The Government of Tamil Nadu and Another vs M. Natarajan

Madras High Court · Decided on 31 July 1997 · Citation: (1997) 2 CTC 347 : (1997) 2 MLJ 604

HON’BLE JUDGES
C. Shivappa, J · Akbar Bhasha Khadiri, J
RESULT
Dismissed
CASE NUMBER
W.A. No. 952 of 1995

AI Structured Summary

Not yet generated for this judgment

Judgment

24 paragraphs · 508 words

C. Shivappa, J.—This appeal is directed against the order of the learned single Judge, dated 26.6.1992, passed in W.P. No. 14563 of

1990.

2.

A Division Bench of this Court, in The Government of Tamil Nadu and Another Vs. S. Jayaraman, has held that the delay between the

publication of Section 4(1) notification in the official gazette and the public notice of the substance at convenient places of the locality should not

exceed two months. If it exceeds two months, it is liable to be questioned.

3.

The contention of the learned Government Pleader is that there is no statutory rule of limitation regarding the publication of notice provided u/s

4(1) of the Land Acquisition Act (hereinafter referred to as ''the Act'') and, therefore, discretion should have been exercised only in favour of the

validity of the notification . There must be continuity of action in the publication of Section 4(1) notification in the official gazette and in the

newspapers, and also in giving public notice of the substance at convenient places in the locality. If there is any long delay or break in the

continuity, in any individual case, it may defeat the scheme for which the acquisition was intended and it may create an uncertainty in putting the

land for the required use and may also prevent the development of such land by the land owner and many such consequences. The provisions

being mandatory and the law of acquisition being one of depriving the citizens of their right to property to which some of them are sentimentally

attached, strict compliance of the provisions of law is required, atleast within the minimum possible time after notification. The officials concerned

have to act sincerely and in a most diligent manner because any unavoidable delay would render the publicity contemplated u/s 4(1) of the Act

effectless. Therefore, in order to prevent the deep gap between the publication of the notification and public notice of the substance at convenient

places of the locality should not exceed the minimum possible time.

4.

Though there is nothing like stipulating a time in Section 4 of the Act, but a reading of the section and the expedition with which the notice has to

be published, as contemplated in the Act, would make it clear that the Act prevents any delay which can take in its ambit a deep gap between the

date of publication of the notification and the date of public notice of the substance of such notification at convenient places in the locality.

Therefore, in order to prevent any undue delay and evil consequences on the land owners and also to keep the effect of the notice intact, a

reasonable time has to be read or presumed to a provision as has been done by this Court, with which we respectfully concur. There is no

substance in the contention raised by the Government Pleader.

5.

We see no ground to interfere with the order of the learned single Judge. The writ appeal is, therefore, dismissed. Parties to bear their own

costs.