AI Structured Summary
Not yet generated for this judgment
Judgment
,
Prathiba M. Singh, J",
Present petition under Section 34 of the Arbitration and Conciliation Act, 1996 challenges the award dated 18th June, 2008 passed by the learned",
Sole Arbitrator.,
Brief background is that the Petitioner was awarded a work order No./Supply order No. F8(5) EE(W)C-VII/2000/1497 dated 7th August, 2000.",
Completion certificate was given to the Petitioner on 1st March, 2005. Disputes arose between the parties and a Sole Arbitrator was, accordingly,",
appointed on 16th December, 2005. Petitioner had challenged the appointment of Arbitrator before this Court. However, the Petitioner chose to",
withdraw the said challenge on 20th September, 2007 in OMP No.154/2006. The matter remained pending before the learned Arbitrator for some",
time.,
On 14th January, 2008, the Petitioner wrote a letter on the letterhead of the Petitioner firm, withdrawing his claims in the following terms.",
“ Dated:14.1.2009,
Shri Surinder Gandotra,",
Sole Arbitrator,",
115, Palika Bazar, Connaught Place,",
New Delhi-110001,
In the matter of arbitration between:,
V.K. Dewan & Co.,",
MD-67, Vishakha Enclave,",
Pitampura, Delhi-110088",
v/s,
Delhi Jal Board,",
(thru) Executive Engineer ....,
Jal Sadan, Shiv Mandir Marg,",
Lajpat Nagar, Phase-11",
New Delhi-1100,
In regard to: Construction of under ground reservoir and booster pumping station at SurajMal Vihar, Trans-Yamuna, Delhi",
(Contract agreement no.: 8 of 2000...),
In the aforesaid matter, without prejudice to his right",
to agitate elsewhere, the claimant contractor",
withdraws all his claims.,
Copy to:,
Delhi Jal Board,
(thru) Executive Engineer,
Jal Sadan, Shiv Mandir Marg",
Lajpat Nagar, Phase-11",
New Delhi-1100â€,
Since the Petitioner withdrew the claims before the Arbitrator, the Arbitrator awarded costs. Operative portion of the award, by which costs have",
been awarded in favour of the Respondent, reads as under:",
“ I Surinder Gandotra arbitrator make and publish this award and hereby direct that M/s. V. K. Dewan & Co should pay a sum of Rs.5,00,000/- to",
the Chief Executive Delhi Jal Board forthwith + Rs.3,00,000/-towards cost of litigation in the court of Arbitrator, and cost of litigation in Delhi High",
Court incurred by them + Rs.1,91,550/- as arbitration fee for both the parties M/s Delhi Jal Board and M/s. V. K. Dewan & Co under Section 31 &",
38 of Arbitration and Conciliation Act 1996. Now the total amount to be paid by M/s. Dewan & Co. come to Rs.9,91,550/-. Thus M/s. Dewan & Co.",
has to pay a sum of Rs.9,91,550/- (Rupees Nine Lacs Ninety One Thousand Five Hundred Fifty only) to Delhi Jal Board within a period of 1 month",
from the date of order and incase M/s. V. K. Dewan & Co. fails to pay this amount of Rs.9,91,550/- the Delhi Jal Board will be entitled to recover",
and interest of 15% on this amount from M/s. Dewan & Co. till its full realization of the amount Rs.9,91,550/- (Rupees Nine Lacs Nintey One",
Thousand Five Hundred Fifty only.) â€,
Arbitration Fee,"Rs. 60,000
Based on the claim of M/s.
Dewan & Co. including interest
right from the beginning of the
contract till the end of the
contract and interest on delayed
payments made by Delhi Ja
Board to the contractor.","Rs. 55,000
l
Administrative Fee,"Rs. 30,000
,"Rs. 30,000
TOTAL,"Rs. 1,75,000
Towards conveyance charges
@ Rs. 750/- per hearing and
total hearing in this case were
around 20","Rs. 16,550
Grand Total,"Rs. 1,91,550
