AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
197 paragraphs · 4,413 wordsArun Kumar Goel, J.
1 Since identical questions of law are involved in both these appeals, therefore, they are being disposed of by a common judgment
CIMA No 157/96 and CIMA No 158/96
2 Brief facts giving rise to these appeals need to be tested
CIMA No 157/96
3 This appeal has arisen from the order passed by the learned Sessions Judge, Jammu in CID No 17/Arbitration dated 2741996, whereby petition
for appointment of an arbitrator has been alleged and as a consequence of this authority of arbitrator who was appointed by respondent during the
pendency of the said petition before trial court was revoked and in his place another arbitrator viz R V Ahuja (AVSM) Retd Chief Engineer,
A2/53, Azad Apartment, Opp IIT Gate, Hauz Khas, New Delhi was appointed an arbitrator and matter in dispute was further referred to him for
adjudication Parties had entered into an agreement No CE (P) Samparak/MD4/8687 for the construction of permanent bridge over River Tain at
KN 8050 on AkhnoorPoonch Road This work was allotted to the respondent This work was undertaken by respondent, however, numerous
difficulties on account of nonpayment as well as lack of decision on the part of department This resulted in work being not completed even within
the extended period of contract Though fault was on the part of Chief Engineer, Samparak, who instead of admitting the name chose to cancel the
contract vide its communication dated 1461993
4 Since dispute had arisen between the parties to the agreement, therefore, respondents admittedly approach and requested designated authority
for the appointment of the arbitrator in terms of clause 70 of the contract agreement for referring the dispute for determination The contract period
in the instant case has already expired on 3131993
5 The designated authority ie Director General Border Roads Organisations, Army Headquarter, Kashmir House New Delhi was under obligation
to have appointed an arbitrator within a period of 15 days on receipt of communication in that behalf from the respondent Since it failed to appoint
an arbitrator and thus neglected in his duty, therefore, respondent filed an application for appointment of an arbitrator The claim of the respondent
was contested on behalf of the appellants According to them whatever amount was due stands already paid The contract had to be cancelled
because of failure on the part of the respondent and alternate arrangement for its completion was undertaken by them It was admitted that
arbitrator is to be appointed to adjudicate the disputes He is to be appointed by the authority named in the agreement It is specific case of the
appellants that it is respondent who owes money to them and not other way around as claimed by latter It is also case of the respondent that
arbitrator if at all could be appointed was only after the arrangement to carry out the balance work at the risk and cost of the respondent was
completed
6 Another fact that needs to be noted is that respondents approached the competent authority in terms of the agreement to appoint an arbitrator on
1621994 Till 11th July, 1995 no action had been taken by the appellants Even in the objections filed by the appellants to the application for
appointment of an arbitrator by the Court, it is nowhere stated that arbitrator has been appointed on 11th July, 1995, ie, during the pendency of
the application for appointment of an arbitrator It appears that when Brig Sudhir Kumar was appointed as an arbitrator, an application was filed
for quashing the said order This application has also been disposed of by means of impugned order by the learned Court below
CIMA No 158/96
7 In this case vide Agreement No CE(P) Samparak/Mn1/ 8989 parties entered into an agreement for construction of permanent bridge over Nisra
Tawi at KN 6550 on AkhnoorPoonch Road Other facts are almost identical as are of CIMA No 157/96 In this case also Brig Sudhir Kumar was
appointed an arbitrator on 1171995, for quashing the said order of appointing him as arbitrater, an application was filed, and by means of
impugned order dated 2771996 authority of Brig Sudhir Kumar has been revoked and in his place Brig B V Ahuja (AVSM) Retired above named
has been appointed an arbitrator
8 Record of these cases that applications were initially filed in this court in both the cases for appointment of an arbitrator These appear to have
been assigned to learned District Judge for disposal in accordance with law vide order dated 1331995 This is how the matter came to be
adjudicated upon by the said court
9 Other fact that needs to be noticed is that both the parties did not lead any evidence before trial so court proceeded on the basis of the facts as
were pleaded by both the sides before it Even during the course of hearing of these appeals, learned Counsel for the parties stated that no
evidence in the face of admitted position was necessary as such those appeals may be disposed of accordingly
10 Learned Sr Central Govt Standing Counsel submitted that court had no power muchless authority to have appointed an arbitrator as has been
done in the case that too by cancelling appointment of the arbitrator appointed by the competent authority and thereby revoking his power to act
as such Besides this, he submitted that even if it be assured for the sake of argument that there were disputes existing between the parties which
were to be adjudicated upon by the arbitrator still power to appoint him always remained with the authority named in the arbitration clause and not
with the Court Therefore, he has prayed for allowing the appeals and upholding the appointment of Brig Sudhir Kumar as arbitrator and for
allowing both the appeals accordingly This plea has been seriously contested by Shri Pandita who urged that no doubt the power to appoint an
arbitrator was vested with the competent authority named in the agreement Still no exception can be taken to the revocation of the authority of
BrigSudhir Kumar in the peculiar circumstances of this case that too without spelling out such an appointment in the objections which were filed
after such appointment Therefore, he urged for dismissal of the appeals with costs
11 On the basis of aforesaid submissions urged on behalf of the parties Sole question involved in this case is that whether the appellants had
forfeited their right to appoint arbitrator in both the cases, after competent authority failed to do so when it was notified on behalf of the respondent
or not
12 As already noted that power to appoint an arbitrator is with the competent authority in terms of clause 70 of the General conditions of the
contract contained in AAFW No 2249 Arbitrator was to be appointed by CWE or any other person who was to refer the dispute after written
notice by either party to the contract had been given to him for sole arbitration by an Engineer officer As already noted admittedly, on 1621994
CWE was called upon to appoint an arbitrator since disputes had arisen between the parties For the reasons best known to him he chose to sleep
over the matter for more than one year and four months till Brig Sudhir Kumar was appointed an arbitrator on 1171995 This in my considered
view tantamounts to overreaching as well as circumventing judicial process which were pending before the learned court below
13 As per Section 8 of the Arbitration Act, if the competent authority like CWE in the present case in terms of clause 70 (supra) fails to appoint an
arbitrator then there is nothing that prohibits the court to appoint an arbitrator as has been ordered in the present case
14 In AANo 64/90, Om Prakash Nargotra v Union of India, matter relating to removal of arbitrator was pending since appointee was not
Engineer officer as was directed by the court on 2111989 in AANo 631/88 As such, a prayer was made for removal of the arbitrator and
independent Engineer be appointed to act as arbitrator This application was contested and resisted In addition to this, another arbitrator was
appointed during the pendency of the matter before this court In these cicumstances when arbitrator was appointed during the pendency of the
proceedings for removal of the arbitrator who had not been appointed in terms of the earlier order of the court it was held as under :
It is now after a lapse of more than nine months that arbitrator has been appointed Section 8(2) of Arb Act makes it obligatory to appoint
arbitrator within a period of 15 days after service of notice It comes out from abovesaid provision of law that the party who receives notice for
appointment of arbitrator has to act in haste and shall communicate appointment of arbitrator otherwise other party would be justified in taking
action under above said law, in which case the court assumes jurisdiction to appoint any other arbitrator Respondent No2 has now appointed
arbitrator after institution of this petition which cannot be permitted under law
15 In AIR 1996 Raj 170 State of Rajasthan v M/s GS Atwal and Co while considering the case in almost identical circunstances it was observed
as under :
Where State Government failed to appoint the Arbitrator in accordance with Section 8(1) (a) the Act within the stipulated period of 15 days from
notice as envisaged under arbitration clause of the agreement, the claimant can make an application He before Court for appointment of arbitrator
was not obliged to wait indefinitely since rights which were already vested with the claimant had got to be exercised in accordance with S8(2) of
the Act and, therefore, the claimants could not get its rights defeated at the instance of the State Government The very purpose of the arbitration
agreement in view of clause 23 of the agreement would have stood defeated Consequently the appointment of the arbitrator by the court by
treating the application as under Section 8 was perfectly justified, valid and in accordance with law It could not be said in such a case, that as
under arbitration clause there was no mention of appointment of arbitrator by concerned authorities and a specific power was given to Chief
Engineer to appoint Arbitrator, it was only application under Section 20 which was maintainable and, therefore, appointment of Arbitrator by
Court under Section 8(1) was illegal
16 In AIR 1980 Orissa 51, Executive Engineer, Parchi Division, Bhubaneshwar v Gangaram Chharolia it was observed as under at page 52 :
4 It is well settled that when the parties do not concur in the appointment of an arbitrator or arbitrators, or the party who was to appoint the
arbitrator does not make a proper appointment in accordance with the agreement within time the court may, on the application of the party who
gave the notice and after giving the other party an opportunity of being heard, appoint an arbitrator or arbitrators, as the case may be, who shall
have the like power to act in the reference and to make an award as if he or they had been appointed by consent of all parties There is no doubt
that on the failure of the Chief Engineer to appoint a proper arbitrator in accordance with the clause 23 of the F2 agreement within 15 days of due
service of notice as provided in subsec(2) of Section 8 of the Act, the court below had the jurisdiction to appoint an arbitrator and it actually did so
by appointing Sri Dey as the arbitrator in this case As the Chief Engineer did not make a proper appointment within time, he forfeited his right to
appoint the arbitrator, and the court, in due exercise of its power vested on it under the Act, has already appointed an arbitrator The arbitrator
therefore has the power to act in the reference made or to be made to him and to pass an award on that matter as if he had been appointed by the
consenu of all the parties
17 In AIR 1996 Orissa 19, Union India v Prahallad Moharana, after following 1994(5) SCC 142 : AIR 1994 SC 2381, it was observed as under
at page 21; of AIR Orissa :
9 To take up the first point of Mr Behura ie whether the court is competent to appoint an arbitrator of its own choice when the parties agreed to
appoint a named arbitrator in the written agreement
A direct decision on the point in the case of G Ramchandra Reddy and Co (1994 (5) SCC 142 : (AIR 1994 SC 2381) (supra) has been cited to
support the view that the Court is competent to appoint an arbitrator of its own choice in the peculiar facts and circumstances of a given case In
that case, the contract was terminated by the authorities The contractor exercised his option under the General Conditions of Contract and called
upon the appellants to appoint the sole arbitrator in terms of the agreement When no action was taken by the authorities, the respondent filed a suit
under Section 20 of the Act for appointment of arbitrator by the Court The Court appointed a Retired Judge of the High Court as the sole
arbitrator That was reversed by a Division Bench of the High Court The Apex Court following its earlier decision reported in (1993) 2 SCC 654 :
(1993 AIR SCW 2260) Nandyal Cooperative Spinning Mills Ltd v K V Mohan Rao held in para6 of the judgment that when a notice was given
by the contractor to the opposite contracting party to appoint an arbitrator in terms of the contract and if no action had been taken, it must be
deemed that he had neglected to act upon the contract It further held that when no agreement was reached even in the Court between the parties,
the Court would get jurisdiction and power to appoint an arbitrator Even if Section 8(a) of the Arbitration Act per se does not apply, yet it was a
notice indicating the opposite party to act upon the terms of the contract and in spite of this notice when it does not act in strict terms of the
contract, this amounts to forfeiture of the power to appoint an arbitrator in terms of the contract and gives right to the other party to invoke the
Court's jurisdiction under Sec 20 of the Act
Mr Behura during course of argument very much relied on the case of Union of India v Prafulla Kumar Sanyal, reported in (1979) 3 SCC 631 :
(AIR 1979 SC 1457) and submitted that the Court shall always make an endeavour to find out the feasibility of appointing an arbitrator agreed by
the parties The Apex Court in the case of G Ramachandra Reddy (1994 (5) SCC 142 : (AIR 1994 SC 2381)) (supra) distinguished the Prafulla's
case from the case before them inasmuch as they observed that in Prafulla's case, the parties agreed that the arbitrator should be appointed by the
President and that too, even before the Court they agreed for such appointment, and such a situation was neither before the Apex Court in the
case of G P Ramchandra Reddy (supra) nor the same situation is also before us in the case at hand In the case before this Court, the defendant
Railway did not respond to the notice though admittedly they received the same The nonresponse to the plaintiff's notice for appointing the named
arbitrator in the agreement amounts, as has been held by the Apex Court, to forfeiture of the right to appoint an arbitrator so named in the
agreement Therefore, I have no hesitation to hold that the Court is competent to appoint an arbitrator of its own choice in a given situation as is
found in the present case
11 In view of the decision of the Apex Court in the case of G Ramchandra Reddy (1994 (5) SCC 142 : (AIR 1994 SC 2381) (supra) holding
that Section 20, subsection (4) of the Act directly applies to a case where the contracting party does not respond to the notice of the contractor for
appointment of the named arbitrator in the agreement, the two single Bench decisions of this Court should be held to have been overruled That
apart, the two decisions of the Delhi High Court which were followed by this Court in the case of Lingaraj Das (supra) were overruled in the
Bench decision of the Delhi High Court in the case of Ved Prakash Mitthal v Union of India, reported in AIR 1984 Delhi 325 In that case the
Court held that in a situation as in the case at hand, the Court would not be powerless to make an appointment of an arbitrator itself The Court is
competent under Section 20(4) of the Act to appoint the arbitrator of its own choice because it would be a case where the parties cannot agree
upon to appoint an arbitrator It further held that if the so named arbitrator was not appointed by the parties, such a case was contemplated by the
authors of Section 20(4) The Full Bench further held that to such a case, neither Sec 8(1)(a) nor Section 8(1)(b) of the Act applied I have no
hesitation in following the proposition laid down by the Full Bench since a bare reading of Section 8 of the Act it would be amply clear that the
section would not apply to a case as at hand The reason is as follows :
12 Section 8(1)(a) of the Act provides that the reference shall be to one or more arbitrators to be appointed by consent of the parties and if all the
parties do not after differences have arisen concur in the appointment or appointments, any of them can move under this section It is not the case at
hand Therefore, subclause (a) is not applicable
Subclause (b) comes into play only when an arbitrator already appointed either neglects or refuses to act or is incapable of acting, or does, and
then only the question of supplying the vacancy would arise and that would itself depend on the peculiar facts and circumstances of each case and
on the interpretation of the arbitration clause and we are not concerned with such a situation here
Subclause (c) prescribes a situation where the parties or arbitrators do not appoint an Umpire The question of supplying the vacancy would only
arise in a case under Section 8(1) (b) and not under Sec 20(4) of the Act, because Section 20, subsection (1) clearly predicates that action under
that section can be taken by either of the parties even if the party does not proceed under Chapter II in which Section 8 is included Therefore, it is
abundantly clear that the power under Section 20(4) of the Act and the power under Section 8 are distinct powers prescribed for meeting different
situations and there is no reason to hold that both the sections overlap each other To give the real effect and to serve better the purpose of
arbitration, the provisions of both the sections can be resorted to independently Therefore, the contention of Mr Behura cannot be accepted
18 Shri Bhat learned counsel for the appellants placed reliance on a Full Bench decision reported in AIR 1984 Delhi 325 Ved Prakash Mithal v
Union of India and urged that since agreement between the parties require arbitrator to be appointed by CWE, Srinagar, therefore, Section 8 (1)
(a) or 8(1)(b) of the Arbitration Act were not attracted as such, appointment of revocation of the authority of Brig Sudhir Kumar and in his place
appointment of another persons as an arbitrator as detailed hereinabove was liable to be set aside When a reference is made to this decision, it
does not in any manner support muchless advance the plea urged on behalf of the appellants Because while conceding the situation as in the
present two appeals what was observed by the Full Bench is as under :
325 A contractor and the Government were parties to an arbitration agreement a clause wherein provided that the reference of their disputes
would be made to an arbitrator who would be appointed by the Chief Engineer A dispute arose and the contractor issued a notice to Chief
Engineer requiring him to appoint the arbitrator The Chief Engineer refused to appoint the arbitrator An application under Section 20 was filed by
the contractor against the Government and Chief Engineer
Held that, in such a case, the Court would not be powerless to make the appointment of the arbitrator itself Under Section 20 (4) the Court would
appoint the arbitrator because then it would be a case ""where the parties cannot agree upon an arbitrator"" In such a case a notice would be issued
to the defendant, ie the Government, to show cause why the agreement should not be filed If the Union of India showed a good cause for not filing
the agreement, the Court would refuse to file the agreement and dismiss the petition But if no sufficient cause was shown by the Govt the Court
would order the agreement to be filed and would make an order of reference by asking the Chief Engineer to appoint the arbitrator, in terms of the
clause If the Chief Engineer would then refuse to appoint the arbitrator he must mention a reason for his refusal If the reasons were satisfactory the
Court would refuse to appoint arbitrator and file the arbitration agreement The Chief Engineer was a third party to the agreement though he was
the employee of the Govt, one of the parties It was a ministerial job which the Chief Engineer was to perform Such a ministerial functionary could
not destroy the arbitration agreement Section 20(4) conferred upon the Court a general residual power to appoint an arbitrator when the parties
do not agree upon the arbitrator The purpose of the section was to effectuate the intention of the parties in certain events in which one would
expect them to intend that the provision for arbitration should stand but which were not covered in terms by the arbitration provision If the
arbitrator was not appointed by the agreed appointor such a case was contemplated by the authors of Section 20(4) They were the authors of
Section 4 also where the power of appointment could be committed to some other party ILR (1974) 2 Delhi 637, overruled Case law discussed
19 Similarly, reliance placed on the Division Bench judgment reported in 1973 KLJ 311 Chief Engineer (Construction) Northern Railway v M/s
Badri Nath Maggu, does not in any manner improve the case of the petitioner especially under the light of the latter two decisions of Supreme
Court relied upon by the Orissa High Court in AIR 1996 Orissa 19 (supra) Besides this, in both the cases under consideration it was on the failure
of the appellant to have acted within the reasonable time in terms of the agreement by appointing arbitrator in question It was during the pendency
of such proceedings when the arbitrator came to be appointed
Next decision relied by Shri Bhat reported in AIR 1993 J and K 47, Council of Scientific and Industrial Research v M/s Ganga Construction
Corporation, also does not in any manner advance the case of the appellants Reliance was also placed on behalf of the appellants in AIR 1995 SC
2464 Bhupinder Singh Bindra v Union of India This case is of no benefit in the circumstances of the present two appeals It is no body who either
has made any averment of misconduct against the arbitrator or his having delayed in passing of the award While conceding these circumstances,
Supreme Court held that revocation of the authority of the arbitrator appointed by the parties was held to be unjurisdictional and in such
circumstances, appointment of an independent arbitrator by the High Court was found to have been rightly set aside by the High Court in the
appeal of the contract
On examination of the precedent noted hereinabove as well as on consideration of the circumstances of this case there is no infirmity in the order of
the trial Court Even if it be assumed for the sake of argument that Sec 8 is not applicable as was urged by Shri Bhat The question that needs
further examination is whether the authority like CWE in the present case can be permitted to sit over request for appointment of an arbitrator for
unreasonably long period This can never be intention of either clause 70 of the General Conditions of the contract or for that matter no power can
be assumed by the CWE to act on his whim and fancy To meet such a situation, the Court is not powerless It was only after the objections having
been filed in July, 1995 with the order of appointment of Brig Sudhir Kumar as an arbitrator was conveyed for cancellation whereof an application
was filed by the respondent The whole effort by appointing Brig Sudhir Kumar on the part of respondent appears to be to circumvent the judicial
process started by the respondent on the failure of the appellants in the matter of appointment of an arbitrator when called upon to do so on
1621994 As already observed that proceedings were initiated for appointment of an arbitrator in the Court somewhere in the year 1994 to be
precised on 22101994, nothing was done till 1171995 That being so, there is nothing wrong with the order passed by the trial Court in passing the
impugned order Accordingly plea urged on behalf of the appellants against the impugned order has no merit and it is accordingly rejected
20 No other point is urged
21 As a result of aforesaid discussion, there is no merit in these appeals which both are accordingly dismissed Appellants shall pay one set of the
costs to the respondent Registry is directed to place a copy of this judgment in file No CIMA 158/96 Record of both these cases shall be sent
back immediately to the trial Court which shall thereafter proceed in the matter and ex parte interim order passed on 3996 for staying the
proceedings before the arbitrator shall stand vacated forthwith Copy of this order be also sent to Brig B V Ahuja (AVSM) Retired, by the registry
Appeals dismissed
