AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
54 paragraphs · 1,097 wordsM.M. Kumar, C.J.—A short issue raised in this appeal is whether the Arbitrator is required to a pass a reasoned award by virtue of
arbitration Clause 70 of the IAFW 2249 or such an award could be without reason. The matter is no longer res integra. The arbitration clause 70
of IAFW 2249 came up for consideration of their Lordships of Hon'ble the Supreme Court in the case of Gora Lal Vs. Union of India (UOI), .
The expression 'finding' used in arbitration Clause 70 of IAFW 2249 has been interpreted in para 7 of the judgment, which is set out below in
extenso:--
The point for determination in this case is: Whether the Arbitrator ought to have given reasons in support of his findings, along with the sums
awarded, on each items of dispute. To decide this point, we have to go by the text and the context of Clause 70 of the arbitration agreement
quoted above. Under the said Clause, the Arbitrator was required to identify each individual item of dispute and give his findings thereon along with
the sum awarded. In this context, one has to read the word ""findings"" with the expression ""on each item of dispute"" and if so it is clear that the
word ""finding"" denotes ""reasons"" in support of the said conclusion on each item of dispute. The word ""finding"" has been defined in Words and
Phrases, Permanent Edition 17, West Publishing Co. to mean ""an ascertainment of facts and the result of investigations"". Applying the above test to
Clause 70, we are of the view that the ""Arbitrator was required to give reasons in support of his findings on the items of dispute along with the
sums awarded. We make it clear that this order is confined to the facts of this case and our interpretation is confined to clause 70 of the arbitration
agreement in this case.
(emphasis added)
The aforesaid view taken by Hon'ble the Supreme Court in M/s Gora Lal's case (supra) has also been followed by this Court in the case of Union
of India (UOI) and Another Vs. Wazir Chand Bhatia, .
In the present case, Clause 70 of IAFW 2249 is also the arbitration clause and the view taken by Hon'ble the Supreme Court in respect of the
aforesaid Clause is obviously binding. As the issue goes to the roots of the matter and the fate of the award dated 22.09.1975 has to be decided in
accordance with the law laid down by Hon'ble the Supreme Court, it would be necessary to consider whether the award is a reasoned award or it
is a non-speaking award. In that regard, a part of the award is set out in extensor as a sample which represents the nature of the award announced
by the Arbitrator and the same reads as under:
Dealing with each claim separately, I award and direct as under: A. Claims of the Claimant:
A. Claims of the Claimant:
Claim no. 11 to 18..........................................
B. Claims of the Respondent
Claim no.11 to 22................................
A perusal of the aforesaid award made by the Arbitrator makes it evident that after noticing the claim made by the appellant, the Arbitrator has
merely recorded his decision allowing or rejecting the claim. In some items he has partially accepted the claim as against the whole claim made by
the appellant, whereas in another cases he has completely rejected the claim. The reasons which are necessary links between the evidence
adduced and the findings recorded on each item of dispute are obviously missing. Therefore, it is necessarily hit by the vice of Section 30(a) of the
Jammu and Kashmir Arbitration Act, 1945 (for brevity the Act). It has to be concluded that the Arbitrator has misconducted the proceedings and
has not passed a reasoned award as per the judgment of Hon'ble the Supreme Court in M/s Gora Lal's case (supra).
The learned Single Judge has primarily taken the view that no misconduct has been committed and it cannot constitute a ground for setting aside
the award. It is obvious that the aforesaid view was expressed by the learned Single Judge on 31.05.2001 while delivering the impugned judgment
and the view taken by Hon'ble the Supreme Court in 2002 in M/s Gora Lal's case (supra) was not available at that time. Obviously same could not
have been applied to hold that the Arbitrator misconducted the proceedings within the meaning of Section 30(a) of the Act. The law laid down by
Hon'ble the Supreme Court in M/s Gora Lal's case (supra) goes to the roots of the matter and necessary consequence is that the award is liable to
be set aside by virtue of the provisions of Section 30(a) of the act.
Mr. Choudhary, learned counsel for the respondents has, however, argued that a plea of this nature should have been raised by the appellant
before the learned Single Judge and having failed to raise the same it would not be available before the appellate Court in the instant appeal filed
Section 39(i)(vi) of the Act.
Mr. Ajay Pal Singh, learned counsel for the appellant has on the other hand pointed out that the plea was set up in para 54 of the application
filed u/s 30 while challenging the award, which reads thus:
The Arbitrator has not only misconducted the proceedings but also did not comply with the mandatory provisions of clause 70 of General
Conditions of Contract which provides that the Arbitrator shall give his award on all matters referred to him and shall indicate his findings along
with the sums awarded separately on each individual item of dispute.
A perusal of the aforesaid para would show that specific plea in fact has been set out in the application. Even otherwise, this is a purely legal
issue which does not involve appreciation of facts. The award dated 22.09.1975 is on the record. The issue raised before us goes to the roots of
the matter as already observed. Therefore, we do not find any merit in the objection raised by Mr. Choudhary.
As a sequel to the above discussion, we find that the view taken by the learned Single Judge in the judgment and order dated 31.05.2001 is set
aside. Consequently, the award dated 22.09.1975 is also set aside. The Engineer-in-Chief who is competent authority shall appoint a new
Arbitrator in accordance with the provisions of the Arbitration Agreement. The needful shall be done within a period of one month from today.
Appeal stands disposed of in the above terms.
