in reply to the writ petition has submitted in preliminary that the petition is neither competent nor maintainable and also that in view of this Court has decided CWP No. 918/07 vide judgment dated 3.7.2007, therefore, this petition is not maintainable being barred by the principle of res judicata. The questions of estoppel and maintainability of the writ petition on account of delay and latches have also been raised. It is specifically averred that the petitioner is seeking adjudication of serious and disputed question of facts, which cannot be decided in the writ jurisdiction and as such the writ petition has been sought to be dismissed on this score alone. The abandonment of its entire claim by the petitioner-company at the time of withdrawal of the suit in the Court at Paonta Sahib has also been pressed in service.
On merits, the entire case as set out in the writ petition has been denied being wrong and it has been urged that nothing is due and payable by the respondent-Board to the petitioner-Company.
The petitioner-Company has filed rejoinder and controverted the case as set out by the respondent-Board in the reply filed to the writ petition. Mr. K.D. Sood, learned Senior Advocate, during the course of arguments, has mainly emphasized on the issue of utilization of the huge amount charged by the respondent-Board, by raising inflicted bills not as per the actual consumption of energy, but on exaggeration, however, not refunded the same together with interest irrespective of the said bills were held to be excessive and false by the 2nd respondent.
On the other hand, Mr. Satyen Vaidya, learned standing counsel has urged that whatever amount was due and admissible to the petitioner, has been refunded consequent upon the order Annexure P-13 passed by the appellate authority. Since no interest has been awarded by the competent authority, therefore, according to Mr. Vaidya, the petitioner is neither entitled to any other and further amount nor the interest as claimed. It is further urged that the entitlement to receive any other and further amount including interest constitutes disputed facts, which need evidence for its proof and cannot be gone into in writ jurisdiction. Mr. Vaidya has also pointed out that in view of the judgment passed by this Court in CWP No. 918 of 2007, filed by the petitioner-Company with identical questions of law and facts, this writ petition is not maintainable.
On analyzing the rival submissions and also the record of this case, it would not be improper to conclude that the machinery needs to be set in motion in a dispute of this nature has been provided under the Electricity (Supply) Act 1948 and other enabling provisions in this behalf. The respondent-Board in exercise of the powers conferred upon it under sub-section (j) of Section 79 of the Act vide Sales Circular No. 15/2002 dated 19.10.2002 has constituted various Dispute Settlement Committees at different level and also appellate authority to review the award announced by the concerned Dispute Settlement Committee, in case the consumer still feels aggrieved and not satisfied with the award. The award made by the appellate authority shall be final and binding on the consumer. The constitution and powers of the appellate authority as per Sales Circular No. 15/2002 referred to hereinabove read as follows:
"The appellate Authority to review the award of the concerned dispute settlement committee in case the consumer is not satisfied with the award shall be the next dispute settlement committee whose award shall be final and binding on the consumer. The appellate authority against the award of Boards Level Dispute Settlement Committee shall be the Secretary (MPP & Power) to H.P. Government.
The appeal before the authority can be preferred within a period of 30 days from the date of issue of award/decision by the Dispute Settlement Committee. Appellate Authority before admitting the appeal for review of the decision of Dispute Settlement Committee shall decide the quantum of amount to be deposited by the consumer before the commencement of hearing/proceedings. The consumer shall deposit the quantum of balance disputed amount as directed by the appellate Authority within 15 days.
Adverting to the case in hand the Board Level Dispute Settlement Committee had considered the matter qua excess billing brought before it by the petitioner-Company vide representation Annexure P-8 after taking on record the response Annexure P-9 of the respondent-Board and rejected the same vide order dated 5.3.2003 Annexure P-10. In an appeal Annexure P-11, the appellate authority while partly setting aside the order Annexure P-10 has arrived at a conclusion that the bills partly raised were excessive and raised wrongly and as such while allowing the appeal partly, directed the respondent-Board to charge the disputed bills in the light of the order Annexure P-13 and refund the due and admissible amount to the petitioner-Company. The directions so issued by the appellate authority stand reproduced in this judgment in para supra.
Consequently, the respondent-Board vide Cheque Annexure P-15 had refunded a sum of Rs. 39,08,205/- to the petitioner-Company. The Company was not satisfied with the refund so made and when the respondent-Board failed to refund the amount claimed by it in its representation and also the legal notice Annexure P-16, filed CWP No. 918 of 2007 in this Court, which was disposed of vide judgment dated 3.7.2007, which reads as follows:-
"The petitioner by means of this writ petition has basically sought implementation of order dated 23.9.2006 passed by the Principal Secretary (Power) to the Government of Himachal Pradesh in case No. 10/2003 titled as M/s Steel Strips Limited v. HPSEB. According to the petitioner, the Himachal Pradesh State Electricity Board has sent a cheque of Rs. 39,08,205/- to the petitioner in purported compliance of the said order. According to the petitioner, even after adjusting this amount, a sum of Rs. 46,89,995/- is still due to it.
This court in exercise of its extraordinary writ jurisdiction, cannot be turned into an executing court to execute the orders passed by the statutory appellate authority under the Electricity Act. It is for the appellate authority itself to determine what is the amount due and payable to the petitioner, if any, under its orders. We, therefore, dispose of this writ petition with a direction that in case the petitioner approaches the Principal Secretary (Power) to the Government of H.P. within three weeks from today, he shall, after issuing notice to the HPSEB and hearing both the parties, determine the amount, if any, due to the petitioner within three months thereafter. With these observations, the petition stands disposed of."
The matter, therefore, landed again before learned appellate authority i.e. Chief Secretary (Power) to the Government of Himachal Pradesh, who has decided the same with the following observations:-
"I have gone through the judgment dated 23.09.2006. I find that my predecessor only partly accepted the appeal of the petitioner against the order passed by the Board Level Dispute Settlement Committee. He had specifically ordered that the consumer be billed for the month of December, 1987 on consumption basis up to 28.12.1987 as the defect in PT had developed on 29.12.1987 only. The bill of Rs. 11,40,180.75 was to be revised accordingly. Further he had held that for 9/87 to 11/87 the bill be reviewed by taking actual consumption and it should not be doubled. Accordingly, the energy bill of Rs. 29,25,606.55 was to be reviewed. Lastly he had said that the charges for the period 6/86 to 11/87 be reviewed as the respondent did not maintain the apparatus in order. In his order he had indicated an amount of Rs. 23,884.58/- as the amount which had been wrongly charged by the Board Level Dispute Settlement Committee on the basis of production date for the period 6/86 to 11/87. In my opinion he has referred to this amount in the last para of the order where he is summarizing the relief he has granted to the petitioner company while accepting it partially. No mention has been made by him with regard to the relief to be granted to the petitioner for the supplementary bill of Rs. 17,84,121.10 nor has he given any relief on account of interest to the petitioner. I also find that the petitioner has not raised the issue of interest vide his own letter dated 11.10.2006 addressed to Secretary, HPSEB in the context of implementation of the order of Pr. Secretary (MPP & Power) dated 23.09.2006.
In view of the above I hold that the order of my predecessor has been properly executed by the respondent i.e. H.P. State Electricity Board.
I further hold that my predecessor had not allowed any relief to the petitioner company with regard to the supplementary Bill of Rs. 17,84,121.10 raised by the Board in February, 1998. I also hold that the claim of interest had not been allowed by my predecessor."
It is thus seen that no other and further amount was found to be due and admissible to the petitioner-Company either towards principal or the interest. It is this order, which has been challenged in this writ petition as noted at the very outset in this judgment.
This Court is of the considered opinion that the machinery to set in motion in a dispute of this nature is provided under Sales Circular No. 15/2002 dated 19.10.2002. The respondent-Board has constituted various Dispute Settlement Committees at Sub Divisional/Circle and Zonal Level as well as at Board Level. At the apex, is the appellate authority referred to hereinabove and its decision, in the matter, is final and binding on the consumer. Whatever was found due and admissible to the petitioner, the appellate authority while adjudicating upon the appeal preferred by the petitioner against the order Annexure P-10 passed by the Dispute Settlement Committee has been paid to the petitioner vide cheque Annexure P-15.
The appellate authority has re-considered the matter consequent upon the above quoted directions of this Court, issued in CWP No. 918 of 2007. No other and further amount has been found to be recoverable by the petitioner against the respondent-Board. Interest has not been awarded by the appellate authority and as such has not been paid on the amount so refunded. The bills raised by the respondent-Board from time to time are excessive or wrong is a question of facts, which cannot be determined in writ jurisdiction for the reason that the adjudication thereof needs proof, which can only be produced in competent Court having jurisdiction over the matter including the Fora established for redressal of the complaints of the consumers in case there is deficiencies in service being rendered by the service providers.
It has already been held in the judgment dated 3.7.2007, rendered in CWP No. 918 of 2007 that this Court cannot sit as an executing Court to execute the order passed by the appellate authority and it is for this reason the said authority was directed to re-examine the matter qua the refund of any other and further amount except the one refunded to the petitioner consequent upon the order Annexure P-13. The appellate authority, however, has not found the petitioner entitled to any other and further amount as is apparent from the perusal of impugned order Annexure P-21.
In Kanaiyalal Lalchand Sachdev and Others Vs. State of Maharashtra and Others, , a similar case where appellant after having availed the statutory remedy of the appeal under Section 17 of the Securitization and Reconstruction of Financial Assets and Enforcement of Security Interest (Second) Ordinance, 2002, the apex Court has held as under:-
"22. We are in respectful agreement with the above enunciation of law on the point. It is manifest that an action under Section 14 of the Act constitutes an action taken after the stage of Section 13(4), and therefore, the same would fall within the ambit of Section 17(1) of the Act. Thus, the Act itself contemplates an efficacious remedy for the borrower or any person affected by an action under Section 13(4) of the Act, by providing for an appeal before the DRT.
In our opinion, therefore, the High Court rightly dismissed the petition on the ground that an efficacious remedy was available to the appellants under Section 17 of the Act. It is well settled that ordinarily relief under Articles 226/227 of the Constitution of India is not available if an efficacious alternative remedy is available to any aggrieved person. (See Sadhana Lodh Vs. National Insurance Company Ltd. and Another, , Surya Dev Rai Vs. Ram Chander Rai and Others, and State Bank of India Vs. Allied Chemical Laboratories and Another--> .)
In City and Industrial Development Corporation Vs. Dosu Aardeshir Bhiwandiwala and Others, this Court had observed that: (SCC p. 175, para 30)
"30. The Court while exercising its jurisdiction under Article 226 is duty-bound to consider whether:
(a) adjudication of the writ petition involves any complex and disputed questions of facts and whether they can be satisfactorily resolved;
(b) the petition reveals all material facts;
(c) the petitioner has any alternative or effective remedy for the resolution of the dispute;
(d) the person invoking the jurisdiction is guilty of unexplained delay and laches;
(e) ex facie barred by any laws of limitation;
(f) grant of relief is against public policy or barred by any valid law; and host of other factors."
In the instant case, apart from the fact that admittedly certain disputed questions of fact viz. non-receipt of notice under Section 13(2) of the Act, non-communication of the order of the Chief Judicial Magistrate, etc. are involved, an efficacious statutory remedy of appeal under Section 17 of the Act was available to the appellants, who ultimately availed of the same. Therefore, having regard to the facts obtaining in the case, the High Court was fully justified in declining to exercise its jurisdiction under Articles 226 and 227 of the Constitution."
Above all in the exercise of jurisdiction under Article 226 of the Constitution of India, the matter where foundational facts are in dispute should not be adjudicated by the High Court. In the case in hand, as noticed hereinabove, the facts such as the quantity of electricity consumed, the bills raised allegedly are not as per the actual consumption of electricity, hence exaggerated or inflated and that such bills should have not been raised nor the amount would have been payable, are disputed questions of facts. The same cannot be adjudicated upon in these proceedings. Above all this Court has entertained the writ petitions twice previously and it is on the direction of this Court, the appellate authority has decided the appeal and in the order so passed by the appellate authority, the petitioner even has obtained refund also. Therefore, for all the reasons hereinabove, the relief as sought in this petition cannot be granted. The petitioner, however, is at liberty to approach appropriate forum, in accordance with law, against its surviving grievances, if any.
For all the reasons hereinabove, this petition fails and the same is accordingly dismissed. Pending application(s), if any shall also stand disposed of.
