 N. V. RAMANA, J.
Civil Appeal Nos.6003Â6004/2018
(Arising out of SLP (C) Nos. 27516Â27517/2014)
Leave granted.
These appeals are filed against the final judgment and order dated 14.07.2014, passed by the High Court of Judicature at Bombay (Nagpur Bench)
in First Appeal No. 116 of 1996 and First Appeal No. 31 of 1996.
A brief reference to facts of the case may be necessary for the disposal of this case. The predecessor interest of the appellant herein was the
owner of the property in dispute. In the year 1985, the disputed land, was proposed to be acquired by the Divisional Controller, MSRTC Corporation,
Amravati for construction of city service terminus at Amravati. Required Notification under Section 126 (4) of the MRTP Act, 1966 read with Section
6 of the Land Acquisition Act was published in the Government Gazette dated 05.12.1985. Thereafter the objections from the interested parties were
heard by the Special Land Acquisition Officer, Zilla Parishad Works, Amravati. By a final order dated 30.11.1987, the Special Land Acquisition
Officer, passed an award, wherein an amount of Rs. 5,83,366/Â was payable by the respondent authorities to the appellant herein. On 21.12.1987, the
predecessor interest of the appellant received a notice from the collector/Land Acquisition Officer informing them about the award being passed on
30.11.1987, which is reproduced as underÂ
You are hereby given notice that you are being treated as person interested in the aboveÂmentioned case. In the said case on 30.11.1987, I, have
pronounced the following Award under subÂsection 1 of Section 11 of the 1894 Act.
(1)The area of the land is 704.31 sq. meters in plot No. 3.
(2)The amount of Rs. 2,58,849.00 as compensation be given for the land.
(3)The amount of compensation has been divided as follows:…..
…..
(2) The amount payable to you is Rs.2,58,849.00. You personally or through authorized representative should remain present before me on 28.12.1987.
You can receive the compensation under protest so that there is no impediment in your right to send reference to the Civil Court in respect of this
case.
It may be noted that the actual award was not enclosed with the aforesaid notice and the predecessor interest of the appellant received the certified
copy of the award only on 03.02.1988. On 09.02.1988, the predecessor interest of the appellant, aggrieved by the compensation awarded to him by the
Special Land Acquisition Officer, filed a reference against the award for enhancement of compensation under Section 18 of the Land Acquisition Act.
In the meantime, the predecessor interest of the appellant, had received the award amount under protest, that the reference for enhancement was
pending.
The Reference Court (Court of Civil Judge), after hearing the parties concerned, partly allowed the reference and increased the compensation from
Rs. 110/Â per square meter to Rs. 210/Â per square meter. It may not be out of context to note that respondent authority had not raised any issue on
limitation.
Aggrieved, both parties, filed Cross appeals being First Appeal No. 116 of 1996 and First Appeal No. 31 of 1996 and the present matter was tagged
along with various other similar petitions. The High Court by order dated, 07.10.2010, while remanding the matter back to the Reference Court on the
issue of limitation, kept the matter pending before the High Court in the following mannerÂOn hearing the learned counsel for the parties and on
perusal of the Record and proceedings along with the copy of Section 12(2) notices, which were sought to be produced by the learned Assistant
Government Pleaders before this Court at the time of the arguments that it would be necessary in the interest of justice to refer the issue of limitation
to the reference Court from whose judgments, the appeals are preferred by invoking the provisions of Order 41 Rule 25 of the Code of Civil
Procedure, since the reference Court has omitted and failed to frame and try the issue of limitation, which essentially ought to have been decided
before deciding the reference applications on merit.
Hence, by keeping all these first appeals pending in High Court, the issue of limitation is referred to the reference Court for trial after granting an
opportunity to the parties to amend the pleadings on the issue of limitation and also to tender evidence on the said issue. The reference Court is
directed to try the issue of limitation in all these cases within a period of six months from the date of appearance of the parties before the reference
Court and shall return the record to this Court and shall return the record to this Court together with its findings on the issue of limitation along with the
reasons therefor.
On remand, the reference Court granted opportunity to the parties to lead evidence and upon hearing the parties, it passed judgment and order dated
11.10.2011. The reference court, found that the predecessor interest had filed the reference for enhancement, before the expiry of the limitation as
they became aware of the contents of the award only on 03.02.1988 and not when a notice informing the award was sent.
The High court resumed hearing of the case, after receiving the order of the Reference Court on remand. The High Court again dealt with the
contention concerning the issue of limitation and concluded, by order dated 14.07.2014, that the appellants herein, had not filed the reference for
enhancement of compensation within the time limitation, in the following mannerÂ
The next submission made by Mr. K.H. Deshpande, learned Senior Counsel, is that the details about the Award in order to raise a challenge or
grounds to be taken in the reference Application, could be available only after obtaining certified copy of the Award and a mere visit to the office of
the Land Acquisition officer for receipt of compensation on 28th December, 1987 cannot be taken to mean that the claimants were posted with the
details of the Award in order to raise a challenge. It is an admitted fact that all the claimants received compensation on  28 th December, 1987
and, therefore, constructively and practically, they must be posted with the knowledge about the contents and details of the award .
Aggrieved by the aforesaid impugned order, the appellant is in appeal before this Court.
The main contention canvassed by the appellants, in these Civil Appeals, is whether an effective notice of the award was provided to the appellant
herein, as per the mandate of Section 12 (2) of the Land Acquisition Act, 1894?
Learned counsel for the petitioner, Ms. Bansuri Swaraj, relies on the judgment of Premji Nathu v. State of Gujarat and Anr., (2012) 5 SCC 250,
wherein this court has observed as underÂ
In the light of the above, it is to be seen whether the conclusion recorded by the Reference Court, which has been approved by the High Court
that the application filed by the appellant was barred by time is legally sustainable.
A careful reading of the averments contained in Para 2 of the application filed by the appellant under Section 18(1) shows that the notice issued by
the Collector under Section 12(2) was served upon him on 22Â21985. Thereafter, his advocate obtained certified copy of the award and filed
application dated 8Â4Â1985 for making a reference to the Court. This implies that the copy of the award had not been sent to the appellant along with
the notice and without that he could not have effectively made an application for seeking reference.
On behalf of the State Government, no evidence was produced before the Reference Court to show that the copy of the award was sent to the
appellant along with the notice. Unfortunately, while deciding Issue 3, this aspect has been totally ignored by the Reference Court which mechanically
concluded that the application filed on 8Â4Â1985 was beyond the time specified in Section 18(2)(b). The learned Single Judge of the High Court also
committed serious error by approving the view taken by the Reference Court, albeit without considering the fact that the notice issued by the Collector
under Section 12(2) was not accompanied by a copy of the award which was essential for effective exercise of right vested in the appellant to seek
reference under Section 18(1).
(emphasis supplied)
The learned counsel appearing on behalf of the Government, has not disputed the aforesaid proposition of law. Accordingly, we are of the opinion
that the aforesaid observations are squarely applicable to the present case as the notice dated 4.12.1987, was not accompanied with the award. In this
case, there could not have been a valid notice of the award, by letter dated 4.12.1987, under subÂsection (2) of Section 12 of the Land Acquisition
Act, until the appellant received a certified copy of the award, which he did on 03.02.1988. Therefore, the reference for enhancement was,
accordingly, not barred by limitation.
Having regards to the facts and circumstances of this case, we set aside the order of the High Court concerning the point of limitation and remand
the matters back for fresh consideration on merits of the case inter alia, as to the quantum of compensation. Taking into consideration, the long
pendency, we request the High Court to dispose of the matter expeditiously.
The appeals are disposed of in the aforeÂstated terms.
Civil Appeal Nos.6006Â6007 of 2018
(Arising out of SLP (C) Nos.16339Â16340/2018)
(Arising out of SLP (C) No. ………….CC No. 17187 of 2014)
Permission to file the Special Leave Petitions is granted.
Application for deletion of respondent no. 3 in Special Leave Petition arising out of First Appeal No. 35 of 1996 is allowed.
Leave granted.
As these appeals are filed against the same impugned judgment and order dt. 14.07.2014 passed by the High Court of Judicature at Bombay
(Nagpur Bench) and having the same question of law, these appeals are also disposed of in a sequel to the discussion set out above.