High CourtsSingle Bench

Usman Sharif vs The Superintending Engineer, CEDC/N, The Executive Engineer, O and M, Tamilnadu Electricity Board and The Asst. Executive Engineer, O and M/Madhavaram/C ED C/North, Tamilnadu Electricity Board

Madras High Court · Decided on 11 March 2008 · Citation: (2008) 03 MAD CK 0072

HON’BLE JUDGES
P. Jyothimani, J
ACTS & SECTIONS REFERRED
Electricity Act, 1910 — Section 26, 26(1), 26(6)
RESULT
Allowed
CASE NUMBER
Writ Petition No. 16251 of 1998
Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

No AI summary yet

Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.

Judgment

88 paragraphs · 1,806 words

P. Jyothimani, J.—This writ petition is filed challenging the order of the third respondent the Assistant Executive Engineer, O&M/

Madhavaram/C ED C/ North, Tamil Nadu Electricity Board dated 15.09.1998, under which the third respondent has issued a revised bill for

payment to be made by the petitioner in respect of M.E.S. A/c. No. 73:01:30 in the factory premises of the petitioner at No. 69, G.N.T. Road,

Madhavaram.

2.

The impugned order is challenged on various grounds including that the third respondent has computed the period of defective supply from

15.02.1997 to 28.07.1998, which is without any basis. It is also the case of the petitioner that inspection was carried out by the Electricity Board

on 29.05.1998 and thereafter, new meter was installed on 28.08.1998 and in such circumstances, the amount which should have been fixed must

be as per the provisions of the Electricity Supply Act and therefore the exorbitant claim of the third respondent against the petitioner for payment of

Rs. 1,53,363/- has no legal basis whatsoever.

3.

A perusal of the impugned order shows that the amount has been arrived at by the third respondent by calculating the consumption recorded

with effect from 25.02.1997 to 28.07.1998. It is also admitted that the petitioner has deposited 50% of the amount demanded by the third

respondent in the impugned order as per the order of this Court.

4.

The learned Counsel appearing for the petitioner by relying upon Section 26(6) of the Indian Electricity Act, 1910 would submit that as per the

said provision, when there is dispute regarding any meter, the same has to be decided by the Electrical Inspector, such Inspector has to estimate

the amount of energy supplied to the consumer, during the said time, not exceeding six months prior to the period when the defect was detected. In

the present case, the third respondent has taken nearly 22 months prior to the date of detection of the fault of the meter and it is against the

provisions of the said Act. He would also submit that even as per Clause 17(10) of the terms and conditions of supply, the Electricity Board can

only take four previous months and calculate the average amount due and therefore according to the learned Counsel appearing for the petitioner,

calculation given by the third respondent in the impugned order has no legal basis at all. Further to substantiate his contention the learned Counsel

referred to the Judgments of the Hon''ble Supreme Court and this Court reported in (i) Madhya Pradesh Electricity Board and Others Vs. Smt.

Basantibai, (ii) Bihar State Electricity Board and others Vs. Parmeshwar Kumar Agarwala, etc. etc., (iii) A.A. Mohd. Rafi v. Tamil Nadu

Electricity Board 2000 (3) M.L.J. 293

5.

On the other hand, it is the contention of the learned standing counsel for the respondent Electricity Board that the calculation is made in the

usual process and there is no deviation or illegality in the calculation made by the third respondent. It is his submission that when inspection was

made on 29.05.1998, out of three phase commercial connection, the meter reading was not recorded in one phase at all and therefore, it was a

suspected case of tampering. In view of the same, instead of proceeding under power theft, the amount has been calculated as per the Code.

6.

Heard Mr. Zaffarullah Khan, learned Counsel appearing for the petitioner and Mr. S.N. Kirubanandam, learned standing counsel appearing for

the respondents and perused the entire records.

7.

It is an admitted fact that there was an inspection on 29.05.1998 and the third respondent has passed the assessment order by taking into

consideration the meter reading for the period from 25.02.1997 to 28.07.1998 to arrive at the calculation that the petitioner is liable to pay a sum

of Rs. 1,53,363/-. As correctly pointed out by the learned Counsel for the petitioner that under the Electricity Act, 1910, Section 26(6) provides

for inspection by Electrical Inspector and even the Electrical Inspector has to make assessment taking into consideration the meter reading not

exceeding six months. It is also contemplated to give notice by the Electrical Inspector before making such inspection. Section 26(6) of the Act as

follows:

Section 26. Mete Rs.

(1) ...

(2) ...

(3) ...

(4) ...

(5) ...

(6) Where any difference or dispute arises as to whether any meter referred to in Sub-section (1) is or is not correct, the matter shall be decided,

upon the application of either party, by an Electrical Inspector; and where the meter has, in the opinion of such Inspector ceased to be correct,

such inspector shall estimate the amount of the energy supplied to the consumer or the electrical quantity contained in the supply, during such time,

not exceeding six months, as the meter shall not, in the opinion of such Inspector have been correct; but save as aforesaid, the register of the meter

shall, in the absence of fraud, be conclusive proof of such amount or quantity:

Provided that before either a licensee or a consumer applies to the Electrical Inspector under this sub-section, he shall give to the other party not

less than seven days'' notices of his intention so to do.

8.

The above said provision came to be scrutinised by the Hon''ble Supreme Court in Madhya Pradesh Electricity Board and Others Vs. Smt.

Basantibai, . After analyzing Section 26 of the Act, it was held that till the decision is taken by the Electrical Inspector as per Section 26(6), no

supplementary bill can be prepared by the Board estimating the energy supplied to consumer, since as per the Act, the Board is not empowered to

do so. It is also held that tampering or commitment of fraud in respect of use of electricity, does not come within the purview of Section 26(6) of

the Act. After analysing the entire legal aspects of the said provision, the Hon''ble Supreme Court has held in Paragraph 10 as follows:

10.

In the instant case it appears from the report of the Assistant Engineer of the State Electricity Board that one phase of the meter was not

working at all, so there is undoubtedly a dispute as to whether the meter in question is a correct one or a faulty meter and this dispute has to be

decided by the Electrical Inspector whose decision will be final. It is also evident from the said provision that till the decision is made no

supplementary bill can be prepared by the Board estimating the energy supplied to the consumer, as the Board is not empowered to do so by the

said Act....

9.

In Bihar State Electricity Board and others Vs. Parmeshwar Kumar Agarwala, etc. etc., again the Hon''ble Supreme Court has reiterated the

Judgment in Madhya Pradesh Electricity Board and Others Vs. Smt. Basantibai, stating that u/s 26(6) of the Act, there is no authority on the part

of the Electricity Board to submit a supplementary bill to the consumers. The operative portion of the judgment is as follows:

21.

This is not all, as it has been held by this Court in Madhya Pradesh Electricity Board and Others Vs. Smt. Basantibai, , that Section 26(6) of

the 1910 Act does not authorise the Electricity Boards to issue any supplementary bill in respect of the energy consumed during the pendency of

the dispute with an Electrical Inspector. We have mentioned about this decision because pursuant to the notification, the Board did submit

supplementary bills to the respondent-consumers. It seems to us that this action was really in conflict with the statutory provision contained in

Section 26(6) of 1910 Act, as interpreted by this Court in Madhya Pradesh Electricity Board and Others Vs. Smt. Basantibai, .

10.

Mr. Justice P. Sathasivam, as he then was, in A.A. Mohd. Rafi v. Tamil Nadu Electricity Board and Ors. 2000 3 M.L.J. 293 while referring to

the above said Judgments has held that the procedure provided u/s 26(6) of the Electricity Act, 1910 has to be followed in cases where there is

difference or dispute with reference to the Meter referred to in Section 26(1). This Court has also considered Clause 17(10) of the Terms and

Conditions of Supply of Electricity and ultimately held that if the provision u/s 26(6) is not followed, the Board has no right or jurisdiction to issue

any supplementary bill. The operative portion of the order is as follows:

5...It is clear from the above said provision that in case of any difference or dispute with reference to the meter referred to in Sub-section (1) of

Section 26, the same has to be decided by making an application either by the consumer or the officers of the Electricity Board by an Electrical

Inspector. It is also clear that it is for the Electrical Inspector to verify and ascertain the correctness of the meter and even if there is any defect in

the meter, it is for the Inspector to estimate the amount of average supply, not exceeding six months. A reading of the said provisions shows that an

elaborate procedure is provided in case of any defect in the meter. Admittedly, the respondents, particularly, the third respondent has not followed

the said recourse.

11.

On the established judicial precedent on this aspect especially with regard to the finding that the amount to be paid in case of dispute regarding

the meter reading and applying the same to the facts and circumstances of the present case, it is patent that the third respondent has not at all

followed the provisions contemplated u/s 26(6) of the Act. It is relevant to point out that, admittedly it is not a case of power theft and it is the case

of dispute regarding meter reading and in such circumstances, the respondents have no other option than to follow the provision contained u/s

26(6) of the Electricity Act, 1910 and in the absence of following of the said provision, I am of the view that the impugned order of the third

respondent is not sustainable in law. In view of the same, the impugned order of the third respondent is set aside and the writ petition stands

allowed.

12.

The third respondent is directed to ascertain the payment due from the petitioner as per the dispute regarding meter reading taking into

consideration the procedure contemplated u/s 26(6) of the Electricity Act, 1910 and pass appropriate orders. It is also made clear that the

petitioner who has deposited Rs. 75,000/- as per the interim order of this Court and on ascertaining the amount due by the petitioner, the third

respondent shall give credit to the said amount deposited by the petitioner and pass appropriate orders. The above said process shall be

completed within a period of eight weeks from the date of receipt of a copy of this order. No costs.