AI Structured Summary
Not yet generated for this judgment
No AI summary yet
Generate an eight-section analysis of this judgment — facts, issues, reasoning, ratio and a plain-language gist.
Judgment
607 paragraphs · 13,035 wordsW.P.(C) No.5408 of 2019:
The present writ petition has been filed by the petitioner Vinod Kumar Jain (hereinafter to be referred as P-1) for quashing of the decision of the
Tender Committee dated 03.10.2019 as uploaded in Form No.5B by respondent no.4 to the extent the technical bid of the P-1 has been declared as
non-responsive to Clause 16.3 of the Instructions to Bidders (ITB) to Standard Bidding Document (SBD) in respect of the work pertaining to
“Reconstruction of Meral-Bana-Ambakhoriya Road (MDR-140) (hereinafter to be referred as W-1). Further prayer has been made for issuance
of direction upon the respondent-State of Jharkhand to declare the technical bid of the P-1 as responsive and consequently to open the price bid of the
P-1 and award the work in question to it by issuing of Letter of Intent/Work Order if the petitioner’s financial bid is found to be the lowest.
The factual background of the case as stated in the writ petition is that the respondent-State of Jharkhand vide e-Tender Notice dated 07.06.2019
invited tenders for Reconstruction of Meral-Bana-Ambakhoriya Road. The P-1 participated in the said tender namely W-1 and as per Clause 16 of
the ITB to Standard Bidding Document (in short to be referred as SBD) of the said tender, submitted requisite bid security of Rs.133.58 lakhs by way
of bank guarantee in the format as prescribed in the SBD. However, the said e-Tender was cancelled by the State respondents vide notice dated
20.08.2019 issued by the respondent no.4 and the original bank guarantee submitted by the P-1 was returned back to it. Thereafter, a fresh e-Tender
notice dated 20.08.2019 was issued for the same work with a similar condition contained in Clause 16 of the ITB to SBD to furnish a bid security of
Rs.133.58 Lakhs. Pursuant to the 2nd Call tender dated 20.08.2019, the P-1 again participated in the said tender process and submitted the same bank
guarantee after getting it amended by its banker. However, the technical bid of the P-1 was declared non-responsive by the Tender Evaluation
Committee of the respondent authorities on the ground that its bid was non-responsive to Clause 16.3 of the ITB to SBD. The P-1, having come to
know about the said fact, filed representation before the respondent no.3 on 04.10.2019 requesting therein to revise the decision taken by the Tender
Evaluation Committee, however the respondents did not pay any heed of the same.
W.P.C No. 5689 of 2019:
The present writ petition has been filed by RAMIYA-HS(JV) (hereinafter referred as P-2) for quashing the Government e-Procurement System
Tender Summary Report in connection with NIT No.RCD/Garhwa/726/19-20(2nd Call) dt.20.08.2019 for award of contract for construction of Meral-
Bana-Ambakhoriya Road (MDR-140) (W-1) (Length-0.00 to 36.629 Km) dated 07.10.2019 along with appendix thereof at serial no.7 qua the
petitioner RAMIYA-HS(JV) (70:30), Gaya whereby it has been declared non-responsive in technical bid due to alleged non satisfaction of clause
2.7.1(ii) of the Addendum/Amendments to the Instruction to Bidders (ITB) to SBD. Further prayer has been made for issuance of direction upon the
State respondents to declare the technical bid of P-2 as responsive as it satisfied all the criteria of the SBD and consequently to open the Financial Bid
of the P-2 as well as to declare it L1 in as much as it has quoted the bid price of Rs.107,55,36,040.91/- as against the minimum bid price quoted by one
M/s Agrawal Global Infratech Private Limited @ Rs.111,78,68,989/-.
The factual background of the case as stated in the writ petition is that the P-2 has been formed by way of Joint Bidding Agreement dated
02.09.2019 to participate in the 2nd Call tender dated 20.08.2019 for the work W-1. As per the joint venture agreement and the power of attorney
executed by and between the parties of joint venture M/s RAMIYA Construction Pvt. Ltd. has been designated as lead partner with power of
attorney to conduct, participate and transact in the entire tender process through its one of the Directors namely Mr. Vineet Yadav. The P-2
thereafter participated in the said tender but its technical bid was rejected being non-responsive to Clause 2.7.1(ii) of the amended ITB to SBD.
W.P.(C) No. 5416 of 2019:
The present writ petition has been filed for quashing/setting aside the decision of the Tender Committee dated 03.10.2019 as uploaded in the Form
No.5B by respondent no.4 to the extent the technical bid of the P-1 has been declared as non-responsive to Clause 16.3 of the ITB to SBD in respect
of the work pertaining to “Reconstruction of Nagaruntari-Dhurki-Ambakhoriya Road (MDR-139)†(hereinafter referred as W-2). Further prayer
has been made for issuance of direction upon the respondent-State of Jharkhand to declare the technical bid of the P-1 as responsive and
consequently to open its price bid and award the work in question in its favour by issuance of Letter of Intent/Work Order if the petitioner’s
financial bid is found to be the lowest.
The factual background of the case as stated in the writ petition is that respondent-State of Jharkhand vide e-Tender Notice dated 07.06.2019
invited tender for the said work i.e. W-2 and as per Clause 16 of the ITB to SBD of the said tender, the petitioner submitted the requisite bid security
of Rs.105.72 lakhs by way of bank guarantee in the requisite format as prescribed in the SBD. However, the said e-Tender Notice was cancelled by
the respondents vide notice issued by respondent no.4 dated 20.08.2019 and the bid security of the P-1 was returned. Thereafter, it issued a fresh e-
Tender notice for the same work with similar conditions for furnishing the bid security of Rs.105.72 Lakhs as prescribed under Clause 16 of the ITB
to SBD. The P-1 again participated in the said tender and submitted the amended bank guarantee. However, the Tender Evaluation Committee of the
respondents declared the bid of the petitioner as non-responsive to Clause 16.3 of the ITB to SBD and the summary of the decision of the Tender
Evaluation Committee was uploaded in the website of the respondent-authorities under the signature of the respondent no.4 in Form No.5B. The P-1,
after having come to know about the decision of the Tender Evaluation Committee, filed a representation before the respondent no.3 on 04.10.2019
requesting the respondent no.3 to revise the decision taken by the Tender Evaluation Committee and declare the bid of the P-1 as technically
responsive, however the respondents did not pay any heed to the representation of the P-1.
W.P.C No. 5894 of 2019:
The present writ petition has been filed for quashing the e-Tender notice dated 26.10.2019 being 3rd Call tender issued by the respondent-State of
Jharkhand pertaining to “Reconstruction of Dandai Bazar to Panghatwa P.W.D Road via Lawahikala Road (total length 10.05 km) (hereinafter
referred as W-3) as the same has been issued after cancelling 2nd Call tender dated 26.08.2019 is a most arbitrary and unreasonable manner vitiated
by mala fide and malice in law against the P-1. Further prayer has been made for issuance of direction upon the State respondents to issue letter of
acceptance (LoA) and enter into consequential agreement with the P-1 pursuant to e-tender notice dated 26.08.2019 being 2nd call tender for the said
work especially because the P-1 was declared both technically and financially qualified in respect of the said tender and the P-1 was even declared as
the lowest bidder in respect of said tender.
The factual background of the present case as stated in the writ petition is that the respondent-State of Jharkhand through the Executive Engineer
initially issued e-Tender Notice dated 07.06.2019 inviting eligible bidders for undertaking the work W-3 wherein the P-1 participated and submitted the
bid security in terms of Clause 16 of the tender document, however the said tender notice was cancelled. Thereafter, 2nd call tender notice dated
26.08.2019 was issued wherein the P-1 again participated and submitted the amended Bank Guarantee. The technical bid of the P-1 was accepted by
the State respondents and thereafter its financial bid was opened and the State respondents declared the bid of the P-1 as the lowest, the details
thereof was uploaded in the official website of the State respondents in the form of BOQ summary details. The respondent no.4 vide letter no.972
dated 16.10.2019 invited the P-1 for finalization of tender and it is in that background that rate justification was sought for from the P-1 for execution
of the said tender in question. The P-1 also submitted its rate justification with the respondent no.4 vide letter dated 20.10.2019 and kept waiting for
issuance of LoA. However suddenly the State of Jharkhand floated another e-tender notice dated 26.10.2019 being 3rd call tender for the said work
i.e. W-3. No order/decision has been uploaded by the respondents in its official website cancelling the 2nd Call tender dated 26.08.2019 but in view of
the fact that 3rd Call Tender for the said work has been issued, it reveals that 2nd Call tender has been cancelled by the State of Jharkhand.
The learned counsel appearing on behalf of the P-1 submits that the P-1 submitted the requisite bank guarantee of the bid security amount as
prescribed in the SBD and the same was in the requisite format as prescribed in the SBD. However the respondents in a most arbitrary manner
rejected the technical bid of the petitioner allegedly being non-responsive to Clause 16.3 of the ITB to SBD. It is further submitted that the decision of
the Tender Evaluation Committee was not furnished to the P-1 and no further reason was explained to it as to how its bank guarantee was not in the
requisite format as prescribed under the SBD. It is also submitted that for the work W-3 also, the P-1 after cancellation of the first e-tender, furnished
the amended bank guarantee to the respondent authorities in the second call tender and in the evaluation by the tender committee, its bid was held
responsive and further decision was taken to open the financial bid and later on its financial bid was declared as the lowest. Thus it would be evident
that the State respondents, in the matter of evaluation of the tenders invited by them, have adopted completely contrary stand disqualifying one or the
other bidder dehors the terms and conditions of the SBD. So far as W-1 and W-2 are concerned, the P-1 followed the same practice as was followed
in the tender W-3 but the State respondents adopted completely different stand in the tender W-1 and W-2 which is not permissible in the eye of law.
It is further submitted that the technical bid of the P-1 has been declared as non-responsive by the State respondents in a most arbitrary and whimsical
manner de hors the terms and conditions of the Tender Document with a view to favour one or the other bidder who participated in the tender
process. It is further submitted that the financial bid of the P-1 is lower than the successful bidder i.e. respondent no.5 thus the petitioner is entitled for
allotment of work in its favour being the lowest bidder. It is further submitted that due to the action of the State respondents in rejecting the technical
bid of the P-1 in a most arbitrary manner, even larger public interest is being affected putting extra burden on the State exchequer. The petitioner is
ready and willing to execute the work W-1 at a much lesser price than that quoted by the lowest bidder i.e. the respondent no.5.
The learned counsel for the P-1 further submits that the P-1 has downloaded the copies of the Bank Guarantee of the other four bidders whose
technical bids were declared responsive. It would be evident from the technical bid of the respondent no.5 who was also declared the lowest bidder
that its Bank Guarantee incorrectly spells the name of the employer’s representative and instead of the name of the Executive Engineer, Road
Construction Department, Road Division, Garhwa, the Bank Guarantee has been issued in the name of Executive Engineer, Road Division, Garhwa.
Further, the Bank Guarantee of M/s N.G Projects Ltd. was also not in proper format and in the bid document, an additional condition has been
incorporated wherein the employer has reserved its right to get the Bank Guarantee extended and notice for such extension to the Bank has been
waived. The substantive condition has also been changed in the Bank Guarantee of M/s N.G Projects Ltd. and it has been mentioned that the Bank
Guarantee can be extended only at the “Banker’s sole discretion.†It is further submitted that the Bank Guarantee submitted by M/s M.G
Contractors Private Limited as well as M/s RKC Infra-built Private Limited would show that the same were exactly in the same format to that of the
petitioner but those bank guarantees were accepted. It is further submitted that though there was error in the amount mentioned in word in the
covering letter of the Bank, but in the amended Bank Guarantee there is no such error. There was no condition in the SBD that Bank Guarantee
cannot be of an anterior date. The only condition was that the Bank Guarantee submitted by way of a Bid Security shall be valid for 45 days beyond
the validity of the Bid. The Bid Validity was prescribed in the tender document as 120 days from the end date of bid submission which was 04.07.2019
and thus the Bid was valid for a period of 120 days beyond 04.09.2019. Admittedly the Bank Guarantee of the petitioner was valid beyond such period
and thus the objection of the respondent authorities is not valid. It is further submitted that one of the stands of the State-respondents is that the
affidavit filed by the petitioner was not in true format however it would appear from the affidavits of two other Bidders namely M/s N.G Projects
Limited and M/s Agarwal Global Infratech Pvt. Ltd. (the respondent no.5) that those were also same as the affidavit of the petitioner. Thus, the
hyper-technical objection taken by the State respondents is not proper cannot be accepted for justifying their action of rejection of the technical bid of
the P-1. The affidavit of M/s M.G Contractors Pvt. Ltd. whose technical bid was also declared responsive, was in the same format to that of the P-1.
It is further submitted that the State-respondents have not filed any copy of letter or email to suggest that they had made communication with the
Bank for verification of the Bank Guarantee and as such said statement cannot be accepted without any cogent materials on record. It is further
contended that in W.P.(C) No. 5408 of 2019 which relates to the work - W-1, this Court after observing the fact that the P-1 has been disqualified in
respect of W-1 and W-2 whereas it has been declared qualified for the work - W-3 and all the three works were substantially the same, vide order
dated 24.10.2019 directed the State of Jharkhand to file counter affidavit. Thereafter, the State-respondents hurriedly to somehow justify their action
also cancelled the tender for the work - W-3 without assigning any reason and floated the 3rd Call Tender vide e-Tender notice dated 26.10.2019. The
cancellation of 2nd call e-Tender for the work W-3 is an exercise undertaken with malafide and malice in law. On bare perusal of the bank guarantee
submitted by said two successful bidders in respect of the works - W-1 and W-2, would clearly demonstrate that those were not in the requisite
format as required in view of the SBD, yet the said Bank Guarantee were accepted by the State respondents.
The learned counsel for the P-2 submits that the action of the State-respondents is nepotic and malafide in law in as much as the technical bid of
the P-2 was rejected contrary to the principles of fairness as well as the relevant provisions of SBD without affording any opportunity to clarify a
formal error, if any, by disclosing the same. The grounds upon which the bid of the P-2 has been declared non-responsive is whimsical and in violation
of the principles of natural justice and fair play. It is further submitted that Clause 2.7.1(ii) of the Addendum/Amendments to the Instruction to Bidders
(ITB) to SBD is an exhaustive clause which provides that a joint venture must collectively satisfy the criteria of Clause 2.6.4 and 2.6.5 for which
purpose relevant figures for each of the partners shall be added together to arrive at the Joint Venture’s total capacity. Individual member must
satisfy the requirement of Clause 2.6.7 and 2.6.8. So far Clause 2.6.4 is concerned, the same relates to personal capacities, whereas Clause 2.6.5
relates to equipment capabilities and Clause 2.6.7 relates to Audited Balance Sheet for last five years. So far as Clause 2.6.8 is concerned, the same
relates to litigation history of the Bidders either jointly or severally in case of JV. However, the State respondents did not mention in the rejection order
as to which clause of the SBD has been violated by the P-2 and thus the order suffers from the violation of principles of natural justice. It is further
submitted that it would be evident from the Financial Bid Opening Summary Report that one Agrawal Global Infratech Private Limited which has
been declared as L1 has quoted the Bid amount of Rs.111,78,68,989/- whereas the P-2 has quoted amount of Rs.107,55,36,040.91 as the financial bid
price. If the genuine bidders are eliminated on illegal, arbitrary and unreasonable grounds much less vague ground, which is otherwise not mandatory
as would be evident from the very language of Clause -2.7.1 to be read with Clauses 2.6.4, 2.6.5, 2.6.7 and 2.6.8, the same causes not only serious
prejudice to such bidder but also put extra burden on the public exchequer as the open tenders are floated in order to secure best suited bidders on
competitive bidding for cost effective and proper execution of the work.
The learned counsel for the P-2 puts reliance on the judgment of the Hon’ble Supreme Court rendered in the case ofK anhaiya Lal Agrawal
Vs. Union of India & Ors., reported in (2002) 6 SCC 315, wherein it has been held that the issue as to whether a condition is essential or collateral
can be ascertained by reference to the consequence of non-compliance thereof. If non-fulfilment of the requirement results in rejection of the tender,
then it would be treated as an essential part of the tender otherwise it would be only a collateral term. It is further submitted that since the alleged
deviation on the part of P-2 is a collateral term, the State-respondents ought to have relaxed the same.
Per contra, The learned Advocate General appearing on behalf of the respondent-State of Jharkhand while justifying the action taken by the State-
respondents submits that the Amended Bank Guarantee could not have been accepted by the respondents as the same was not in the prescribed
format. In fact it was an amended one and containing various other conditions/stipulations beyond what was prescribed in the SBD. There is no
provision in the SBD for accepting amended Bank Guarantee. It is further contended that so far the work-W-1 is concerned the letter issued by the
bank contains a clause stating “This letter forms an integral part of the original guarantee referred above†and thus the same changes the format
of the Bank guarantee submitted by the bidder (the P-1) which in no way can be said to be in terms of the format as prescribed in the SBD. The
State-respondents had made communication with the Bank vide letter and E-mail to verify about the Bank Guarantee submitted by the P-1 but it did
not reply the said communication till date. The bank guarantee of the respondent no. 5 was strictly in adherence to the format prescribed in the SBD
and as such it was awarded the work being L1 as well. The case of the P-1 cannot be equated with the case of the respondent no.5. The P-1 cannot
seek direction of this court to accept the bank guarantee which was not in the proper format. It is further submitted that there was discrepancy in the
letter of the Bank with regard to the amount of the bank guarantee. In the figure, the amount was written as Rs.1,34,00,000/- however in word, the
amount was written as “One Crore Six Lacs Onlyâ€. As per Clause 27.1 of the ITB to SBD, where there is discrepancy between the quantum
mentioned in figures and words, the amount written in words will prevail and it is followed in the financial matters. Moreover, the Bank Guarantee
presented by the P-1 was of anterior date and as such the same was not in adherence to the financial rules. It is further submitted that one of the
requirements in the tender was that the bids of the respective bidders were to be duly notarized, however, the P-1 had submitted attested affidavit
which could not have been accepted. In the present case there was two way envelop system. Unless the technical bid of any bidder is found
responsive, the quoted price in the financial bid has no relevance. There is no arbitrariness in declaring the technical bid of the P-1 as non-responsive.
There were several infirmities in the same including that the P-1 did not submit a proper Bank Guarantee being a mandatory condition as per Clause
16.3 of the ITB to SBD which clearly stipulates that any bid not accompanied by an Acceptable Bid Security and not secured as indicated in clause
16.1 and 16.2 shall be rejected by the employer as non-responsive. It is further submitted that the tender-W-3 has been cancelled by the Department
and has issued fresh tender and thus the P-1 cannot take reference of the said tender for making out its case.
Learned counsel for the private respondent no.5 (namely M/s. Agrawal Global Infratech Private Limited) in W.P.(C) No.5408 of 2019 submits
that the private respondent no.5 has been selected as L-1 and the agreement to execute the work W-1 has already been entered with the State
respondents. The work order has also been issued to it on 18th October, 2019 and has been instructed to proceed in terms with the agreement. In view
of the aforesaid work order, the work has already been started on 20th October, 2019 and a substantial part of which has been carried out by the
Company. The respondent no.5 has mobilized its entire team and machineries. The numbers of machines, vehicles, men power etc. have been
transferred to the work place i.e. at Garhwa and the earth work has been done for about 6-7 kms. Moreover clearing of road by uprooting rank
vegetation, grass, bushes etc. as well as excavation of soil with the help of hydraulic excavator and other related works have also been completed by
the company. The periodic bill in relation to the said work has been submitted before the Executive Engineer, Road Construction Department, Road,
Division, Garhwa as per the agreement. It is further submitted that the measurement of the work has also been done by the competent authorities of
the department. For the last two months, the work is going on in full swing as per satisfaction of the authority concerned. The respondent no.5 has
invested huge amount in execution of the said work. In reply to the contentions made by the learned counsel for the P-1, it is submitted by the learned
counsel for the respondent no.5 that it was known to all the tenderers participating in the tender that each and every term of the SBD is required to be
fulfilled by them and any deviation from the same would be detrimental to the cause of the employer, who has right to reject the tender on any such
deviation. Moreover, the respondent no.5 is a bona fide allottee of the work, who has participated in the tender process and on being declared
successful, has been awarded the said work. The bank guarantee, additional performance guarantee etc. have duly been submitted by the respondent
no.5. There is no question of opening the financial bid of those participants who did not succeed in the technical bid and as such any statement of the
P-1 to the effect that its financial bid was lower than the respondent no.5 is imaginary and cannot be considered.
Learned counsel for the private respondent- M/s. N. G. projects Limited [the respondent no.5 in W.P.(C) No.5416 of 2019] submits that the
Tender Evaluation Committee has not accepted the technical bid of the P-1, as it did not submit the bank guarantee in the prescribed format as per the
SBD. The amended bank guarantee presented by the P-1 could not have been accepted by the Tender Evaluation Committee. Even in the bank
guarantee dated 30th August, 2019 there was difference in the amount mentioned in figure and words. The present respondent submitted the bank
guarantee strictly in accordance with the format prescribed in the SBD. The date of re-tender was 20th August, 2019, whereas the bank guarantee of
the P-1 was issued prior to the date of tender i.e. 9th July, 2019. As per the SBD, an affidavit was required to be duly notarized, however, the P-1
instead of getting the said affidavit notarized, merely submitted an attested affidavit. Moreover, as per the SBD, the bank guarantee was required to
furnished in the prescribed format by the bidders. After the evaluation of the technical bid, the financial bid was opened and the private respondent
was found L-1. Accordingly, letter of acceptance was issued to it vide letter dated 16th October, 2019. The agreement for execution of the work has
also been executed with the State respondents on 21st October, 2019 and, thereafter, the work has already been started. The present respondent has
also submitted a bill of Rs.75.00 lacs for execution of the work and as such the writ petition preferred by the P-1 is not worth consideration.
In course of argument, learned Advocate General puts reliance on a judgment of the Hon’ble Supreme Court rendered in the case ofS outh
Delhi Municipal Corporation Vs. Ravinder Kumar & Anr., reported in (2015)15 SCC 54,5 and submits that the Government being the guardian of the
public finance has the right to refuse the tender bid submitted by the bidder provided the said decision should not be arbitrary or unreasonable. The
learned Advocate General further puts reliance on the judgment of the Hon’ble Supreme Court rendered in the case of Jagdish Mandal Vs. State
of Orissa & Ors., reported in (2007)14 SCC 517, and submits that the writ Court should not interfere in a contractual matter unless the decision
making process of the State authority is found mala fide or to favour any undeserving person. The interference of the writ Court is warranted only in
those cases in which the decision of the State authority is found so arbitrary and irrational, which no responsible authority can reasonably take as well
as on the ground that the decision of the State authority is against the public interest.
Heard learned counsel for the parties and perused the materials available on record. In the present batch of writ petitions, the case of the P-1 is
related to the works W-1, W-2 and W-3, whereas the case of the P-2 is related to the work W-1. The financial bid of the P-1 was declared non-
responsive to Clause 16.3 of the ITB to SBD for the work, namely, W-1 and W-2. So far as the work W-3 is concerned, though the technical bid of
the P-1 was declared responsive and its financial bid was found to be the lowest, the tender itself was cancelled at the stage of issuing letter of
acceptance and third call tender was issued for the said work.
The main submission of the learned Advocate General and the learned counsel for the private respondents is that the P-1 submitted amended bank
guarantee in all the three works which were found non-responsive to Clause 16.3 of the ITB to SBD. On the contrary, the stand of the learned
counsel for the P-1 is that the bid was required to be accompanied by an acceptable bid security, which should have been secured as indicated in sub-
clauses 16.1 and 16.2 failing which the bid was to be held non-responsive and since the bid security of the P-1 was satisfying all the said conditions,
the State respondents have arbitrarily rejected its technical bid.
Before analysing respective contentions of the parties, it would be appropriate to go through the judgment rendered by this court in the case of
ARETPL-AT(JV) Vs. M/s. Central Coalfields Limited. & Ors., reported in 2018(3) JLJR 208, wherein several judgments of the Hon’ble
Supreme Court on the issue of entertaining a writ petition in contractual matter have been incorporated as under:-
“20. In the case of “Verigamto Naveen Vs. Govt. of A.P. and othersâ€, reported in (2001) 8 SCC 344, the Hon’ble Supreme Court
held as under:-
On the question that the relief as sought for and granted by the High Court arises purely in the contractual field and, therefore, the
High Court ought not to have exercised its power under Article 226 of the Constitution placed very heavy reliance on the decision of the
Andhra Pradesh High Court in Y.S. Raja Reddy v. A.P. Mining Corpn. Ltd. and the decisions of this Court in Har Shankar v. Dy. Excise &
Taxation Commr., Radha Krishna Agarwal v. State of Bihar, Ramlal & Sons v. State of Rajasthan, Shiv Shankar Dal Mills v. State of
Haryana, Ramana Dayaram Shetty v. International Airport Authority of India and Basheshar Nath v. CIT. Though there is one set of cases
rendered by this Court of the type arising in Radha Krishna Agarwal case much water has flown in the stream of judicial review in
contractual field. In cases where the decision-making authority exceeded its statutory power or committed breach of rules or principles of
natural justice in exercise of such power or its decision is perverse or passed an irrational order, this Court has interceded even after the
contract was entered into between the parties and the Government and its agencies. We may advert to three decisions of this Court in
Dwarka Das Marfatia & Sons v. Board of Trustees of the Port of Bombay, Mahabir Auto Stores v. Indian Oil Corpn. And Shrilekha
Vidyarthi (Kumari) v. State of U.P. Where the breach of contract involves breach of statutory obligation when the order complained of was
made in exercise of statutory power by a statutory authority, though cause of action arises out of or pertains to contract, brings it within the
sphere of public law because the power exercised is apart from contract. The freedom of the Government to enter into business with
anybody it likes is subject to the condition of reasonableness and fair play as well as public interest. After entering into a contract, in
cancelling the contract which is subject to terms of the statutory provisions, as in the present case, it cannot be said that the matter falls
purely in a contractual field. Therefore, we do not think it would be appropriate to suggest that the case on hand is a matter arising purely
out of a contract and, therefore, interference under Article 226 of the Constitution is not called for. This contention also stands rejected.
In the case of “Noble Resources Ltd. Vs. State of Orissaâ€, reported in (2006) 10 SCC 236, the Hon’ble Supreme Court held as
under:-
It may, however, be true that where serious disputed questions of fact are raised requiring appreciation of evidence, and, thus, for
determination thereof, examination of witnesses would be necessary; it may not be convenient to decide the dispute in a proceeding under
Article 226 of the Constitution of India.
On a conspectus of several decisions, a Division Bench of this Court in ABL International Ltd. opined that such a writ petition would be
maintainable even if it involves some disputed questions of fact. It was stated that no decision lays down an absolute rule that in all cases
involving disputed questions of fact, the party should be relegated to a civil court.
In Mahabir Auto Stores v. Indian Oil Corpn. this Court observed: (SCC p. 761, para 12)
“It appears to us that rule of reason and rule against arbitrariness and discrimination, rules of fair play and natural justice are part of
the rule of law applicable in situation or action by State instrumentality in dealing with citizens in a situation like the present one. Even
though the rights of the citizens are in the nature of contractual rights, the manner, the method and motive of a decision of entering or not
entering into a contract, are subject to judicial review on the touchstone of relevance and reasonableness, fair play, natural justice,
equality and non-discrimination in the type of the transactions and nature of the dealing as in the present case.â€
In State of U.P. v. Vijay Bahadur Singh a Division Bench of this Court held that the Government cannot be denied to exercise its
discretionary power provided the same is not arbitrary.
Interplay between writ jurisdiction and contractual disputes has given rise to a plethora of decisions by this Court. See, for example,
Dwarkadas Marfatia & Sons v. Board of Trustees, Port of Bombay and Mahabir Auto Stores.
In Jamshed Hormusji Wadia v. Board of Trustees, Port of Mumbai this Court stated: (SCC p. 235, paras 16-17)
“16. The position of law is settled that the State and its authorities including instrumentalities of States have to be just, fair and
reasonable in all their activities including those in the field of contracts. Even while playing the role of a landlord or a tenant, the State and
its authorities remain so and cannot be heard or seen causing displeasure or discomfort to Article 14 of the Constitution of India.
It is common knowledge that several rent control legislations exist spread around the country, the emergence whereof was witnessed by
the post-World War scarcity of accommodation. Often these legislations exempt from their applicability the properties owned by the
Government, semi-government or public bodies, government-owned corporations, trusts and other instrumentalities of State.â€
Non-statutory contracts have, however, been treated differently. (See Bareilly Development Authority v. Ajai Pal Singh.)
A distinction is also made between performance of a statutory duty and/or dealing of a public matter by a State and its commercial
activities. (See Indian Oil Corpn. Ltd. v. Amritsar Gas Service and LIC of India v. Escorts Ltd.)
In ABL International Ltd. this Court opined that on a given set of facts, if a State acts in an arbitrary manner even in a matter of
contract, a writ petition would be maintainable. It was opined: (SCC p. 570, para 23)
“23. It is clear from the above observations of this Court, once the State or an instrumentality of the State is a party to the contract, it has
an obligation in law to act fairly, justly and reasonably which is the requirement of Article 14 of the Constitution of India. Therefore, if by
the impugned repudiation of the claim of the appellants the first respondent as an instrumentality of the State has acted in contravention of
the abovesaid requirement of Article 14, then we have no hesitation in holding that a writ court can issue suitable directions to set right the
arbitrary actions of the first respondent.â€
Contractual matters are, thus, not beyond the realm of judicial review. Its application may, however, be limited
In the case of “Joshi Technologies International Inc. Vs. Union of India and othersâ€, reported in (2015) 7 SCC 728, it is held as
under:-
The position thus summarised in the aforesaid principles has to be understood in the context of discussion that preceded which we have
pointed out above. As per this, no doubt, there is no absolute bar to the maintainability of the writ petition even in contractual matters or
where there are disputed questions of fact or even when monetary claim is raised. At the same time, discretion lies with the High Court which
under certain circumstances, it can refuse to exercise. It also follows that under the following circumstances, “normallyâ€, the Court
would not exercise such a discretion:
69.1. The Court may not examine the issue unless the action has some public law character attached to it.
69.2. Whenever a particular mode of settlement of dispute is provided in the contract, the High Court would refuse to exercise its discretion
under Article 226 of the Constitution and relegate the party to the said mode of settlement, particularly when settlement of disputes is to be
resorted to through the means of arbitration.
69.3. If there are very serious disputed questions of fact which are of complex nature and require oral evidence for their determination.
69.4. Money claims per se particularly arising out of contractual obligations are normally not to be entertained except in exceptional
circumstances.
Further, the legal position which emerges from various judgments of this Court dealing with different situations/aspects relating to
contracts entered into by the State/public authority with private parties, can be summarised as under:
70.1. At the stage of entering into a contract, the State acts purely in its executive capacity and is bound by the obligations of fairness.
70.2. State in its executive capacity, even in the contractual field, is under obligation to act fairly and cannot practise some discrimination.
70.3. Even in cases where question is of choice or consideration of competing claims before entering into the field of contract, facts have to
be investigated and found before the question of a violation of Article 14 of the Constitution could arise. If those facts are disputed and
require assessment of evidence the correctness of which can only be tested satisfactorily by taking detailed evidence, involving examination
and cross-examination of witnesses, the case could not be conveniently or satisfactorily decided in proceedings under Article 226 of the
Constitution. In such cases the Court can direct the aggrieved party to resort to alternate remedy of civil suit, etc.
70.4. Writ jurisdiction of the High Court under Article 226 of the Constitution was not intended to facilitate avoidance of obligation
voluntarily incurred.
70.5. Writ petition was not maintainable to avoid contractual obligation. Occurrence of commercial difficulty, inconvenience or hardship in
performance of the conditions agreed to in the contract can provide no justification in not complying with the terms of contract which the
parties had accepted with open eyes. It cannot ever be that a licensee can work out the licence if he finds it profitable to do so: and he can
challenge the conditions under which he agreed to take the licence, if he finds it commercially inexpedient to conduct his business.
70.6. Ordinarily, where a breach of contract is complained of, the party complaining of such breach may sue for specific performance of
the contract, if contract is capable of being specifically performed. Otherwise, the party may sue for damages.
70.7. Writ can be issued where there is executive action unsupported by law or even in respect of a corporation there is denial of equality
before law or equal protection of law or if it can be shown that action of the public authorities was without giving any hearing and
violation of principles of natural justice after holding that action could not have been taken without observing principles of natural justice.
70.8. If the contract between private party and the State/instrumentality and/or agency of the State is under the realm of a private law and
there is no element of public law, the normal course for the aggrieved party, is to invoke the remedies provided under ordinary civil law
rather than approaching the High Court under Article 226 of the Constitution of India and invoking its extraordinary jurisdiction.
70.9. The distinction between public law and private law element in the contract with the State is getting blurred. However, it has not been
totally obliterated and where the matter falls purely in private field of contract, this Court has maintained the position that writ petition is
not maintainable. The dichotomy between public law and private law rights and remedies would depend on the factual matrix of each case
and the distinction between the public law remedies and private law field, cannot be demarcated with precision. In fact, each case has to be
examined, on its facts whether the contractual relations between the parties bear insignia of public element. Once on the facts of a
particular case it is found that nature of the activity or controversy involves public law element, then the matter can be examined by the
High Court in writ petitions under Article 226 of the Constitution of India to see whether action of the State and/or instrumentality or
agency of the State is fair, just and equitable or that relevant factors are taken into consideration and irrelevant factors have not gone into
the decision-making process or that the decision is not arbitrary.
70.10. Mere reasonable or legitimate expectation of a citizen, in such a situation, may not by itself be a distinct enforceable right, but
failure to consider and give due weight to it may render the decision arbitrary, and this is how the requirements of due consideration of a
legitimate expectation forms part of the principle of non-arbitrariness.
70.11. The scope of judicial review in respect of disputes falling within the domain of contractual obligations may be more limited and in
doubtful cases the parties may be relegated to adjudication of their rights by resort to remedies provided for adjudication of purely
contractual disputes.
Keeping in mind the aforesaid principles and after considering the arguments of the respective parties, we are of the view that on the
facts of the present case, it is not a fit case where the High Court should have exercised discretionary jurisdiction under Article 226 of the
Constitution. First, the matter is in the realm of pure contract. It is not a case where any statutory contract is awarded.
Having gone through the aforesaid judgments of the Hon’ble Supreme Court, it may be construed that there is no absolute bar in
entertaining a writ petition in a contractual matter where some disputed question of facts are involved. However, if the dispute involved in a
matter is so complex which can only be determined after thorough long drawn adjudicatory process by leading evidences, the writ petition
should not be entertained. Each and every case is to be dealt with on its own facts. If the materials on record are clearly evincible, the writ
court may exercise the power of judicial review.
The power under Article 226 of the Constitution of India is plenary in nature and is not subjected to any of the other provisions of the
Constitution. The High Court has discretion to exercise or not to exercise such discretion having regard to the facts of each case. However,
the High Courts have imposed self-restraints in such exercise of extraordinary jurisdiction of the High Court to issue a prerogative writ will
not normally be exercised by the Court to the exclusion of other available remedies unless such action of the State or its instrumentality is
arbitrary and unreasonable so as to violate the constitutional mandate of Article 14 or for other valid and legitimate reasons, for which the
Court thinks it necessary to exercise the said jurisdiction.â€
Undoubtedly, the High Court while making the judicial review is not expected to act as a court of appeal in examining the administrative decision
and to find out as to whether any different decision could have been taken by the State authorities in the facts and circumstances of the case. It is also
trite that the writ court should ordinarily refrain from examining the details of the terms and conditions of the contract, which are entered by the
State/its functionaries. The writ court has inherent limitation on the scope of any detailed enquiry in contractual matters. However, the writ court can
certainly examine whether the decision making process by the State authorities is unreasonable, irrational, arbitrary and violative of Article 14 of the
Constitution of India. Once the procedure adopted by any authority of the State in the matter of public contract is held to be against the mandate of
Article 14 of the Constitution of India, the writ Court cannot ignore such action of the State authorities on the pretext that there should be some
latitude or liberty in contractual matters and any interference by the writ court would amount to encroachment over the exclusive right of the State
authorities to take such decision.
In the case of Jagish Mandal (Supra.), as has been relied upon by the learned Advocate General, the Hon’ble Supreme Court after referring to
various earlier judgments, has held as under:
“22. Judicial review of administrative action is intended to prevent arbitrariness, irrationality, unreasonableness, bias and mala fides. Its
purpose is to check whether choice or decision is made “lawfully†and not to check whether choice or decision is “soundâ€. When
the power of judicial review is invoked in matters relating to tenders or award of contracts, certain special features should be borne in
mind. A contract is a commercial transaction. Evaluating tenders and awarding contracts are essentially commercial functions. Principles of
equity and natural justice stay at a distance. If the decision relating to award of contract is bona fide and is in public interest, courts will
not, in exercise of power of judicial review, interfere even if a procedural aberration or error in assessment or prejudice to a tenderer, is
made out. The power of judicial review will not be permitted to be invoked to protect private interest at the cost of public interest, or to
decide contractual disputes. The tenderer or contractor with a grievance can always seek damages in a civil court. Attempts by unsuccessful
tenderers with imaginary grievances, wounded pride and business rivalry, to make mountains out of molehills of some technical/procedural
violation or some prejudice to self, and persuade courts to interfere by exercising power of judicial review, should be resisted. Such
interferences, either interim or final, may hold up public works for years, or delay relief and succour to thousands and millions and may
increase the project cost manifold. Therefore, a court before interfering in tender or contractual matters in exercise of power of judicial
review, should pose to itself the following questions:
(i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone;
or
Whether the process adopted or decision made is so arbitrary and irrational that the court can say: “the decision is such that no
responsible authority acting reasonably and in accordance with relevant law could have reachedâ€;
(ii) Whether public interest is affected.
If the answers are in the negative, there should be no interference under Article 226. Cases involving blacklisting or imposition of penal
consequences on a tenderer/contractor or distribution of State largesse (allotment of sites/shops, grant of licences, dealerships and
franchises) stand on a different footing as they may require a higher degree of fairness in action.â€
Further in the case of Monte Carlo Ltd. Vs. National Thermal Power Corporation Ltd., reported in (2016)15 SCC 27, 2the Hon’ble Supreme
Court has held as under:
“19. In Sterling Computers Ltd. v. M&N Publications Ltd., (1993) 1 SCC 445, the Court has held that under some special circumstances
a discretion has to be conceded to the authorities who have to enter into contract giving them liberty to assess the overall situation for
purpose of taking a decision as to whom the contract be awarded and at what terms. It has also been observed that by way of judicial
review the Court cannot examine the details of the terms of the contract which have been entered into by the public bodies or the State.
Courts have inherent limitations on the scope of any such enquiry.
In Tata Cellular v. Union of India, (1994) 6 SCC 651 a three-Judge Bench after referring to earlier decisions culled out certain
principles, namely, (a) the modern trend points to judicial restraint in administrative action, (b) the Court does not sit as a court of appeal
but merely reviews the manner in which the decision was made, (c) the Court does not have the expertise to correct the administrative
decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expertise which
itself may be fallible, and (d) the Government must have freedom of contract and that permits a fair play in the joints as a necessary
concomitant for an administrative body functioning in an administrative sphere or quasi-administrative sphere. Hence, the Court has laid
down that the decision must not only be tested by the application of the Wednesbury principle [Associated Provincial Picture Houses Ltd. v.
Wednesbury Corpn., (1948) 1 KB 223 (CA)] of reasonableness (including its other facts pointed out above) but must be free from
arbitrariness not affected by bias or actuated by mala fides.â€
Both the parties have heavily relied upon the judgment of the Hon’ble Supreme Court rendered in the case of Central Coalfields Limited &
Anr. Vs. SLL-SML (Joint Venture Consortium) & Ors., reported in (2016)8 SCC 62.2 In the said case, the technical bid of one of the bidders,
namely, SLL-SML was rejected on the ground that the bank guarantee submitted by it was not in the format prescribed in the NIT read with GTC.
The said rejection was challenged by the said bidder before this Court by way of filing a writ petition, contending, inter alia, that the said condition was
not mandatory to be complied and as such its bid could have been accepted. The learned Single Judge, however, dismissed the said writ petition.
Aggrieved thereby, the bidder preferred letters patent appeal before the learned Division Bench of this Court, which allowed the same by reversing
the judgment of the learned Single Judge and held that the submission of the bank guarantee in the prescribed format was a non-essential term of NIT
and since the bidder had substantially complied the requirement of the bank guarantee being in the format prescribed by the Central Coalfields Limited,
the rejection of the bid was unjustified. The said matter travelled up to the Hon’ble Supreme Court and the Hon’ble Supreme Court examined
the decision taken by the Central Coalfields Limited so as to find out as to whether it acted perversely while rejecting the bid so as to warrant any
judicial interference. It was noticed by the Hon’ble Supreme Court that the Central Coalfields Limited had not relaxed or deviated from the
requirement of furnishing a bank guarantee in the prescribed format and, thus, every bidder was required to adhere to the prescribed format of the
bank guarantee and thus did not find any arbitrariness, unreasonableness or perversity in the decision of the Central Coalfields Limited so as to make
any interference with the same.
The relevant paragraphs of the judgment of the Hon’ble Supreme rendered in the case of SLL-SML (Joint Venture Consortium) (Supra.) are
quoted herein below:-
“32. The core issue in these appeals is not of judicial review of the administrative action of CCL in adhering to the terms of NIT and the
GTC prescribed by it while dealing with bids furnished by participants in the bidding process. The core issue is whether CCL acted
perversely enough in rejecting the bank guarantee of JVC on the ground that it was not in the prescribed format, thereby calling for
judicial review by a constitutional court and interfering with CCL's decision.
For JVC to say that its bank guarantee was in terms stricter than the prescribed format is neither here nor there. It is not for the
employer or this Court to scrutinise every bank guarantee to determine whether it is stricter than the prescribed format or less rigorous. The
fact is that a format was prescribed and there was no reason not to adhere to it. The goalposts cannot be rearranged or asked to be
rearranged during the bidding process to affect the right of some or deny a privilege to some.
The result of this discussion is that the issue of the acceptance or rejection of a bid or a bidder should be looked at not only from the
point of view of the unsuccessful party but also from the point of view of the employer. As held in Ramana Dayaram Shetty v. International
Airport Authority of India, (1979) 3 SCC 489 the terms of NIT cannot be ignored as being redundant or superfluous. They must be given a
meaning and the necessary significance. As pointed out in Tata Cellular [Tata Cellular v. Union of India, (1994) 6 SCC 651] there must be
judicial restraint in interfering with administrative action. Ordinarily, the soundness of the decision taken by the employer ought not to be
questioned but the decision-making process can certainly be subject to judicial review. The soundness of the decision may be questioned if
it is irrational or mala fide or intended to favour someone or a decision “that no responsible authority acting reasonably and in
accordance with relevant law could have reached†as held in Jagdish Mandal v. State of Orissa, (2007) 14 SCC 517 followed in Michigan
Rubber (India) Ltd. v. State of Karnataka, (2012) 8 SCC 216].â€
It is, thus, clear that a term of NIT is essential or otherwise is a decision to be taken by the employer and even if any term of the NIT is found to
be essential, the same can be deviated by the employer provided that such deviation is made applicable to all bidders and potential bidders. The
goalposts cannot be rearranged during the bidding process to affect the right of some or deny a privilege to other. The power of judicial review is to be
exercised to look into the lawfulness of the decision and not the soundness of the same. The judicial review is intended to prevent arbitrariness,
irrationality, unreasonableness, mala fide or bias. In case of SLL-SML (Joint Venture) (Supra.), the Hon’ble supreme Court confined itself to find
out as to whether the action of the Central Coalfields Limited was perverse while rejecting the bank guarantee of the bidder on the ground that it was
not in the prescribed format.
The issue before this Court in the present case is as to whether there is any arbitrariness, unreasonableness, mala fide, biasness in the decision
making processing of the State respondents so as to make any interference with the present tender(s). If so, what appropriate order can be passed in
the facts and circumstances of the present case.
The State respondents initially while filing counter affidavit took stand that there was infirmity in the bid document of the P-1, whereas the bids of
the private respondents were strictly in accordance with the terms and conditions prescribed in the SBD. However, the P-1 filed rejoinder affidavit to
controvert the said averment made by the State respondents in their counter affidavit and stated that there were infirmities in the bid documents of the
private respondents as well as other bidders, whose technical bids were held responsive. In support of the said contention, the P-1 has annexed the
relevant part of the bid document of other bidders. The argument advanced by the learned counsel for the P-1 on the said issue has not specifically
been controverted by the learned Advocate General while making his argument, however, has taken a stand that some of the mistakes committed by
the bidders while submitting their respective bank guarantees were waived by the Tender Evaluation Committee and were made effective for all
bidders, including the P-1. Apart from the common mistakes, the petitioner had committed other major mistakes, which could not have been waived
and, thus, the Tender Evaluation Committee held the technical bid of the petitioner to be non-responsive. In support of the said argument advanced by
the learned Advocate General, no such minutes of Tender Evaluation Committee has been brought on record so as to satisfy this court that the
common mistakes were waived, but major/fatal mistakes found in the bank guarantee presented by the P-1 could not have been waived and, thus, its
technical bid was declared non-responsive.
In the case of P-1, its technical bid in the work W-3 was held to be responsive despite the fact that the amended bank guarantee was furnished by
it. Its financial bid was also opened, which was found to be the lowest. However, the State respondents for the other works W-1 and W-2 held the
technical bid of the P-1 as non-responsive to Clause 16.3 of the SBD merely on the ground that the P-1 had filed amended bank guarantee, which was
violative of one of the tender conditions. The contention made on behalf of the P-1 is that the SBD of all the works in question is almost the same and
the said contention has not been denied by the respondents. Thus, the State respondents appear to have taken different approach in similar works
particularly in relation to the same defect. When the P-1 challenged the rejection of its technical bid for the work W-1 and the court took note of such
fact vide order dated 24th October, 2019, the State respondents hurriedly cancelled the tender relating to the work W-3 and issued third call tender. In
the above context, the contention of the learned counsel for the P-1 is that the decision of the respondent authorities suffers from arbitrariness and
unreasonableness has some substance.
In the case of SLL-SML (Joint Venture) (Supra.), the Hon’ble Supreme Court has held that the discretion is with the authorities to decide as
to whether a term of NIT is essential condition or not and also to deviate from such term provided that the said decision is made applicable to all the
bidders and potential bidders. Thus, the conduct of State authorities is one of the relevant factors to gather their intention as to whether they have
treated filing of the bank guarantee in the prescribed format as a mandatory condition and have applied the said decision against all the bidders
uniformly. So far as the works W-1 and W-2 are concerned, it appears from the record that almost all the bidders have deviated from the prescribed
format of the bank guarantee and had thus violated one or the other condition of the SBD. If the State respondents had any intention to strictly follow
the format of the bank guarantee, there was no reason as to why they would have deviated from it by relaxing some of the defects in the bank
guarantee of other bidders including the private respondent irrespective of the fact whether those were condonable or otherwise. It is well settled law
that even if an action is in the realm of contract, the writ Court is empowered to make judicial review of the action of the State authorities and to
determine as to whether there has been any illegality, perversity, unreasonableness, unfairness or irrationality thereby vitiating the said action.
In the case of Poddar Steel Corporation Vs. Ganesh Engineering works & Ors., reported in (1991)3 SCC 27,3 followed in the case of Rashmi
Metaliks Limited & Anr. Vs. Kolkata Metropolitan Development Authority & Ors., reported in (2013)10 SCC 9,5 a distinction has been drawn by the
Hon’ble Supreme Court between essential, ancillary and subsidiary condition of a bid document and has held that the essential term of a tender
document cannot be deviated from, however, an ancillary or subsidiary or non-essential term can be deviated which could be without any reference to
the potential bidders. Further, in the case of SLL-SML (Joint Venture) (Supra.), the Hon’ble Supreme Court has held that whether a term of the
NIT is essential or not is a decision to be taken by the employer. If the essential terms is to be deviated, the same is to be made applicable to all the
bidders. In the said case, the Hon’ble Supreme Court has put reliance on the principle laid down by the privy council in the case of Nazir Ahmad
Vs. King Emperor, reported in 1936 SCC Online PC 41, and has held that if the employer prescribes a particular format of the bank guarantee to be
furnished, the bidders are required to submit bank guarantee in that format only. However, any flexibility in this regard is to be applied to all the
bidders. The Hon’ble Supreme Court has put emphasis on the principle that the decision of the authority should be applied to all similarly situated
bidders uniformly. If the authority treats the format prescribed in the bank guarantee as an essential term, the same cannot be relaxed by adopting a
pick and choose method on the pretext of making it condonable or otherwise, which certainly makes the said decision to be arbitrary and unreasonable
requiring interference of the writ court under its power of judicial review.
Since the main argument of learned Advocate General in support of rejection of the bid of the P-1 in all three works is that the bid security of the
P-1 was not in accordance with the prescribed format provided in the SBD, whereas the bid of the successful bidders was strictly in accordance with
the conditions prescribed in the SBD, it would be relevant to go through the format of the bank guarantee security, which is quoted as under for the
purpose of reference:
“Bid Security (Bank Guarantee)
Whereas, ------ (name of Bidder) (hereinafter called “the Bidderâ€) has submitted his Bid dated ---- (date) for the construction of ----
(name of Contract hereinafter called “the Bidâ€)
Know all people by these presents that We ---- (name of
Bank) ----- (name of country) having our registered office at ----(hereinafter called “the Bankâ€) are bound unto ----- (name of
Employer) (hereinafter called “the Employer) in the sum of ----- for which payment well and truly to be made to the said Employer the
Bank itself, his successors and assigns by these presents.
Sealed with the Common Seal of the said Bank this --- day of --,20---.
The Conditions of this obligation are:
(1) If after Bid opening the Bidder withdraws his bid during the period of Bid validity specified in the Form of Bid;
(2) If the Bidder having been notified to the acceptance of his bid by the Employer during the period of Bid validity:
(a) fails or refuses to execute the Form of Agreement in accordance with the Instructions of Bidders, if required; or
(b) fails or refuses to furnish the Performance Security, in accordance with the Instructions to Bidders; or
(c) does not accept the correction of the Bid Price pursuant to Clause 27.
We undertake to pay to the Employer up to the above amount upon receipt of his fist written demand, without the Employer having to
substantiate his damned, provided that in his demand the Employer will note that the amount claimed by him is due to him owing to the
occurrence of one or nay of three conditions, specifying the occurred condition or conditions.
This Guarantee will remain in force up to and including the date ----- ** days after deadline for submission of Bids as such deadline is
stated in the Instructions of Bidders or as it may be extended by the Employer, notice of which extension(s) to the Bank is hereby waived.
Any demand in respect of this guarantee should reach the Bank not later than the above date.
Date ------
Signature ----------
Witness ----
Seal -------
Signature, name and address
* The Bidder should insert the amount of the guarantee in words and figures denominated in Indian Rupees. This figure should be the same
as shown in Clause 16.1 of the Instructions to Bidders.
** 45 days after the end of the validity period of the Bid. Date should be inserted by the Employer before the Bidding documents are
issued.â€
So far as the work W-1 is concerned, it appears that M/s. Agrawal Global Infratech Pvt. Ltd. (respondent no.5 in W.P.(C) No.5408/2019)
presented the bank guarantee in the name of the Executive Engineer, Road Division, Garhwa, whereas other bidders submitted the bank guarantee in
the name of the Executive Engineer, Road Division, Garhwa. The State respondents have contended that it was provided by an addendum that the
bank guarantee is required to be issued in the name of the Executive Engineer, Road Construction Department, Road Division, Garhwa. Even if the
said contention of the State respondents is accepted, they have deviated from the terms of SBD by accepting the technical bid of other bidders, who
had presented the bank guarantee in the name of the Executive Engineer, Road Construction Department, Road Division, Garhwa. Apart from it, the
respondent no.5 had put a “notwithstanding clause†in the bank guarantee, which was certainly a deviation from the format of the bank guarantee.
M/s. N.G. Projects Limited [respondent no.5 in W.P.(C) No.5416/2019], whose technical bid was also found responsive, also deviated from the
format of the bank guarantee by changing the condition of the bank guarantee by providing that the bank guarantee can be extended only at the
“banker’s sole discretionâ€. It further appears that in the bank guarantee of M.G. Contractors Private Limited and RKC Infrabuilt Private
Limited, whose technical bids were also found responsive, there were deviations from the prescribed format, which were relaxed by the State
respondents.
The learned Advocate General as well as learned counsel for the private respondent, while justifying the impugned orders, further highlighted some
other infirmities in the tender document of the P-1, which has been replied by the learned counsel for the P-1 and by referring to the rejoinder
affidavit, has submitted that the bid documents of other tenderers also suffer from similar infirmities, which have been ignored by the State
respondents and as such they should not have rejected the bid of the P-1. In fact, the State respondents have given different treatment to the different
bidders in the tender process, which is not permissible in the eye of law.
So far as the work W-2 is concerned, it appears from the bank guarantee submitted by the M/s. N. G. Projects Limited that it deviated from the
format of the bank guarantee by changing the condition of the bank guarantee mentioning “banker’s sole discretion†and the said deviation
has been ignored by the State respondents.
The Hon’ble Supreme Court in the case of Ramana Dayaram Shetty Vs. International Airport Authority of India & Ors., reported in (1979)3
SCC 489, has held as under:
“21. ------ It must, therefore follow as a necessary corollary from the principle of equality enshrined in Article 14 that though the State is
entitled to refuse to enter into relationship with any one, yet if it does so, it cannot arbitrarily choose any person it likes for entering into
such relationship and discriminate between persons similarly circumstanced, but it must act in conformity with some standard or principle
which meets the test of reasonableness and non-discrimination and any departure from such standard or principle would be invalid unless it
can be supported or justified on some rational and non-discriminatory ground.â€
So far as the work W-3 is concerned, the State respondents have cancelled the second call tender after accepting the technical and financial bid of
the P-1 and declaring it the lowest tenderer to somehow justify their action taken for the works W-1 and W-2, which certainly suffers from mala fide
and arbitrariness.
I am of the considered view that the decision making process of the State respondents, while rejecting the technical bid of P-1 and by accepting
the technical bids of the private respondents as well as other bidders, suffers from arbitrariness and unreasonableness more so when there were
infirmities in the bid documents of all the bidders. The State respondents appear to have adopted pick and choose method, which is not permissible in
the eye of law so as to satisfy the requirement of Article 14 of the Constitution of India.
The learned Advocate General has also argued that the prayer made in the writ petitions being W.P.(C) No.5408 of 2019 and W.P.(C) No.5416
of 2019 is only confined to opening of the technical bid of the P-1 and since the works have already been awarded to the private respondents, no other
relief can be granted to the petitioners and the writ petitions are liable to be dismissed.
To appreciate the said argument, the law laid down by the Hon’ble Supreme Court in this regard is required to be discussed. In the case of
Satya Narain Singh Vs. District Engineer, PWD & Ors., reported in 1962 Supp.(3) SCR 10, 5a Constitution Bench of the Hon’ble Supreme Court
has held as under:
“10. In the result we allow the appeal and set aside the judgment of the Division Bench as well as of the Single Judge of the High Court
of Allahabad and direct that a writ in the nature of mandamus shall issue to the respondents directing them to pay to the appellant full tolls
with respect to every crossing of the Roadways buses over the ferry between 16-3-1954 and the date on which the licence in favour of the
appellant expired.â€
In the case of B.C. Chaturvedi Vs. Union of India & Ors., reported in (1995)6 SCC 74,9 the Hon’ble Supreme Court of India has held that
merely because there is no parallel provision of Article 142 of the Constitution of India available to the High Courts, it cannot be a ground to think that
they cannot do complete justice and if moulding of relief would do complete justice between the parties, the same cannot be ordered.
In the case of Shangrila Food Products Ltd. & Anr. Vs. Life Insurance Corporation of India & Anr., reported in (1996)5 SCC 5,4 the Hon’ble
Supreme Court has held that the High Court in exercise of its jurisdiction under Article 226 of the Constitution of India can take cognizance of the
entire facts and circumstances of the case and pass appropriate orders to give complete and substantial justice to the parties.
Thus, in view of the aforesaid ratio laid down by the Hon’ble Supreme Court in this regard, I do not find any substance in the said argument of
the learned Advocate General. The power of the High Court under Article 226 of the Constitution of India being discretionary in nature, the writ Court
cannot be confined to the prayer made in the writ petition, if the situation so warrants. For rendering complete justice, the High Court may pass
appropriate order as it may deem fit in the facts and circumstances of the case. Moreover, the petitioners in their respective writ petitions have made
prayer for “any other reliefâ€, which would certainly have an exhaustive meaning.
So far as the merit of the case of the P-2 [petitioner of W.P.(C) No.5689 of 2019] is concerned, I have gone through the relevant provisions of the
Addendum/Amendments to the Instruction to Bidders (ITB) to SBD and the same are quoted hereunder:
“2.6.7 The audited balance sheets for the last five years should be submitted, which demonstrates the soundness of the Applicant’s
financial position, showing long-term profitability including an estimated financial projection for the next two years. If necessary, the
Employer will make inquiries with the applicant’s bankers.
2.6.8 Litigation History
The Applicant should provide accurate information on any litigation or arbitration resulting from contracts completed or under execution
by him over the last five years. A consistent history of awards against the Applicant or any partner of a joint venture any result in failure of
the applicant.
2.7.1 Joint Venture must comply with the following requirements;
(a) Following are the minimum qualification requirements; ----
(ii) The joint venture must satisfy collectively the criteria of para 2.6.4 and 2.6.5 above for which purpose the relevant figures for each of
the partners shall be added together to arrive to arrive at the joint venture’s total capacity. Individual members must each satisfy the
requirements of para 2.6.7 & 2.6.8 above, ------------“
It would, thus, be evident that in view of Clause 2.7.1 of the Addendum/Amendments to the Instruction to Bidders (ITB) to SBD, if the bidder is a
joint venture, the individual members are to satisfy the requirement of Clause 2.6.7 and 2.6.8. So far as the case of P-2 is concerned, Clause 2.6.8
would be relevant which specifically provides that the applicant has to satisfy the litigation history of last five years. Though the contention of the State
respondents is that P-2 submitted the litigation history of joint venture instead of individual litigation history of both the members of the joint venture,
the said contention has been controverted by the learned counsel for the P-2 and by inviting the notice of this Court to Annexure-A to the counter
affidavit, has contended that the litigation history submitted by the P-2 has wrongly been interpreted by the State respondents.
To appreciate the contention of the learned counsel for the parties, I have perused the litigation history submitted by the P-2 from which it appears
that though the litigation history was submitted in the letterhead of the joint venture, namely, Ramiya-HS (JV), it was specifically stated therein “No
Litigation History of Either J.V. Memberâ€. Thus, I do find substance in the argument of learned counsel for the P-2 that the State respondents
arbitrarily rejected the technical bid of the P-2. I am of the considered view that since the litigation history was required to be filed by the
“Applicant†and here the applicant was the joint venture, namely, Ramiya-HS (JV), the said litigation history was furnished in the letterhead of the
Ramiya-HS(JV), disclosing the litigation history of both the partners.
Now, the question before this Court is as to what nature of order can be passed in the present facts and circumstances of the case.
In the case of TRF Limited Vs. Energo Engg. Projects Ltd., reported in (2017)8 SCC 37, 7the Hon’ble Supreme Court has held that once the
infrastructure collapses, the superstructure is bound to collapse. One cannot have a building without the plinth. Or to put it differently, once the identity
of the Managing Director as the sole arbitrator is lost, the power to nominate someone else as an arbitrator is obliterated. Therefore, the view
expressed by the High Court is not sustainable and we say so.
Further in the case of Chairman-cum-Managing Director, Coal India Limited & Ors. Vs. Ananta Saha & Ors., reported in (2011)5 SCC 14, 2the
Hon’ble Supreme Court has held as under:
“32. It is a settled legal proposition that if initial action is not in consonance with law, subsequent proceedings would not sanctify the
same. In such a fact situation, the legal maxim sublato fundamento cadit opus is applicable, meaning thereby, in case a foundation is
removed, the superstructure falls.â€
Since it has already been discussed hereinabove that the decision making process adopted by the State respondents suffers from several infirmities
and by applying the principle laid down by the Hon’ble Supreme Court in the aforesaid cases, I am of the considered view that it would not be
appropriate to allow the State as well as private respondents to continue with the allotted work, namely, W-1 and W-2 and the same are liable to be
quashed and set aside. Moreover, it appears from the counter affidavit of the private respondents that they have already started the work and the part
work has already been completed and, therefore, it is not feasible to direct the State respondents to proceed with the same tender by opening the
financial bids of the petitioners.
Since non-adherence of the prescribed format of the bank guarantee, the technical bids of five tenderers for the work W-1 and three tenderers for
the work W-2 have been rejected, in view of the principle of privilege of participation laid down by the Hon’ble Supreme Court in the case of
Ramana Dayaram Shetty (Supra.), they have also been discriminated as against the private respondents on the issue of deviation from the prescribed
format of bank guarantee.
Under the aforesaid facts and circumstances, all the writ petitions are disposed of by passing following orders:-
(i) The decision of the Tender Committee dated 3rd October, 2019 for the work, namely, “Reconstruction of Meral-Bana-Ambakhoriya Road
(MDR-140)†in relation to W.P.(C) No.5408 of 2019 and W.P.(C) No.5689 of 2019 is hereby quashed. All the consequential action of the State
respondents taken in relation to the said tender including the award of the tender in favour of the private respondent- M/s. Agrawal Global Infratech
Private Limited is also quashed. The State respondents are directed to issue fresh tender for the said work and to proceed accordingly.
(ii) The decision of the Tender Committee dated 3rd October, 2019, for the work, namely, “Reconstruction of Nagaruntari-Dhurki-Ambakhoriya
Road (MDR-139)†in relation to W.P.(C) No.5416 of 2019 is hereby quashed. All the consequential action of the State respondents taken in relation
to the said tender including the award of the tender in favour of the private respondent- M/s. N.G. Projects Limited is also quashed. The State
respondents are directed to issue fresh tender for the said work and to proceed accordingly.
(iii) The writ petition being W.P.(C) No.5894 of 2019 filed by the petitioner- M/s. Vinod Kumar Jain challenging the third call tender for the work,
namely, “Reconstruction of Dandai Bazar to Panghatwa P.W.D. Road via Lawahikala Road (total length 10.05 kms.)†is allowed and third call
tender issued by the State respondents is hereby quashed and set aside. The State respondents are directed to proceed further with the petitioner as
per the terms and conditions of the said tender.
